Outline Business Case for Maldon Museum Extension Project

Deferred Committee 6 papers

AI summaryMaldon District Council has deferred a decision on the Outline Business Case for the Maldon Museum Extension Project to its meeting on 2 July 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredItem to return to Council then
MoneyNo money approvedProposed revenue budget of £329,200 not agreed
What happens nextCouncil meeting on 2 July 2026Item will be reconsidered at that meeting
Who it affectsMuseum and Promenade Park visitorsNo immediate change to current services

What was decided

The Council resolved to defer the Outline Business Case decision to the Council meeting on 2 July 2026, meaning none of the officer recommendations were approved at this stage.

What happens next

The item will return to the Council meeting on 2 July 2026 for further consideration.

If approved on return, the next stage would be development of a Full Business Case, with detailed proposals on capital cost, design, construction programme and operational management arrangements, and a further Council approval required. Report P6, P7

The money

  • £329,200 Proposed revenue budget to progress the Full Business Case (not approved) Report P7
  • c£3.2m Estimated capital financing requirement for the project Report P24, P25
  • £3.2m Estimated capital build cost, assumed funded through external borrowing at circa 5% interest, repaid over 25 years Report P25
  • £400,000 Estimated cost to complete the Full Business Case Report P46
  • £2.8m Estimated capital build cost in the resources implications section Report P46

Implications

  • Risk: Time pressures linked to Local Government Reorganisation: a final decision may need consent from any new strategic authority, depending on total cost and the terms of Section 24 of the Local Government and Public Involvement in Health Act 2007. Report P32, P48
  • Financial: If the project does not continue, costs already incurred in developing the Full Business Case would need to be written off. The proposed borrowings are described as affordable within the existing Authorised Limit and Minimum Revenue Provision tolerance. Report P24, P46
  • Equalities: No immediate equalities impact identified at this outline stage. Report P44
  • Other: No immediate impact on customers at this outline stage. Report P43
  • Staffing: The proposed budget includes provision to procure additional resources to support Council officers in delivering the business case. Report P47
  • Climate: The proposal would use environmentally considerate materials and be mindful of ecology in the park. Report P41

Who and where

  • Visitors to Maldon District's Promenade Park, which the report says accommodates around half a million visitors a year Report P16
  • Maldon Museum users and the local community, including schools and other museums, who would be expected to engage with the extended facility Report P14, P20
  • Tourists and the wider district economy, given the museum's role in the visitor offer Report 3.2, P16, P39

Timeline

  • September 2017: Maldon District Council's Planning and Licensing Committee adopted the Central Area Masterplan, identifying a Destination Hub and PPMP opportunity Report P13
  • 12 June 2025: Strategy and Resources Committee approved the Promenade Park Management Plan and concept business case for the museum development (Minute No. 85) Report 3.1
  • October 2025 to February 2026: Strategic Assets Working Group developed the brief from concept designs to formation of the Outline Business Case Report P14
  • February 2026: Council approved the Capital Investment and Treasury Management Strategy which provides the Authorised Limit for the borrowing Report P24
  • 2026-03-26: Council deferred the decision on the Outline Business Case
  • 2 July 2026: Council meeting now scheduled to reconsider the Outline Business Case

Plain English for the jargon

  • OBC: Outline Business Case
  • FBC: Full Business Case
  • PPMP: Promenade Park Management Plan
  • CAMP: Central Area Masterplan, a 2017 planning document for Maldon town centre
  • SAWG: Strategic Assets Working Group
  • LGR: Local Government Reorganisation
  • MDC: Maldon District Council
  • Minimum Revenue Provision: The amount a council sets aside each year from revenue to repay borrowing, here assumed as 1/25th of capital cost over 25 years
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

RESOLVED that this item of business be deferred to the Council meeting scheduled to take place on 2 July 2026.
Word for word from the decision Maldon published for this meeting. Source: democracy.maldon.gov.uk

Follow this further

Built from Maldon's papers

What the report saysPro

Report to Council

Purpose of the report

1.1To present the Outline Business Case (OBC) for the Maldon Museum Extension Project and to seek Council approval to progress to a Full Business Case (FBC).

Recommendations

(i) That the Outline Business Case at APPENDIX 1 for the Maldon Museum Extension Project be approved;

(ii) That a Maldon Museum Extension Project Board (the Project Board) be set up and Councillors J Driver, A M Lay, R H Siddall, W Stamp and M E Thompson be appointed to it;

(iii) That the Project Board Terms of Reference as set out at A6 of APPENDIX 2 be agreed;

(iv) That delegation is granted to the Chief Executive, in consultation with the Project Board, to finalise and submit the planning application for this project;

(v) That the Council supports the development of the Full Business Case to be brought back to a future meeting of the Council, including detailed proposals on capital cost, design, construction programme, and proposed operational management arrangements;

(vi) That subject to the approval of (v), a revenue budget of up to £329,200 to progress the Full Business Case be agreed.

3. SUMMARY OF KEY ISSUES

3.1The Promenade Park Management Plan (PPMP), and associated appendices, were approved by the Strategy and Resources Committee on 12 June 2025 (Minute No. 85 refers) along with a detailed range of projects that are being delivered to improve existing facilities and provide new attractions in the park. Within this, a concept business case for the Promenade Park Museum Development was approved.

3.2Since the PPMP adoption, officers have been progressing the concept business case for the Promenade Park Museum Development to OBC as detailed at APPENDIX 1. This identifies that an extension to the existing museum, fits within the PPMP to recognise the park area as a destination, capitalising on the tourist market, visitor attractions and heritage that curate our local history.

Our Vision: Where Quality of Life Matters 3.3 The Outline Business Case for the Maldon Museum Extension Project APPENDIX 1 clearly sets out the project against a standardised business case model of:  Strategic Case - alignment with Maldon District Council’s (MDC) Corporate Plan, priorities and strategies;  Economic Case - ability to demonstrate value for money;  Socio-Economic Case – ability to demonstrate social viability;  Financial Case - the funding arrangements required to support the project;  Management Case - capacity of MDC to deliver this project .

3.4Strategic Case

3.4.1 Maldon District Council’s Planning and Licencing Committee in September 2017, adopted the Central Area Masterplan (CAMP) 2017 which identified the opportunity to create new visitor attractions within Maldon's Promenade Park and Hythe Quay, including specifically a “Destination Hub” and the “PPMP”. This was identified via intermediate studies, and support was given to providing a new regional restaurant/cafe within Promenade Park (providing much needed under cover seating) which would be combined with a visitor centre and destination point.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 2 MB Download
PDF
A1Appendix 2 986 KB Download
PDF
A2Appendix 2 5 MB Download
PDF
A3Appendix 2 266 KB Download
PDF
A4Appendix 2 962 KB Download
PDF
Outline Business Case for Maldon Museum Extension ProjectReport 238 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

28 of 32 attended
KM
Councillor Kevin M H LaganChairperson, present
RG
Councillor Ron G PrattVice-Chairperson, present
MG
Councillor Mark G BassengerCommittee Member, present
VJ
Councillor Vanessa J BellCommittee Member, present
DO
Councillor Doug O BownCommittee Member, apologies
JR
Councillor James R Burrell-CookCommittee Member, present
SJ
Councillor Simon J BurwoodCommittee Member, apologies
SD
Councillor Sarah DodsleyCommittee Member, present
JD
Councillor John DriverCommittee Member, present
MF
Councillor Mark F L Durham CCCommittee Member, present
TF
Councillor Tony FittockCommittee Member, present
AS
Councillor Adrian S FlukerCommittee Member, present

All 32 on the meeting page

More from Maldon Council

All decisions
MeetingDecisionOutcome
22 Oct 2026 Minutes - 10 September 2026RESOLVED (i) that the Minutes of the meeting of the Council held on 10 September 2026 be received. The following typo... Noted Open
22 Oct 2026 Changes to Planning CommitteesRESOLVED (i) That the Council establish a single Planning Committee of 13 Members from 31 October 2026; (ii) That the... Decided Open
22 Oct 2026 Appointment of Membership of the Planning CommitteeRESOLVED that the following Members be appointed to the Planning Committee: Councillors M G Bassenger, J R Burrell-Co... Decided Open
22 Oct 2026 Adjournment of meetingRESOLVED that the meeting be adjourned at 7:46pm to allow a special meeting of the Planning Committee to be held. Decided Open
22 Oct 2026 Resumption of BusinessRESOLVED that the business of the Council be resumed at 7:55pm. Decided Open