Maldon District Council
Council, Tuesday 23 February 2021 at 6.00pm

Bradwell B Programme Closedown and Local Development Plan Review

Noted Committee 2 papers

Council noted this item on Tuesday 23 February 2021. Below is the council's own wording, with the papers it was decided on.

Item282

Resolved

RESOLVED (i) that the impacts of the Bradwell B project closedown and funding withdrawal be noted; (ii) that Members agree there is an opportunity to bring forward the review of the Maldon District Local Development Plan, including utilising staff from the Bradwell Team where possible to accelerate delivery; (iii) that Members consider and approve the Maldon District Local Development Scheme 2021 - 2024 as set out in Appendix 1 to the report.
Word for word from the decision Maldon published for this meeting. Source: democracy.maldon.gov.uk

Follow this further

Built from Maldon's papers

What the report saysPro

Report to Council

Purpose of the report

1.1The purpose of this report is to consider the implications of the Bradwell B Programme closedown and the opportunity to bring forward the review of the Local Development Plan, utilising work that has already commenced as much as possible and redeploying the fixed term staffing resources from the Bradwell B project.

Recommendations

(i) that the impacts of the Bradwell B project closedown and funding withdrawal be noted;

(ii) that Members agree there is an opportunity to bring forward the review of the Maldon District Local Development Plan, including utilising staff from the Bradwell Team where possible to accelerate delivery;

(iii) that Members consider and approve the Maldon District Local Development Scheme 2021 - 2024 as set out in APPENDIX 1.

3. SUMMARY OF KEY ISSUES

3.1Impacts of Bradwell B Project Closedown and BRB Funding Withdrawal

3.1.1 On 29 January 2021, BRB wrote to the Council advising that due to the impacts of the Covid-19 pandemic, engagement with local authorities is to pause and the current funding agreement will be withdrawn for at least 12 months.

3.1.2 The funding had enabled the Council to put in place a multi-disciplinary project team to manage the additional burdens created by the Bradwell B project, including resourcing the engagement in the Development Consent Order process. This project is now in the process of being closed down but remains sensitive as it has implications for contractors and staff on fixed-term contracts.

3.1.3 BRB has made it clear that despite the closedown, it remains committed to bringing forward more detailed proposals for a new nuclear power station at Bradwell-on-Sea in due course. In light of this, it would be of a longer-term advantage to the Council if

Agenda Item no. 7 Our Vision: Sustainable Council – Prosperous Future it were to be in a position where it can quickly re-assemble a Bradwell B project team, with previous expertise and specific knowledge of the project, in order to ensure continuity when the project is restarted.

3.2Local Development Plan Review

3.2.1 The instruction to close down the project team and the withdrawal of funding also has an implication on the Bradwell B Development Plan Document (DPD) which the Council agreed to prepare in February 2020 (Minute No. 770 refers); preparation for which had already commenced in accordance with the statutory Local Development Scheme 2020 - 2022 (LDS).

3.2.2 The responsibility for progressing the Bradwell B DPD as set out in the LDS remains, but the delivery will need to transfer to the Local Plans Team following the funding for the Bradwell Project Team being withdrawn by BRB.

3.2.3 The Council has already considered the recommendations from the Strategy and Resources Committee held on 28 January 2021 in respect of budget setting and the Medium-Term Financial Strategy (MTFS) 2021 / 22 – 2023 / 24. This included a £1m investment between 2021 and 2024 for reviewing the Local Development Plan (LDP) and a £0.594m investment to deliver a suite of planning policy products including the Bradwell B DPD, Planning Obligations Supplementary Planning Document, North Quay Development Brief and a Community Infrastructure Levy as set out in the LDS 2020 - 2022.

3.2.4 In setting the 2021 / 22 budget, consideration was given to the need to review the LDP. Specifically, this relates to Policy S2 and S3 which relate to the District’s housing target until 2029 and the trajectory for its development per annum. The Council’s statutory Authority Monitoring Report 2019 / 20 reported that the District’s performance on housing delivery in its Garden Suburbs and Strategic Allocations had unfortunately missed a target set within the policies for completions over three consecutive years, meaning the Council had hit its own trigger for a partial review of the LDP being needed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 441 KB Download
PDF
Bradwell B Programme Closedown and Local Development Plan ReviewReport 308 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

28 of 29 attended
MS
Councillor Mark S HeardChairperson of the Council, present
CM
Councillor Carlie MayesVice-Chairperson, present
MA
Councillor Miss Anne M BealeCommittee Member, present
BS
Councillor Brian S Beale MBECommittee Member, present
MG
Councillor Mark G BassengerCommittee Member, present
VJ
Councillor Vanessa J BellCommittee Member, present
RG
Councillor Robert G Boyce MBECommittee Member, present
MP
Councillor Mrs Penny A Channer CCCommittee Member, present
RP
Councillor Richard P F DewickCommittee Member, apologies
MF
Councillor Mark F L Durham CCCommittee Member, present
MR
Councillor Michael R EdwardsCommittee Member, present
MJ
Councillor Mrs Jane L FlemingCommittee Member, present

All 29 on the meeting page

More from Maldon Council

All decisions
MeetingDecisionOutcome
22 Oct 2026 Minutes - 10 September 2026RESOLVED (i) that the Minutes of the meeting of the Council held on 10 September 2026 be received. The following typo... Noted Open
22 Oct 2026 Changes to Planning CommitteesRESOLVED (i) That the Council establish a single Planning Committee of 13 Members from 31 October 2026; (ii) That the... Decided Open
22 Oct 2026 Appointment of Membership of the Planning CommitteeRESOLVED that the following Members be appointed to the Planning Committee: Councillors M G Bassenger, J R Burrell-Co... Decided Open
22 Oct 2026 Adjournment of meetingRESOLVED that the meeting be adjourned at 7:46pm to allow a special meeting of the Planning Committee to be held. Decided Open
22 Oct 2026 Resumption of BusinessRESOLVED that the business of the Council be resumed at 7:55pm. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies