Internal Audit Plan 2007-08 - 2nd Quarter Report

Agreed Finance 4 papers

Audit Committee - For later meetings please search for Audit and Standards Committee agreed this item on Tuesday 30 October 2007. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

It was agreed that a schedule of how frequently roads were swept would be useful information for the members of the Committee to receive. RESOLVED that the report be noted.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Audit Committee - For later meetings please search for Audit and Standards Committee, 4 pages

Audit Committee

30th October 2007 Report of the Chief Internal Auditor

Internal Audit (IA) 2007-08 Plan – Position at 30th September 2007 (i.e. at end of second quarter).

1. Purpose of Report 1.1 To provide an update of Internal Audit’s progress towards meeting its objectives as set out in the audit plan for 2007/2008 as approved by the Audit Committee on 23rd April 2007.

Recommendation: that the report is noted

2. Introduction This is the third year of the arrangement that Malvern Hills District Council (MHDC) has with Worcester City Council (WCC) for the provision of its Internal Audit function. The initial 3-year contract for Internal Audit Services is coming to an end in March 2008, and the opportunity is being taken to review the terms and conditions of the contract. Negotiation is taking place and Worcester City hope to continue providing the service; therefore no major disruption to the service is anticipated.

This report updates the committee on the position at the end of the second quarter of the current year in terms of resources used and audit work completed; it also informs the committee on work in progress and / or completed during the third quarter to date.

3. Report 3.1 Inputs

A summary of the position at 30th September 2007 is provided at Appendix 1.

3.2Outputs

During 2007/08 Internal Audit are required to:

(a) report on 17 full systems audits, of which 9 must suitably assist the External Auditor reach their “opinion” (systems audits are primarily intended to be constructive attempts to improve the control and risk management environment leading to more effective outputs/outcomes); Page 1 Report No AC33 (b) provide sufficient audit resources for other operational areas which assist the Council to maintain and/or improve its control systems and risk management processes or implement/reinforce its oversight of such systems. Other operational areas consist of:-

carrying out certain health check audits in areas which are not due for a detailed systems audit in the year but nonetheless audit experience has shown need some attention each year to ensure that controls continue to operate properly – e.g. cash receipting points, petty cash accounts;

providing an on-going consultancy to managers on internal control, e.g. where system changes are being made;

carrying out investigations into any suspected instances of fraud and follow up fraud intelligence reports; and

follow-up recommendations from previous audit reports.

All of the above work will be performed by the Worcester City Council Internal Audit team in accordance with the agreed principles and methodology.

3.3Systems Audits

During the second quarter to 30 September 2007 and third quarter to date, 5 audits relating to 2007 / 2008 were completed and 1 relating to 2006 / 2007. Summary details of 3 of these are provided at Appendix 2, and also a list of work in progress.

3.4Other Operational Work

Internal Audit has had two investigations referred to them and work has been completed on both of them; this has been in addition to the normal audit programme.

During the first quarter an assurance methodology was developed and has been incorporated into our audits for 2007 /2008; this continues to be used and a table can be found at Appendix 3.

A formal follow–up to audit reports is being introduced for 2007 / 2008 and is due to start in November 2007, this being six months after the issue of the first audit report for 2007 / 2008.

3.5Work in support of the External Auditor

Nine of the systems audits will be of direct interest to the external auditor. As audit reports are completed they have been automatically passed to the external auditor. It is our understanding that external audit have been able to use our work to the extent that they are allowed and as reported in our 2006 / 2007 end of year report to this committee they gave a good opinion of IA in their Annual Audit and Inspection letter.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AC33 APPENDIX 1Appendix 1 pages Download
PDF
AC33 APPENDIX 3Appendix 1 pages Download
PDF
AC33 APPENDIX2Appendix 4 pages Download
PDF
Internal Audit Plan 2007-08: 2nd Quarter ReportReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Malvern Hills

Search all
  1. Internal Audit Plan 2007-08 - 2nd Quarter ReportThis decision
  2. Audit Reports - InternalApproved
  3. Annual Report of Internal Audit 2024/25 including Audit OpinionNoted
  4. Draft Internal Audit Plan 2025/26Approved
  5. Internal Audit Progress Report 2024/25Noted
  6. Internal Audit Update ReportNoted

More from Malvern Hills Audit Committee - For later meetings please search for Audit and Standards Committee

All decisions
MeetingDecisionOutcome
28 Feb 2019 Certification of Claims and Returns Annual Report 2017-18that the external auditors report on Certification Work for the year ended 31 March 2018 be accepted and the level of... Noted Open
28 Feb 2019 Audit Planning Reportthat the external auditors report on the Audit Plan for year ending 31 March 2019, be accepted. Decided Open
28 Feb 2019 Internal Audit Progress Reportthat the report, be noted. Noted Open
28 Feb 2019 Draft Internal Audit Plan 2019-20that the Internal Audit Annual Plan and Key Performance Indicators for 2019-20, be approved. Approved Open
18 Oct 2018 Confirmation of Minutes of Previous Meetingthat the minutes of the meeting held on 19 July 2018 be confirmed and signed by the Chairman as a true and correct re... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies