Item81
Resolved
RESOLVED (i) that the proposed Levelling Up projects set out in Appendix 1 to the report which will be submitted to the Department for Levelling Up, Housing and Communities for approval in the form of an investment plan be supported; (ii) that subject to ( i ) being agreed, it is noted that the investment plan will require further officer refinement and completion of due diligence up to the submission deadline of 3 June 2024; (iii) that costs of up to £400,000 can be incurred to fund the anticipated project delivery costs and a new earmarked reserve would be created for this purpose from the Council’s General Fund balances and it is intended to capitalise this funding within the project budget where possible; (iv) that subject to ( i ) above, Members note that a request for budget provision will be included in the 2026 / 27 budget to meet the ongoing costs of maintaining and running the assets once developed.
Word for word from the decision Maldon published for this meeting.
Source: democracy.maldon.gov.uk