RESOLVED that (i) progress with the projects be noted; and (ii) approval be given for this Council to enter into the necessary partnership agreements upon terms to be finally agreed by the Head of Customer and Environmental Services and Head of Legal Services in consultation with the Portfolio Holder for Strategic Leadership.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Ward: Tenbury / Upton & Hanley Portfolio Holder: Cllr Di Rayner Executive Committee 20th March 2007
Report of Head of Customer and Environmental Services Tenbury and Upton Customer Service Centres
1. Purpose of Report 1.1 This report provides Members with an update on progress with the projects to provide Customer Service Centres at Tenbury and Upton and seeks authority to enter into the necessary formal agreements with partners.
Recommendation that -
(i) progress with the projects be noted; and (ii) approval be given for this Council enter into the necessary partnership agreements upon terms to be finally agreed by the Head of Customer and Environmental Services and Head of Legal Services in consultation with the Portfolio Holder for Strategic Leadership
2. Background 2.1 In 2003, this Council entered into a partnership agreement to become a member of the Worcestershire Hub (report EC320 refers). This innovative approach has led to the delivery of this Council’s customer facing services through the establishment of the Malvern Customer Service Centre based in the Malvern Library (part of the wider Hub network) and our improved web presence via the Hub portal.
2.2When the Hub vision was developed in 2003, local service centres at Tenbury and Upton were also seen as key projects. Due to issues around scope and affordability of the wider Hub project, the partnership agreement entered into in 2003 was cast in specific terms and did not expressly provide for the provision and operation of the service centres at Tenbury and Upton. Accordingly authority is required to conclude appropriate arrangements.
2.3To progress these projects, Council has approved a capital budget of £294,500 together with additional provision of baseline revenue funding to cover the necessary operating costs.
3. Project Progress 3.1 Following initial work with partners (including West Mercia Police in relation to Upton) a Project Board was established in late 2006 to oversee the progress of both customer service centre projects. PRINCE 2 project management Page 1 Report No: EC852 methodology is being utilised in line with this Council’s approach to major project delivery. Detailed project plans are in place which include for temporary relocation of the Tenbury Library to the Pump Rooms during building works. Detailed risk logs are in place for both projects.
3.2Detailed schemes for both centres have been developed and agreed by the partners that will provide a joint use service desk in each library to enable customer enquiries to be dealt with at a single point. Both schemes include the provision of private interview rooms for dealing with more sensitive matters. Both schemes have been the subject of local consultation with the public and interested parties. This has generated useful feedback enabling refinement on a number of points of detail. Copies of each scheme are available for inspection in the Members Room.
3.3Planning consent was given for the scheme at Upton during February. Due to representations being made, it is necessary for the Tenbury scheme to be considered by the County Council Planning Committee and this will take place at its March meeting. The matters subject to representation are being addressed through discussions with the party concerned.
3.4At the time of writing, receipt of tenders for the Tenbury scheme is awaited. Subject to these being within the budgetary provision of the partners and conclusion of the partnership agreement, it is anticipated that work could begin on site during April 2007 with completion during July.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.