Performance, Governance and Audit Committee decided this item on Thursday 5 June 2025. Below is the council's own wording, with the papers it was decided on.
RESOLVED (i) That Members reviewed the Corporate Risk Register in Appendix 1 to the report and provided comment and feedback for consideration; (ii) That Members reviewed progress of the Corporate Risk Mitigating actions in Appendix 2and provided comment and feedback for consideration; (iii) That Members are assured through this review that corporate risk and was being managed effectively; (iv) That Members challenged risk where the Committee felt that the Council’s corporate goals may not be achieved.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
Report to Performance, Governance and Audit Committee
Purpose of the report
1.1The Risk Management Policy requires this Committee to undertake a quarterly review of the Corporate Risk Register as assurance that the corporate risks are being managed effectively.
1.2Online versions of all previous risk reports are available to view on the Members’ SharePoint site.
Recommendations
(i) That Members review the Corporate Risk Register in APPENDIX 1 and provide comment and feedback for consideration;
(ii) That Members review progress of the Corporate Risk Mitigating actions in APPENDIX 2 and provide comment and feedback for consideration;
(iii) That Members are assured through this review that corporate risk and is being managed effectively;
(iv) That Members challenge risk where the Committee feels that the Council’s corporate goals may not be achieved.
3. SUMMARY OF KEY ISSUES
3.1APPENDIX 1 shows a summary and detailed table of the Corporate Risk Register, the latest ratings and officer commentary. The control strength of each risk as well as if there are any active mitigating actions are also included.
Note: Risk controls are an embedded action/process that help control or minimise the likelihood and/or impact of the risk.
3.2New corporate risk raised: Failure to provide adequate building safety and access systems
3.3Recommended for closure: Failure to have a structured way to engage and support local businesses
3.4There are no changes in existing corporate risk ratings and direction since last quarter
Our Vision: Where Quality of Life Matters 3.5 As of Quarter Four (Q4) 2024 / 25 the corporate risk process has fully migrated to a new internal monitoring system, whilst all risks and supporting detail have been migrated like for like some IDs may have changed when comparing to historic reports.
3.6Service level risks are identified and monitored in Service Plans by the relevant Service Plan Owners. They are then escalated, if deemed appropriate and necessary, to committee level for consideration
4. CONCLUSION
4.1Overall, no major Corporate Risk Register concerns have been raised. Work continues to ensure all risks are mitigated, and where possible, working towards their closure.
4.2All Risk Management criteria is set out in the Risk Management Framework.
5. IMPACT ON PRIORITIES AS SET OUT IN THE CORPORATE PLAN 2025 - 2028
5.1It is important that risk is monitored and managed effectively, to ensure that Maldon District Council progresses towards and/ achieves its stated priorities.
6. IMPLICATIONS
(i) Impact on Customers – Those risks in the Corporate Risk Register are defined as having a wider impact on our customers and delivery. The monitoring and mitigation of these will reduce the impact on customers.
(ii) Impact on Equalities – None.
(iii) Impact on Risk – If risk is not managed effectively by the Council, it puts the Councils strategic delivery at risk and increases unnecessary exposure to potential, operational, reputational, or regulatory consequences.
(iv) Impact on Resources (financial) – All risk management is undertaken within existing planned budget. Exceptions being for a potential enactment of a recommendation outside of pre-defined resource.
(v) Impact on Resources (human) – All risk management is undertaken within existing planned budget. Exceptions being for a potential enactment of a recommendation outside of pre-defined resource.
(vi) Impact on Devolution / Local Government Reorganisation (LGR) - Quarterly review of risk considers the wider implications of Devolution and LGR as part of the risk register.
Background Papers: None.
Enquiries to: Doug Wilkinson, Chief Executive Officer.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Performance, Governance and Audit Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
External Audit: Building Back AssuranceRESOLVED that the Committee received, considered, and accepted the following: (i) the outcomes of the risk assessment...
Corporate Performance Quarter 1RESOLVED (i) T hat the Committee received, considered and reviewed the information as set out in the report and Appen...
Review of Corporate Risk Quarter 1RESOLVED (i) That the Committee reviewed and provided comments and feedback on the Corporate Risk Register as set out...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.