25/00972/FUL Agricultural Building at Oak Nursery, Hackmans Lane, Purleigh

Approved Planning 1 paper

AI summaryMaldon planners approve a detached two-bedroom home at Oak Nursery, Purleigh, after demolishing existing glasshouses. The site lies outside the Cock Clarks settlement boundary but a prior approval for a similar conversion is treated as a fallback.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFull planning permission granted, 18 conditions
MoneyRAMS fee top-upDifference paid by applicant to cover fee rise since last year
What happens nextThree years to startDevelopment must begin within three years of permission
Who it affectsOak Nursery site, PurleighReplaces glasshouses with one two-bedroom home

What was decided

Members approved the application, granting full planning permission for one detached single-storey two-bedroom market home, subject to 18 conditions covering landscaping, boundary treatment, tree protection, ecology, drainage, contamination, construction management and working hours. Report P1, P123

The decision was driven by the council's failure to demonstrate a five-year housing land supply, which engages the tilted balance in paragraph 11d of the NPPF in favour of sustainable development. Report P27, P28, P32, P38, P81

Why

Officers concluded the dwelling would not harm the character of the rural area, would not unreasonably affect neighbours, would reuse the existing access and hardstanding, and the housing mix of two bedrooms matches the latest local housing needs assessment. Report P13, P40, P46, P50, P54, P58, P73, P93

A fallback position was given significant weight: a prior approval granted earlier this year (25/00486/PACUAR) for converting a glasshouse on the site into a dwelling, and another dwelling allowed on appeal in 2021. Report P7, P36, P104, P107

The applicant confirmed by letter dated 26 March 2026 that the nursery's plant-growing operation is winding down, supporting the loss of the glasshouses as effective use of land. Report P79

What happens next

Conditions require submission and approval of hard and soft landscaping details, boundary treatments, a tree survey and protection plan, a biodiversity enhancement strategy, a lighting design for bats, a phase 1 contamination desk study, drainage schemes and a construction management plan before any above-ground works. Report P128, P137, P138, P141, P144, P147, P150, P152, P153

Cycle parking must be provided before first occupation, an asbestos survey must precede demolition, and the applicant must pay the balance of the RAMS contribution. Report P76, P146, P149

Construction hours are restricted to 08:00-18:00 Monday to Friday, 08:00-13:00 Saturday, with no work on Sundays or bank holidays. Report P151

Options considered

  • Chosen: Approve the application. Tilted balance engaged due to 3.97-year housing supply; no demonstrable harm identified; fallback position exists; two-bedroom home meets identified need. Report P1, P27, P42, P107
  • Rejected: Refuse the application. Not formally put forward; officers found no harm that would significantly and demonstrably outweigh the benefits. Report P13, P30, P42

Implications

  • Legal: Tilted balance under NPPF paragraph 11d applied because the council cannot demonstrate a five-year housing land supply (3.97 years as of 6 July 2026). Report P27, P28, P30, P31
  • Environmental: Site exempt from mandatory Biodiversity Net Gain because the dwelling sits on existing hardstanding; ecology officer raises no objection subject to lighting and mammal informatives. Report P69, P73
  • Climate: Surface water drainage must cater for the 1 in 100-year event plus 45% climate change allowance. Report P154
  • Risk: Contamination condition requires a phase 1 desk study and, if contamination is found, a remediation scheme before works continue; asbestos survey required before demolition. Report P147, P148, P149
  • Other: Permitted development rights removed for extensions, garages or outbuildings over 10 cubic metres. Report P157

Who and where

  • Future occupiers of the new two-bedroom dwelling at Oak Nursery, Hackmans Lane, Purleigh Report P8, P9
  • Neighbouring properties Oakside, Fern Cottage and The Willows Report P49, P50, P51, P52
  • Existing Oak Nursery business, which is winding down plant growing Report P79
  • Purleigh Parish Council, which supported the application Report P112
  • Essex County Council Highways, which raised no objections subject to a cycle parking condition Report P60, P62, P114

Timeline

  • 12 December 2024: Amended NPPF published, removing the 5% buffer transitional arrangements and changing the housing target to 569 homes per year Report P23, P27
  • 18 February 2026: Site notice posted Report P118
  • 19 February 2026: Newspaper advertisement placed Report P118
  • 26 March 2026: Applicant's letter confirming the nursery plant-growing business is winding down Report P79
  • 6 July 2026: Council's five-year housing land supply stands at 3.97 years following an appeal decision Report P27
  • 12 August 2026: North Western Area Planning Committee resolved to approve, subject to conditions

Plain English for the jargon

  • Tilted balance: NPPF paragraph 11d, applied when a council cannot show a five-year housing land supply, tilting the planning balance towards granting permission unless harm significantly and demonstrably outweighs benefits.
  • 5YHLS: Five-Year Housing Land Supply, the rolling count of deliverable housing sites a local authority must maintain.
  • Prior Approval: A process under the General Permitted Development Order where certain conversions, such as agricultural buildings to homes, are allowed if the local planning authority does not refuse prior approval.
  • RAMS: Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy, requiring developer contributions to mitigate the impact of new homes on protected coastal sites.
  • Biodiversity Net Gain: A requirement that development delivers a measurable improvement in habitat value, though this site is exempt because it uses existing hardstanding.
  • LDP: Maldon District Local Development Plan 2014 to 2029, the adopted planning policy framework for the district.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item205

Resolved

RESOLVED that the application be APPROVED subject to the following conditions: 1. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. 2 The development hereby permitted shall be carried out in accordance with the approved plans as stated on the Decision Notice. 3 The materials used in the construction of the development hereby approved shall be as set out within the application form/ plans hereby approved. 4 Prior to any works above ground level, full details of the provision and subsequent retention of both hard and soft landscape works on the site have been submitted to and approved in writing by the Local Planning Authority. These details shall include: 1) Details of proposed schedules of species of trees and shrubs to be planted, planting layouts with stock sizes and planting numbers/densities. 2) Details of the planting scheme implementation programme, including ground protection and preparation, weed clearance, stock sizes, seeding rates, planting methods, mulching, plant protection, staking and/or other support. 3) Details of the aftercare and maintenance programme. The soft landscape works shall be carried out as approved within the first available planting season (October to March inclusive) following the commencement of the development unless otherwise agreed in writing by the Local Planning Authority. If within a period of five years from the date of the planting of any tree or plant, or any tree or plant planted in its replacement, is removed, uprooted, destroyed, dies, or becomes, in the opinion of the Local Planning Authority, seriously damaged or defective, another tree or plant of the same species and size as that originally planted shall be planted in the same place, unless the Local Planning Authority gives its written consent to any variation. Hard Landscape works: 4) Details of walls with brick types, construction design and dimensions 5) Details of paved surfacing, with materials finishing and edgings The hard landscape works shall be carried out as approved prior to the first use/ occupation of the development hereby approved and retained and maintained as such thereafter. 5 Prior to any works above ground level, details of the siting, height, design and materials of the treatment of all boundaries including gates, fences, walls, railings and piers should be submitted to and approved in writing by the Local Planning Authority. The boundary treatments as approved shall be retained ... view the full minutes text for item 205.
Word for word from the decision Maldon published for this meeting. Source: democracy.maldon.gov.uk

Follow this further

Built from Maldon's papers

What the report saysPro

Report to North Western Area Planning Committee

Recommendation

APPROVE subject to the conditions (as detailed in Section 8 of this report).

2. SITE MAP

Please see below.

Our Vision: Where Quality of Life Matters 3. SUMMARY

3.1Proposal / brief overview, including any relevant background information

3.1.1 Oak Nursery is a horticultural site operating since 1993 for the growing of bedding plants, perennials and baskets for sale to garden centres. The site is located on the southeastern side of Hackmans Lane, located approximately 450 metres south of the settlement boundary of Cock Clarks. It is within the countryside amongst a collection of farming plots and is not within a conservation area. The area is rural farmland with mostly agricultural buildings and a few sporadic residential units.

3.1.2 The site forms part of a wider site, which comprises of a number of barns, greenhouses and two dwellings. Access to the outbuilding in question, is via an existing gated access from Hackmans Lane. To the northeast of the application site, Prior Approval was granted for a dwellinghouse in 2016 (COUPA/MAL/16/00080) and another was granted via appeal to the southwest of the site (21/00712/COUPA). Furthermore, Prior Approval was granted for one of the glasshouses due for demolition, to be turned into a residential building under 25/00486/PACUAR and stands as a fallback position.

3.1.3 Planning permission is sought for the demolition of existing glasshouses within the red line boundary and the construction of a detached, single storey dwelling with associated parking. The proposed new dwelling would be a two-bedroom dwelling and would be market housing.

3.1.4 The proposed dwelling would have a depth of 19.98 metres and a width of 6.9 metres. The ridge height would be 4.07 metres and would be 2.4 metres to the eaves. Although a very similar scheme to the approved 25/00486/PACAUR, the new dwelling would be slightly wider and taller but would be significantly smaller in terms of depth, than the approved 25/00486/PACAUR. Its design would be similar to the existing glasshouses and would provide for an open plan kitchen / living space, a bathroom, ensuite, utility room and two bedrooms. There would also be a glazed porch at one end. Materials for its construction would be a standing seam aluminium roof, vertical European Larch timber cladding and rendered plinth and aluminium windows and doors. The entrance area/porch would be aluminium faring with glazing.

3.1.5 The proposed outside area and associated parking would be mainly located to the southwest of the development with a small area of curtilage around the dwelling and to the northeast. The parking would accommodate two cars plus turning space.

3.1.6 The site would share an access that is established and already serves the other two residential buildings and the rest of the site.

3.2Conclusion

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/00972/FUL Agricultural Building at Oak Nursery, Hackmans Lane, PurleighReport 457 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
MF
Councillor Mark F L DurhamChairperson, present
LL
Councillor Lisa L WiffenVice-Chairperson, apologies
JC
Councillor Jade C HughesCommittee Member, apologies
SJ
Councillor Simon J N MorganCommittee Member, present
CP
Councillor Clive P MorleyCommittee Member, present
RH
Councillor Richard H SiddallCommittee Member, apologies
EL
Councillor Emma L StephensCommittee Member, present
ME
Councillor Maddie E ThompsonCommittee Member, present
SW
Councillor Sue WhiteCommittee Member, apologies
DH
Devan HearnahOfficer, expected
EH
Emma HolmesOfficer, expected
MJ
Mark JaggardOfficer, expected

All 17 on the meeting page

On this subject at Maldon

Search all
  1. 25/00972/FUL Agricultural Building at Oak Nursery, Hackmans Lane, PurleighThis decision
  2. 25/00590/FUL - Agricultural Barn at Loddarts Farm, Lodge Road, Woodham MortimerApproved
  3. 20/00678/FUL - Agricultural Barns Adjacent 31 Plains Road, Great TothamApproved
  4. 20/00062/FUL - Agricultural Barns Adjacent 31 Plains Road, Great TothamRefused
  5. FUL/MAL/18/00587 - Agricultural Buildings Honeywood Farm, Honeypot Lane, Stow Maries, EssexApproved
  6. FUL/MAL/16/01114 - Agricultural Barn, Goldsands Road, SouthminsterApproved

More from Maldon North Western Area Planning Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 12 August 2026 be approved and confirmed. Approved Open
9 Sep 2026 26/00157/FUL Caravan At Toad Hall, Station Road, Cold NortonRESOLVED that the application be APPROVED subject to the following conditions: 1 The development hereby permitted sha... Approved Open
9 Sep 2026 25/00421/FULM Rosedale, Lea Lane, Great Braxted, Witham, Essex, CM8 3ERRESOLVED (i) that the application be APPROVED and authority be delegated to the Director of Place, Planning and Growt... Approved Open
12 Aug 2026 Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 15 July 2026 be approved and confirmed. Approved Open
12 Aug 2026 25/00997/FUL Land adj to Oak Corner Cottage, Southend Road, Woodham Mortimer CM9 6TGRESOLVED that the application be REFUSED for the following reason: 1 The proposed dwelling, by reason of its close pr... Refused Open