RESOLVED that (i) the development of a Countywide Play Strategy be endorsed; (ii) the commencement through the Leisure Services Project Board of the detailed preparatory work for the district wide projects, be endorsed; (iii) Cllr S Croad be appointed to the Leisure Services Project Board; and (iv) the Leisure Services Project Board report back to Council on the projects to be undertaken.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Ward: All Portfolio Holder: Cllr. Clive Smith Executive Committee 26th September 2006
Report of Head of Community & Economic Development Development of a Worcestershire Play Strategy
1. Purpose of Report 1.1 To recommend the development of a Worcestershire Play Strategy, linked to the Worcestershire Children & Young People’s Plan, with an associated portfolio of projects for Malvern Hills District Council.
Recommendation that -
(i) the Council endorses the development of a Countywide Play Strategy; and (ii) the Council formally approves Malvern Hills District Council’s associated portfolio of projects.
2. Background/Introduction 2.1 The 2004 report by Frank Dobson Getting Serious About Play, concluded that a dedicated children’s play programme was crucial for delivering better opportunities.
2.2As a result The Big Lottery Fund (BIG) has made a £155 million commitment to supporting children’s play in England. The initiative incorporates three key elements – the Playful Ideas programme, the Children’s Play programme and the Play England project. The overall aim of the initiative is to create, improve and develop children and young people’s free local play spaces and opportunities throughout England.
2.3The three elements of the initiative are as follows:-
i) Children’s Play (£124m): In November 2005, BIG wrote to all local authorities, informing them of the amount of money that would be made available to their area. It is now the responsibility of each local authority (LA) to devise a play strategy which identifies areas of greatest need. This will need to include consultation with local stakeholders, including the voluntary and community sector.
ii) Playful Ideas (£16m): This will fund innovative projects, showing creative and novel approaches to addressing need. Under this programme, registered charities, voluntary or community groups, charitable or not-for- profit companies, social enterprises and town and parish councils can apply. Page 1 Report No: EC803 Grants of between £10k and £250k will be available to cover direct revenue and capital costs. Outline proposals must reach BIG before December 2007. All application proposals should show links to the Play Strategy.
iii) Play England (£15m): The Children’s Play Council (CPC), part of the National Children’s Bureau, has been awarded a £15m grant over five years to deliver the project which aims to help local agencies in planning for play by setting up a national support and development infrastructure across the regions. CPC will be working with LA’s to develop their local play strategies enabling them to apply to spend their allocation from the Children’s Play programme.
2.4Malvern Hills District Council have been allocated £200,000 from the Children’s Play Programme. This allocation is based on the number of children in the district and weighted by the level of poverty.
2.5Councillor Serena Croad has been nominated as the Children and Young People’s Champion for the Council, with Amanda Smith, Cultural Services Manager, named as the lead officer.
3. The Need for a Countywide Play Strategy 3.1 Worcestershire has been allocated upwards of £1.2 million from the Children’s Play programme, across its District Councils. However, local play strategies are required by the BIG Lottery to support applications to its programme.
3.2A multi-agency group (Play Partnership) met in April 2006 to scope the possibility of working together to develop a Countywide Play Strategy.
3.3The District Councils have stated that they are prepared ‘in principle’ to contribute towards the development of a Countywide Play Strategy.
3.4In July 2006, the Children & Young People Strategic Board endorsed the development of a Countywide Play Strategy.
4. Project Management 4.1 Using the principles of Prince 2 methodology to manage the brief, the Liveability Partnership Manager will act as the project manager for the development of a Countywide Play Strategy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.