EC919 - Performance Related Pay (PRP) Scheme

Approved Executive 1 paper

Executive Committee approved this item on Tuesday 27 November 2007. Below is the council's own wording, with the papers it was decided on.

Item93

Resolved

RESOLVED that (i) the principle of developing and implementing a scheme linking pay advancement for Chief Executive and Heads of Service to performance, be formally approved; and (ii) delegated authority be granted to the Human Resources Manager to finalise the detail of any such scheme following the completion of a consultation process, in consultation with the Leader of the Council; the Portfolio Holder for Human Resources and the Portfolio Holder for Finance & Resources, before submitting the scheme to the Executive Committee for formal approval.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 3 pages

Ward: All Portfolio Holder: Councillor Paul Cumming Executive Committee 27th November 2007

Report of Human Resources Manager Performance Related Pay (PRP) Scheme

1. Purpose of Report 1.1 To consider the development and implementation of a Performance Related Pay (PRP) Scheme for Chief Executive and Head of Service positions.

Recommendations that -

(i) the principle of developing and implementing a Performance Related Pay (PRP) Scheme for Chief Executive and Heads of Service is formally approved; and (ii) delegated authority be granted to the Human Resources Manager to finalise the detail of any such scheme following the completion of a consultation process, in consultation with the Leader of the Council; the Portfolio Holder for Human Resources and the Portfolio Holder for Finance & Resources.

2. Background/Introduction 2.1 Council resolved at its meeting on 20th March 2007 to grant the Chief Executive, in consultation with the Group Leaders, authority to complete a selection process to recruit to the new Heads of Service posts, from amongst the existing Heads of Service in the first instance, to enable the new structure to be in place at the earliest practicable date. Subsequently in accordance with the authority delegated to them, the Chief Executive in consultation with the three Group Leaders, new pay boundaries were created with the intention of developing a performance related pay scheme. Following the successful appointments to the new Head of Service positions the need to develop and implement such a scheme remains.

2.2Any scheme developed and subsequently implemented would be developed from best practice in other Local Authorities as well as ensuring that any assessment of performance was on an annual basis and against the Council’s priorities.

2.3By introducing a performance related pay scheme, the Council will be ahead of most other councils in England and certainly across Worcestershire. For example the current gradings for senior management in Malvern Hills are mostly comparable with those in the other South Worcestershire Districts. However the remuneration of senior managers in these other Districts is not Page 1 Report No: EC919 related to performance and is generally on the basis of advancement by annual increments.

2.4Formal consultation with those staff affected and Trade Unions is now underway.

3. Corporate Considerations Resource Implications: All such PRP awards will be funded from within existing (Identify Financial, Legal, Property budgets. and Personnel issues)

Policy Implications: Directly linked to the Senior Management Review and (Identify how proposals link to will assist in delivery against the Council’s objective for Council priorities and the current policy framework, and if they do ‘first class, good value services and facilities’ and help to not, identify implications) deliver the priority for action of ‘managing our performance’.

Existing contracts of employment allow for the implementation of such a Scheme

Equalities Issues: None (Identify potential human rights issues and any impact on grounds of race, gender, disabilities, age, sexual orientation and religious belief)

4. Risk Management Risk Identified Inherent Risk Proposed measures Residual Risk Evaluation Evaluation

 Potential legal challenge of Risk Score 5  Implementation of PRP Risk Score 3 not fulfilling contractual Scheme obligations to develop performance framework

 Performance of Senior Risk Score 8  Implementation of PRP Risk Score 6 Managers insufficiently Scheme managed to deliver Council’s objectives and priorities.

NB: Risk Score derived from level of Impact and Likelihood, calculated from the Guide to Report Writing

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EC919: Performance Related Pay (PRP) SchemeReport 3 pages DownloadRead as text

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open
15 Sep 2026 Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies