AI summaryMaldon District Council has agreed to commence a new Local Plan under the 30-month plan-making system, allocating a £2,075,000 reserve. The plan must reach submission by October 2028 to meet the new statutory deadline of 31 December 2026 for starting the process.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommence preparation under new 30-month system
Money£2,075,000 reserveIncludes 15% contingency and three new posts
What happens nextNotice of Intention 25/09/2026Begins four-month notice period before plan-making
Who it affectsMaldon District residents and developersNew planning framework for housing and growth
What was decided
The Council agreed to commence a new Local Plan for Maldon District under the new 30-month plan-making system, approved the Project Initiation Document, the timetable, and the Notice of Intention to Commence. Report P5, P6, P7, P8
The Council revoked the Local Development Scheme (February 2025), which is no longer aligned with the new system. Report P7, 7.2
The Council allocated a £2,075,000 reserve and delegated authority to the Director of Place, Planning and Growth to update the PID and timetable, in consultation with the Planning Policy Working Group. Report P9, P10
Why
The new National Planning Policy Framework of December 2024 nearly doubled Maldon's housing need to 586 homes per annum and the Council lost its Five-Year Housing Land Supply, requiring a fundamental review of sites. Report 3.3
The Government has set a deadline of 31 December 2026 to publish an intention to commence plan-making under the new system, starting the 30-month clock; the legacy system deadline of the same date could not be met. Report 3.5, 3.7
Failure to progress the plan risks increased speculative development, reliance on outdated policies, and potential intervention by the Secretary of State. Report P31
What happens next
The Council will publish the Local Plan Timetable and Notice of Intention to Commence on 25/09/2026, beginning the four-month notice period. Report P68, 7.1
A Regulation 20 Scoping Consultation will run from 25/11/2026 to 22/12/2026, with a Council decision to proceed in November 2026. Report P68, P69
The Council will publish its Gateway 1 self-assessment by 12/03/2027, formally starting the 30-month plan-making period, with the plan targeted for submission on 24/10/2028 and adoption on 02/05/2029. Report P69, P70
The money
£2,075,000 Reserve allocation for the new Local Plan, including 15% contingency and three new posts Report P9, 6.5
£2,076,900 Total estimated budget for the new Local Plan, rounded to £2,075,000 in the recommendation Report 6.2, P64
£1,500,000 Arup's estimated budget for the new Local Plan, excluding officer costs Report 4.3
£450,000 Indicative additional staffing cost for three new posts over the three-year programme Report 6.4, P64
£270,900 15% contingency included in the total budget Report P64
£31,340 Cost of Arup's work to inform the decision to begin a new Local Plan Report 6.1
£1,316,669 Total LDP Review costs 2021-2026 (staffing plus evidence base studies) Report 5.2, P54
£871,671 Staff costs over the five-year LDP Review period to 2026 Report 5.2, P52
Options considered
Rejected: Option 1 - Do nothing. Statutory duty to plan; Government deadline of 31 December 2026 to commence; risk of speculative development and Secretary of State intervention Report 4.5, P29, P30, P31, P32
Rejected: Option 2 - Redeploy internal resources. Planning Policy and Development Management teams are fully committed to statutory functions and lack capacity Report 4.6, P34, P35
Rejected: Option 3 - Work with a neighbouring authority. Discussions with Brentwood and Chelmsford found limited scope for joint working without delaying the programme Report P36, P37
Rejected: Option 4 - Full consultancy support. Less cost-effective than updating existing evidence through original consultants alongside an in-house team Report 4.8, P39, P40
Chosen: Option 5 - Partial consultancy support. Provides targeted specialist expertise and short-term capacity for selected evidence base studies Report 4.9, P42
Chosen: Option 6 - Recruitment of additional planners. Expands Planning Policy team capacity; two roles already being recruited Report 4.10, P44, P46
Implications
Financial: A £2,075,000 reserve is allocated with 15% contingency to reflect uncertainty in the new plan-making system; Arup's budget excludes officer costs. Report 6.3, 6.5, P64
Staffing: Three new posts are proposed: a Policy Planner, a Senior Policy Planner, and a Section 106 Officer, at an indicative £50,000 each over the three-year programme. Report 6.4
Risk: A risk register for the new Local Plan is included as Appendix 3; failure to progress risks Secretary of State intervention. Report P98, P31
Legal: The Council has a statutory duty to prepare a Local Plan; an Equalities Impact Assessment will be undertaken as part of the new plan. Report P29, P97
Other: Local Government Reorganisation means MDC is expected to join a Mid-Essex Unitary Authority from April 2028; final decisions to submit and adopt the plan will rest with the new unitary. Report 8.2, 9.1, 9.3
Who and where
Maldon District residents and communities Report P30, P96
Developers and planning applicants in the district Report P31
Maldon District Council Planning Policy team Report 6.4, 4.10, P44
The future Mid-Essex Unitary Authority (from April 2028) Report 8.2, 9.1
Brentwood Borough Council and Chelmsford City Council, through a Planning LGR Workstream Report 9.3
Timeline
25/09/2026: Publish Local Plan Timetable and Notice of Intention to Commence; four-month notice period begins Report P68
Nov. 2026: Council decision to undertake Scoping Consultation Report P68
12/03/2027: Publish Gateway 1 self-assessment, formally starting the 30-month plan-making period Report P69
Aug. 2027: Council decision to consult on proposed Plan Contents and Evidence Report P70
26/05/2028: Regulation 27 consultation on the new proposed Local Plan starts Report P70
24/10/2028: Submit Local Plan for examination Report P70
02/05/2029: Adoption of Local Plan targeted Report P70
Plain English for the jargon
LDP: Local Development Plan, the existing local plan for Maldon District under review since 2021
5YHLS: Five-Year Housing Land Supply, which the Council lost under the updated NPPF
NPPF: National Planning Policy Framework, updated in December 2024 and again on 17 August 2026
PID: Project Initiation Document, the project management document setting out scope, resources, governance and timelines
LGR: Local Government Reorganisation, the creation of new unitary authorities including a proposed Mid-Essex Unitary from April 2028
PINS: Planning Inspectorate, which provides Gateway 2 and Gateway 3 advice
PPWG: Planning Policy Working Group, a cross-party councillor forum that advises on the Local Plan
LURA: Levelling Up and Regeneration Act 2023, which introduced the new 30-month plan-making system
Gateway 1: Statutory self-assessment that formally starts the 30-month plan-making period
SDS: Spatial Development Strategy, an emerging Greater Essex county-wide strategic planning framework
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
RESOLVED that the Council: ( i ) notes the work undertaken by consultants Arup: · Arup Project Initiation Document (Appendix 1 to the report) · Arup Budget (Appendix 2 to the report) · Arup Risk Register (Appendix 3 to the report) (ii) agrees to commence a new Local Plan for Maldon District; (iii) approves the Local Plan for Maldon District Project Initiation Document (Appendix 4 to the report); (iv) agrees the Local Plan Timetable (Appendix 5 to the report) and revokes the Local Development Scheme (February 2025), as explained in paragraph 3.5.2 of the report; (v) approves the Notice of ... view the full minutes text for item 11.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1For the Council to consider whether to commence work on a new Local Plan for Maldon District under the new 30-month plan-making system.
1.2The draft Council report and appendices were presented to Planning Policy Working Group (PPWG) on Tuesday 11 August 2026, who endorsed the recommendations set out in section 2 of this report.
Recommendations
That the Council:
(i) notes the work undertaken by consultants Arup: Arup Project Initiation Document (APPENDIX 1) Arup Budget (APPENDIX 2) Arup Risk Register (APPENDIX 3)
(ii) agrees to commence a new Local Plan for Maldon District;
(iii) approves the Local Plan for Maldon District Project Initiation Document (APPENDIX 4);
(iv) agrees the Local Plan Timetable (APPENDIX 5) and revokes the Local Development Scheme (February 2025), as explained in paragraph 3.5.2 below;
(v) approves the Notice of Intention to Commence (APPENDIX 6) for publication;
(vi) agrees to allocate a reserve of £2,075,000 to spend on the new Local Plan for Maldon District, including an allowance for contingencies and additional staff resources to progress the Local Plan through a new plan-making system;
(vii) delegates authority to the Director of Place, Planning and Growth to amend and update the Local Plan for Maldon District Project Initiation Document (APPENDIX 4) and Local Plan Timetable (APPENDIX 5), in consultation with the Planning Policy Working Group.
Our Vision: Where Quality of Life Matters 3. BACKGROUND AND CONTEXT
3.1Work began on a review of the Maldon District Local Development Plan (LDP) in 2021. Significant progress having been made, including public consultation, creation of an evidence base and a call for sites exercise being undertaken.
3.2The Levelling Up and Regeneration Act in October 2023 (LURA) introduced a new approach to plan-making, which is based upon a shorter timeframe, more proportionate evidence base and clearer project management steps.
3.3Alongside reforms to the plan-making system, in December 2024 the Government published a National Planning Policy Framework (NPPF), updated sections of the Planning Practice Guidance (PPG) and other updates. This introduced a new way to calculate local housing needs, meaning the housing requirement for Maldon district nearly doubled and the Council lost its Five-Year Housing Land Supply (5YHLS). This required a fundamental review of the sites which could be allocated in a new Local Plan for Maldon district. If these housing figures had not changed in 2024, it is likely that the Council could have submitted its local plan for examination under the legacy system. The latest housing need figure for the Maldon district is a requirement of 586 homes per annum.
3.4Although the LURA 2023 introduced a new approach to plan-making, the secondary legislation for the new plan-making system was not published until March 20261. A diagram summarising the new plan-making system is set out below:
Lichfields’ interpretation of the Local Planning Regulations 2026
3.5As part of the national reforms to the plan-making system, the Government set a limited transition period for Local Plans being prepared under the old / legacy system, with a deadline for submitting the plan for examination by 31 December 2026. However, it has become clear that the review of the Maldon District LDP would not be able to meet that deadline due to the work and consultations that still needed to take place. The Government has also set a deadline for Councils that are not able to submit a plan under the legacy system, having to publish their intention to commence plan-making in the new system by 31 December 2026; this will then 'start the clock' on the 30-month timeframe in the new system.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.