RESOLVED (i) that the Committee considered, commented, and approved the following reports as set out on the agenda: (a) Progress Report 2024 / 25 (February 2025) at 8a; (b) Follow-Up of Recommendations Report (February 2025) – at 8b; (c) Capital and Commercial Project Management Final Report (January 2025) – at 8c; (d) Contract Management Final Report (January 2025) – at 8d; (e) Health and Wellbeing 2024 / 25 Final Report (January 2025) - at 8e (f) Internal Audit Annual Plan 2025 / 26 and Strategic Plan 2023 – 26 – at 8f. The Chairperson thanked the External and Internal Auditors for their reports and attendance. At this point thanks was also given to the Finance Team, particularly the Interim Chief Finance Officer.