RESOLVED that the Council gives approval for the investment of £142 , 000 in addition to the previous approvals totalling £288,000 for additional remedial works to the assets concerned in order to ensure that the subsequent resurfacing works are undertaken in a way that maximises the life of the new surface. The Chairperson thanked Members for the support they had given him this year.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To request £142,000 supplementary funding for works previously approved by the Council to conduct essential resurfacing of Maldon District Council roadways, together with two pay and display car parks.
1.2This is as a result of preparatory works revealing unforeseen structural works. This together with increased material costs require Council approval of the supplementary budget request.
1.3This matter is brought forward for consideration with the agreement of the Chairperson to avoid delay in the planned works which is likely to lead to rescheduling of the works as well as potentially increasing the costs.
Recommendation
That the Council gives approval for the investment of £142,000 for additional remedial works to the assets concerned in order to ensure that the subsequent resurfacing works are undertaken in a way which maximises the life of the new surface.
3. SUMMARY OF KEY ISSUES
3.1Capital schemes previously approved, and changes requested
3.1.1 The 2025/26 capital programme bids included an item for road resurfacing works as: Promenade Park Emergency Road = £55,000, Cobbins Chase = £18,000, and Riverside Park Library Car Park = £25,000, totalling £98,000.
3.1.2 The capital programme also includes an item for resurfacing of the Pay and Display Car Parks at Butt Lane / White Horse Lane totalling £190,000, supporting the Council’s commitment to car park maintenance within its Car Park Strategy.
3.1.3 As the above works have been started, it has become clear that additional previously unplanned and unforeseen works will be required to deliver the overall schemes as originally intended (i.e. with an improved surface and so an extended useful life). This is due to the base layers below the current surface being in a worse state than had
Our Vision: Where Quality of Life Matters been anticipated before the ground was opened. This along with an overall increase to material costs has resulted in a shortfall in the budget requirement.
3.1.4 This report therefore requests additional funding to ensure that works can achieve the previously approved objective, ensuring that the new surface is laid on a base which is fit for purpose so that the useful life of both surface and base will be significantly extended.
3.1.5 At the level of £142,000, this request falls within the delegations to the Council, and cannot be determined by the Strategy and Resources Committee, hence this report.
3.1.6 The contractor is already on site, and there is an advantage to the Council in determining a way forward quickly in order to retain the contractor as planned. Delay is likely to lead to rescheduling of the works with the contractor, as well as potentially increasing the costs. Waiting until the Strategy and Resources Committee in January 2026 and progressing to the Council in February 2026 would create an avoidable eight-week delay.
3.1.7 Members have previously expressed a preference (budget planning in the Finance Working Group and the Strategy and Resources Committee) to invest where appropriate to ensure that the Council’s assets are left in a good state for the successor authority arising through the Local Government Reorganisation (LGR) process. Increasing the funding to ensure that appropriate necessary works are undertaken is in line with this general approach and support the Council’s Car Park Strategy.
4. CONCLUSION
4.1It is considered that approval of additional funding would enable the works to leave the assets in the desired condition (properly repaired and with extended useable life) as previously approved and will ensure that council funds are used consistent with our best value duty.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.