AI summaryMaldon's performance committee reviewed Quarter 3 2025-26 corporate performance and confirmed assurance, with all five Corporate Plan priorities reported on track and no indicators at risk.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedMembers reviewed Q3 and confirmed corporate performance is being managed effectively
MoneyNo specific sums stated; activity within existing planned budgets
What happens nextContinue quarterly monitoringRecovery work where negative impacts are seen
Who it affectsAll five Corporate Plan 2025-2028 prioritiesSupporting communities, investing in district, growing economy, protecting environment, quality services
What was decided
Members reviewed the Q3 performance information, giving priority focus to Strategic Priority level performance. Report P4, 1.2
Members confirmed they are assured that corporate performance is being managed effectively. Report P5, 3.4
Why
The Corporate Performance framework requires this Committee to undertake a quarterly review of Thematic Strategies performance as assurance that corporate priorities are being met. Report 1.1
All reported performance measures are on track at Q3 despite varying influences and resource constraints, for example specific KPIs under Protecting our Environment. Report 4.1
Work is progressing positively for all priorities and the performance delivery of the corporate plan is on track overall. Report 3.4
What happens next
Where negative impacts to performance are seen, priority and focused recovery work will progress to bring measures back on track. Report 4.2
Performance will continue to be monitored and managed to ensure the Council progresses towards or achieves the priorities in the Corporate Plan 2025-2028. Report 5.1
Implications
Risk: If performance is not managed effectively, the Council's corporate priorities delivery is put at risk with potential operational, reputational or regulatory consequences. Report P22
Other: Performance management covers the monitoring of corporate priorities and delivery for customers. Report P20
Equalities: No impact on equalities identified. Report P21
Financial: All performance management is undertaken within existing planned budgets. Report P23
Staffing: All performance management is undertaken within existing planned budgets. Report P24
Other: Ineffective performance management would risk strategic delivery in the context of devolution and local government reorganisation. Report P25
Who and where
Maldon District Council's delivery against the Corporate Plan 2025-2028 priorities Report 5.1, 3.4
Council customers, through the priorities delivery covered by performance management Report P20
Timeline
December 2024: Corporate Plan 2025-2028 adopted; full review of Corporate Performance reporting followed. Report 3.1
Quarter 3 2025-26 (October 2025 to December 2025): Performance period covered by the report and Appendix 1. Report 1.2
12 March 2026: Committee meeting at which Q3 performance was reviewed and assurance confirmed.
Plain English for the jargon
Corporate Plan 2025-2028: Maldon District Council's plan setting out its corporate priorities for that period.
Q3: Quarter 3, covering October 2025 to December 2025.
KPI: Key Performance Indicator, a specific measure used to track performance.
Measure vs Deliverable: Classification showing whether an indicator is a measure or a deliverable.
Control vs Influence: Classification showing the level of responsibility the Council has over an indicator's trajectory.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED (i) That Members reviewed the information as set out in this report and Appendix 1 to the report,with priority focus given to the Strategic Priority level performance; (ii) That Members confirmed they are assured through this review that corporate performance was being managed effectively.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
Report to Performance, Governance and Audit Committee
Purpose of the report
1.1The Corporate Performance framework requires this Committee to undertake a quarterly review of the Thematic Strategies performance as assurance that performance is being managed effectively to achieve the corporate priorities as set out in the Council’s Corporate Plan 2025 – 2028.
1.2APPENDIX 1 to this report provides an overview of the corporate plan performance as of the end of Quarter 3 (October 2025 – December 2025).
1.3Online versions of all previous performance reports are available to view on the MDC Members SharePoint site.
Recommendations
(i) That Members review the information as set out in this report and APPENDIX 1 with priority focus given to the Strategic Priority level performance.
(ii) That Members confirm they are assured through this review that corporate performance is being managed effectively.
3. SUMMARY OF KEY ISSUES
3.1Following the adoption of the Corporate Plan 2025 –2028 in December 2024 a full review of the Corporate Performance reporting has taken place. This has resulted in a new look and feel of the report, as well as a new aligned suite of performance indicators.
3.2All indicators have been classified into groupings to give further definition as to the type of indicator (Measure V Deliverable) and the responsibility that Maldon Council has over the performance trajectory (Control V Influence)
3.3Any concerns affecting the corporate priorities are set out in APPENDIX 1 at priority level, with all supporting data evidencing the priority performance illustrated thereafter.
3.4Overall work is progressing positively for all priorities, and the performance delivery of the corporate plan is on track.
Our Vision: Where Quality of Life Matters Priority Overview Concerns Indicators at risk Not applicable Supporting our communities On track None (N/A) Investing in our District On track N/A None
Growing our economy On track N/A None
Protecting our environment On track N/A None Provide good quality On track N/A None services.
4. CONCLUSION
4.1All the reported performance measures are on track at Q3 despite varying influences and resource constraints, for example specific KPIs under Protecting our Environment
4.2Where negative impacts to performance are seen, priority and focused recovery work will progress to bring measures back on track.
5. IMPACT ON PRIORITIES AS SET OUT IN THE CORPORATE PLAN 2025 - 2028
5.1It is important that performance is monitored and managed effectively, to ensure that Maldon District Council progresses towards and/ or achieves the priorities.
6. IMPLICATIONS
(i) Impact on Customers – Performance management covers the monitoring of corporate priorities. The Corporate Plan includes delivery for our customers.
(ii) Impact on Equalities – None.
(iii) Impact on Risk (including Fraud implications) – If performance is not managed effectively by the Council, it puts the Council’s corporate priorities delivery at risk and increases unnecessary exposure to potential, operational, reputational, or regulatory consequences.
(iv) Impact on Resources (financial) – All performance management is undertaken within existing planned budgets.
(v) Impact on Resources (human) – All performance management is undertaken within existing planned budgets.
(vi) Impact on Devolution and Local Government Reorganisation – If performance is not managed effectively by the Council, it puts the Councils strategic delivery at risk and increases unnecessary exposure to potential, operational, reputational, or regulatory consequences.
Background Papers: None.
Enquiries to: Doug Wilkinson, Chief Executive.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Performance, Governance and Audit Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
External Audit: Building Back AssuranceRESOLVED that the Committee received, considered, and accepted the following: (i) the outcomes of the risk assessment...
Corporate Performance Quarter 1RESOLVED (i) T hat the Committee received, considered and reviewed the information as set out in the report and Appen...
Review of Corporate Risk Quarter 1RESOLVED (i) That the Committee reviewed and provided comments and feedback on the Corporate Risk Register as set out...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.