Resolved
RESOLVED the 2023 / 24 capital funding of £226,000 allocated for the delivery of the Galleon Project be carried forward to 2024 / 25.
Strategy and Resources Committee decided this item on Thursday 13 June 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED the 2023 / 24 capital funding of £226,000 allocated for the delivery of the Galleon Project be carried forward to 2024 / 25.
1.1To seek Member approval to carry forward the previously agreed capital budget of £226,000 from 2023 / 24 to 2024 / 25, to enable delivery of the Galleon play equipment replacement project to proceed at pace.
1.2This matter is brought forward as an urgent item for consideration with the agreement of the Chairperson, as the full list of 2023 / 24 carry-forwards is not due to be considered by this Committee until 25 July 2024; however in order to deliver this project within the planned timescale of 18 October 2024 it is necessary to place an order with the contractor by Monday 17 June 2024.
That Members agree the 2023 / 24 capital funding of £226,000 allocated for the delivery of the Galleon Project be carried forward to 2024 / 25.
3. SUMMARY OF KEY ISSUES
3.1The current play Galleon is a highly valued, well used and much loved piece of play equipment in Promenade Park. After 18 years it has reached its economic end of life and requires complete replacement. The replacement play ship and adjoining lighthouse will increase the current play offer by a capacity of 40% and also increase the accessibility / inclusivity of the play offer to allow further community engagement.
3.2Replacement of the Galleon was approved as part of the 2023 / 24 capital programme, however it was not possible to complete this during 2023 / 24 due to the size and scale of the scheme of works requiring full planning permission. It is now planned to install the new equipment by 18 October 2024 with the intention of it being ready for use during the October half term 2024.
3.3In order to ensure the project can be completed within these timescales it is necessary to place a formal order with the contractors by Monday 17 June 2024.
3.4Any further delays would result in the project having to be delivered during the autumn / winter with increased risk of adverse weather conditions.
Our Vision: Where Quality of Life Matters 4. CONCLUSION
4.1In order to keep the Galleon replacement project on target for delivery in time for October half term, it is important that an order is placed by Monday 17 June 2024.
4.2As the capital budget was agreed for 2023 / 24 financial year, approval is sought to carry forward this commitment into 2024 / 25.
4.3All other carry-forward requests will come forward to the next Strategy and Resources Committee on 25 July 2024.
5. IMPACT ON PRIORITIES AS SET OUT IN THE CORPORATE PLAN 2023 - 2027
5.1Supporting our communities
5.1.1 The delivery of the replacement Galleon project will ensure this facility remains available for residents and visitors to enjoy and will offer improved accessibility and sensory features.
5.2Enhancing and connecting our place
5.2.1 The Galleon has been a key visitor attraction, and the enhanced accessibility and sensory features will provide a great enhancement to the Promenade Park.
5.3Helping the economy to thrive
5.3.1 The new Galleon will attract new visitors, and will support the local economy, both within the Promenade Park and the local area .
5.4Smarter finances
5.4.1 Combining this project with the delivery of the replacement sensory play equipment in the Promenade Park has delivered financial savings through the contractor being able to co-ordinate the delivery of the two projects, creating efficiencies and cost savings on mobilisation, plant and manpower.
5.5Provide good quality services.
5.5.1 This project supports the continued investment in the Promenade Park, ensuring the provision of good quality, free facilities for residents and visitors.
6. IMPLICATIONS
(i) Impact on Customers – Delivery of the project will provide enhanced experience for our residents and visitors to enjoy, including increased accessibility and sensory elements,
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Approval to Carry Forward Capital Funding for the Galleon Replacement from 2023 / 24Report | 124 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jul 2026 | Minutes of the Last meetingRESOLVED that the Minutes of the meeting of the Committee held on 11 June 2026 be approved and confirmed. | Approved | Open |
| 23 Jul 2026 | Anti-Corruption Policy SuiteRESOLVED that the , as set out in Appendices A to E of the report, be agreed: · Anti-Money Laundering Policy at Appen... | Agreed | Open |
| 23 Jul 2026 | Friary Fields Property AcquisitionRESOLVED (i) That a capital budget of up to £800,000 be approved to fund the acquisition of the Friary Fields propert... | Approved | Open |
| 23 Jul 2026 | SUEZ Depot Expansion ProjectRESOLVED (i) That the total Suez Depot Expansion project budget of £348,289 be approved; (ii) That the Committee note... | Approved | Open |
| 11 Jun 2026 | Minutes of the Last meetingRESOLVED that the Minutes of the meeting of the Committee held on 19 March 2026 be approved and confirmed. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.