Resolved
RESOLVED that (i) the report be noted; (ii) the major achievements in performance be recorded and celebrated; and (iii) the actions proposed to enhance performance further be endorsed.
Executive Committee noted this item on Tuesday 23 January 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that (i) the report be noted; (ii) the major achievements in performance be recorded and celebrated; and (iii) the actions proposed to enhance performance further be endorsed.
Ward: All Portfolio Holder: Cllr D Rayner Executive Committee 23rd January 2007
Report of Chief Executive Quarterly Corporate Performance Report
1. Purpose of Report 1.1 To report the review of the council’s corporate performance for the second quarter of 2006/7 ending 30th September 2006
Recommendation that -
(i) the report be noted; (ii) the major achievements in performance be recorded and celebrated; and (iii) the actions proposed to enhance performance further be endorsed.
2. Introduction 2.1 The Performance Management Framework was modified in May 2006 to incorporate revised arrangements for the quarterly review of corporate performance at a strategic level by Portfolio Holders and senior managers.
2.2The review was undertaken by the Quarterly Performance Forum, consisting of all portfolio holders and senior managers, on December 13th 2006. The review was informed by detailed reports from individual managers and portfolio holders, and was structured around the Council’s objectives.
3. Review Findings 3.1 The review found that there have been significant and wide ranging performance achievements during the quarter. They include:
Improvements in the cleanliness of public land areas to levels which are amongst the best in the country;
24.75% of household waste was recycled, a level in the top quartile of all councils;
The number of missed waste collections has reduced by 25% over the previous year
Community safety in the district remains in top quartile and is better than last year; Page 1 Report No: EC828 The completion of the Dyson Perrins High School sports facilities;
Implementation of the Tenbury Tourism project;
Establishment of a shop front grant scheme for Upton;
A total of 12 housing schemes are now in place and which should enable the Council’s target of 110 new affordable units and access to opportunities to be met by the year end. An additional 18 schemes are scheduled for completion during 2007/8 to provide a further 200 affordable homes.
Take up of the enhanced concessionary fares scheme has increased to 40% of those eligible, and the number of subsidised journeys has doubled.
Benefit claims were processed more quickly and more accurately in Malvern Hills than in the majority of other councils.
3.2These major achievements have been made in the context of:
Lower costs than most district councils;
Customer satisfaction levels (across most areas of service) which are amongst the top quartile of all councils;
Overall performance improvement across all services at a rate which is significantly better than the average for district councils
3.3The Forum also considered the need to improve further in particular areas and agreed action plans for improvement as follows:
Waste reduction and recycling
Targets for 2010 will be hard to meet even with plans to recycle street waste and glass. The reasons why some residents do not recycle as much as others needs to be researched and campaigns to encourage greater participation need to be developed. Proposals are due by the end of January 2007.
Customer enquiry handling
The proportion of telephone customer enquiries dealt with at the first point of contact (a key principle of the Worcestershire Hub) has dropped slightly as the number and range of services handled by the Customer Contact Centre has increased. An analysis of customers, service types and other factors affecting this performance will be undertaken by the end of January 2007 as a basis for proposals for improvement in customer service.
Concessionary fares
While the uptake has been strong, there is an increasing cost to the council to support concessionary fares. An assessment of the impact of
Page 2 Report No: EC828 current and future concessionary fares schemes on the council’s transport priority and costs will be undertaken.
Planning applications and appeals
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EC828: Quarterly Corporate Performance ReportReport | 4 pages | DownloadRead as text |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.