Update on the Audit of the 2020/21 Accounts

Decided Finance 1 paper

Performance, Governance and Audit Committee decided this item on Thursday 24 March 2022. Below is the council's own wording, with the papers it was decided on.

Item581

Resolved

RESOLVED that the report was considered.
Word for word from the decision Maldon published for this meeting. Source: democracy.maldon.gov.uk

Follow this further

Built from Maldon's papers

What the report saysPro

Report to Performance, Governance and Audit Committee

Purpose of the report

1.1To update members on the audit of the 2020/21 accounts.

Recommendation

That the report be considered.

3. SUMMARY OF KEY ISSUES

3.1At the Committee meetings on 23 September and 18 November 2021 an update on the delay to the audit of the statement of accounts and reasons for this was provided. Currently the audit of the accounts is still ongoing.

3.2This year the deadline to have accounts audited by was 30 September 2021. In accordance with The Accounts and Audit Regulation 2015 the Council has published an explanation of why the audited accounts are not yet available.

3.3Public Sector Audit Appointments Ltd reported in October that as at the target date of 30 September 2021 only 9% of local government bodies’ 2020/21 audits had been completed. By 31 December 2021 40% had been completed.

4. AUDIT PROGRESS

4.1At the last committee it was reported that a classification issue with how some COVID grants are recorded in the Comprehensive Income and Expenditure Statement (CIES) had been identified. Although an overall nil financial impact, this had implications on the auditor’s level of materiality and would require them to revisit their methodology and carry out additional sample testing.

4.2Audit work commenced again in January 2022 with a view to bringing the accounts to this March Committee for approval. Although good progress has been made on the audit and no areas of significant concern have been identified to date, the audit has not yet concluded. Most areas have been completed but an internal review of the work for quality assurance still needs to be carried out.

4.3Given the progress made and work remaining, the auditors are targeting a sign off date towards the end of April, subject to findings.

Our Vision: Sustainable Council – Prosperous Future 4.4 Preparations for the closure of the 2021/22 remain on track despite responding to audit request throughout the past months. The auditors have also carried out the interim audit for the 2021/22 in the normal timeframes.

5. CHALLENGES FACE IN PREPARING THE ACCOUNTS

5.1Although the audit timeframe has been moved forward from last year, the pandemic has impacted more on this year’s closing process than last year’s. This is due to a variety of factors:

 Consistent with the national infection rates, more staff have been impacted by the virus during this closure period.

 The Council was responding to the pandemic while still delivering business as usual activities. For example, starting events again, paying business grants, supporting local businesses, COVID enforcement and guidance, additional grant funded activities, supporting vaccinations and testing.

 Increased accounting complexities particularly around grants and the Collection Fund (Council Tax and National Non Domestic Rates (NNDR)) due to new legislation and schemes.

 Increased volume of transactions caused by grants and COVID initiatives.

 Additional audit work caused by increased audit requirements (e.g. value for money) and COVID.

 Availability of audit staff caused by a national shortage and the pandemic.

5.2In addition, the Council is reliant on external bodies for parts of the accounts and audit, including Essex Pension Fund. As the Council’s share of the pension fund is included in its accounts there is a reliance on the Pension Fund’s auditors to complete their work. This audit was delayed but has now been completed.

5.3Aside from the issues already listed, the small accounting team also experienced resource challenges. Two members of the team left at short notice during the preparation of the accounts, including the interim who was leading on the closure and handing over. The draft accounts were still prepared on time, but this did have an impact on the preparation of the audit working papers. COVID related sickness also impacted the team during the audit.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on the Audit of the 2020/21 AccountsReport 141 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 12 attended
MJ
Councillor Mrs Jeanette C StiltsChairperson, present
MJ
Councillor Mrs Jane L Fleming CCVice-Chairperson, present
RG
Councillor Robert G Boyce MBECommittee Member, present
MR
Councillor Michael R EdwardsCommittee Member, present
AS
Councillor Adrian S FlukerCommittee Member, present
MS
Councillor Mark S HeardCommittee Member, apologies, sent representative
AL
Councillor Anne L HullCommittee Member, apologies, sent representative
JV
Councillor John V KeyesCommittee Member, present
SJ
Councillor Simon J N MorganCommittee Member, present as substitute
NG
Councillor N G Flo ShaughnessyCommittee Member, present as substitute
WS
Councillor Wendy Stamp CCCommittee Member, present
EL
Councillor Emma L StephensCommittee Member, present

On this subject at Maldon

Search all
  1. Update on the Audit of the 2020/21 AccountsThis decision
  2. Pre-Audit Statement Of Accounts, 2025/26Noted
  3. Update on the Audit of the 2020/21 AccountsDecided
  4. Update on the Audit of the 2020/21 AccountsDecided

More from Maldon Performance, Governance and Audit Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 16 July 2026 be approved and confirmed. Approved Open
17 Sep 2026 External Audit: Building Back AssuranceRESOLVED that the Committee received, considered, and accepted the following: (i) the outcomes of the risk assessment... Decided Open
17 Sep 2026 Corporate Performance Quarter 1RESOLVED (i) T hat the Committee received, considered and reviewed the information as set out in the report and Appen... Decided Open
17 Sep 2026 Review of Corporate Risk Quarter 1RESOLVED (i) That the Committee reviewed and provided comments and feedback on the Corporate Risk Register as set out... Decided Open
17 Sep 2026 Annual Governance Statement Actions UpdateRESOLVED that the Committee had reviewed and commented on the Annual Governance Statement’s table and updates set out... Decided Open