Resolved
RESOLVED that the Minutes of the meeting of the Committee held on 18 July 2024 be approved and confirmed.
Performance, Governance and Audit Committee approved this item on Thursday 19 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Minutes of the meeting of the Committee held on 18 July 2024 be approved and confirmed.
MINUTES of PERFORMANCE, GOVERNANCE AND AUDIT COMMITTEE 18 JULY 2024
PRESENT
Chairperson Councillor W Stamp, CC
Vice-Chairperson Councillor N D Spenceley
Councillors S J Burwood, J C Hughes, N R Miller, U C G Siddall-Norman, M E Thompson and S J N Morgan (Substitute for R G Pratt)
Independent Person [name removed]
182. CHAIRPERSON'S NOTICES
The Chairperson welcomed everyone to the meeting and went through some general housekeeping arrangements for the meeting.
183. APOLOGIES FOR ABSENCE AND SUBSTITUTION NOTICE
Apologies for absence were received from Councillors M G Bassenger, R Pratt and J C Stilts. In accordance with notice duly given Councillor S N J Morgan was attending as a substitute for Councillor Pratt.
184. MINUTES OF THE LAST MEETING
RESOLVED that the Minutes of the meeting of the Committee held on 18 June 2024 be approved and confirmed.
185. MATTERS ARISING
The Chairperson took Members through the matters arising report and the following updates were provided: Annual Governance Statement Actions Update – The Director of Service Delivery reported that the Planning Policy Working Group was due to meet on 31 July and a poll would separately sent to all Members regarding dates for a Local Development Plan all Member briefing.
The Chairperson advised that the action regarding an update being sent to Parish and Town Councils would stay on the matters arising until the letter (as detailed in the update) had been seen by the Committee. Infrastructure Funding Statement – In respect of the request relating to Section 106 expiry dates, the Director of Service Delivery advised that Officers were unable to manipulate the database to present the information in the way required by Members. He had spoken to the Council’s ICT Lead Specialist who was going to review the database, including the resources required to produce the information. The Director was confident that the information could be provided.
Also under this item was the information to be provided to Councillor J Driver regarding the allotments at Handley Green. The Chairperson sought an update on this and in response the Director of Service Delivery advised that due to workload pressures the Officer had been unable to complete this, but he confirmed it would be done by the end of this month (July 2024). He would follow it up and ensure the information was also brought back to the Committee.
It was agreed that where previous meetings were referenced links would be provided to assist Members.
RESOLVED that the matters arising be noted.
186. DISCLOSURE OF INTEREST
There were none.
187. PUBLIC PARTICIPATION
No requests had been received.
188. EXTERNAL AUDIT PROGRESS REPORT
The Committee considered the report of the Interim Chief Finance Officer updating Members on the progress of the external audit and audit fees.
The report outlined a number of factors which resulted in an increase in Council’s audit fees above those originally agreed up to the end of the 2022 / 23 appointment period. It was noted that the Council’s new auditor from 2023 / 24 would be KPMG. The Chairperson advised that KPMG were unable to start work until the previous year’s audits had been signed off or agreed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the last meetingMinutes | 198 KB | DownloadRead as text |
Follow Performance, Governance and Audit Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 16 July 2026 be approved and confirmed. | Approved | Open |
| 17 Sep 2026 | External Audit: Building Back AssuranceRESOLVED that the Committee received, considered, and accepted the following: (i) the outcomes of the risk assessment... | Decided | Open |
| 17 Sep 2026 | Corporate Performance Quarter 1RESOLVED (i) T hat the Committee received, considered and reviewed the information as set out in the report and Appen... | Decided | Open |
| 17 Sep 2026 | Review of Corporate Risk Quarter 1RESOLVED (i) That the Committee reviewed and provided comments and feedback on the Corporate Risk Register as set out... | Decided | Open |
| 17 Sep 2026 | Annual Governance Statement Actions UpdateRESOLVED that the Committee had reviewed and commented on the Annual Governance Statement’s table and updates set out... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.