RESOLVED that – (i) in future, in order to ensure that the Overview and Scrutiny Committee can make a full and meaningful contribution to the development of the three-year financial strategy, it be given full details of all the assumptions on which it is based and, in particular, details of proposed budget reductions; (ii) a briefing report on the current procedures for delivering Disabled Facilities Grants be provided by the Head of Planning and Housing. Council considered the recommendation of Executive Committee of 18 th December 2007, in respect of the Medium Term Financial Plan. RESOLVED that the updated three-year Medium Term Financial Plan from 2008/09 to 2010/11, be approved.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Ward: All Portfolio Holder: Cllr R Madden Executive Committee 18th December 2007
Report of the Head of Finance & Resources Medium Term Financial Plan
1. Purpose of Report 1.1 To review the Council’s medium-term financial plan for recommendation to the Council for adoption.
Recommendation that the proposals for the three years from 2008/09 to 2010/11 be recommended to the Council as the Council’s updated Medium Term Financial Plan.
2. Background 2.1 The Council’s medium-term financial plan provides the framework within which revenue and capital spending decisions can be made over a three-year period, on the basis that the plan is reviewed and updated annually to take into account changing circumstances
2.2The revised revenue and capital budgets for 2007/08 were approved by the Council following the Budget Review process on 18th September 2007.
2.3This report updates the previously approved medium term plan, rolling it forward by a further twelve months to 2010/11, reflecting changes in circumstances and policy decisions taken by the Council, as well as updating the plan for additional known commitments or savings.
2.4Once the Council has approved the overall financial ‘envelope’ for the coming three years, this revised plan will provide a framework within which to prepare the detailed budget proposals for 2008/09 and beyond. Any final changes to the assumptions made in this plan will be assessed, and action can be taken on the basis of a considered strategic approach.
3. Revenue Budget Assumptions and Underlying Principles 3.1 The proposed expenditure and funding levels for the three years from 2008-09 to 2010-11 are set out at Appendix A. The principles underpinning the proposed strategy are:
a. A balanced budget, with no use of balances to meet recurring baseline spending, building the general fund balance to a level between £1m and £1.25million.
Page 1 Report No: EC926 b. Year on year savings targets of at least 5% to be met by ongoing efficiencies and permanent budget reductions.
c. Where possible, additional investment and spending decisions will be made to reflect council priorities, and with disinvestment and budget savings made in non-priority areas.
d. Council tax increases are kept as low as possible with the long term aim of annual increases pegged below inflation.
3.2The following assumptions have been made:
a. Employees’ pay awards will be 2.5% per year for each of the coming three years.
b. Fuel, energy and utility costs will increase by 5% each year. c. Other cost increases will generally be at 2% per year.
d. Employer’s pension fund contributions will increase from 13.8% in the current financial year to 15.9% from April 2008, 18.0% from April 2009 and 20.1% from April 2010. e. Income from fees and charges will increase by 2.5% for each of the next three years. f. Interest rates will be within the range from 5.25% to 5.75% over the three- year period.
g. Expenditure in the current year will be in line with the most recent projections reported to Executive Committee in November 2007.
h. An assumed annual increase in the council tax base of 0.5%.
3.3Appendix A details the build-up of the revenue budget in each of the financial years of the medium term plan, with a further description of key elements below.
4. Increases to the Revenue Budget Pay and prices Increases
4.1In addition to an estimated annual increase of 2.5% to reflect employee pay awards, provision has also been made to meet the ongoing additional increases required to the employer’s contribution to the pension fund. This is part of the council’s ongoing strategy to achieve 100% funding over a 25-year period.
4.2The pension fund is subject to a triennial actuarial valuation, the most recent of which has just been undertaken by Mercers Ltd, on behalf of Worcestershire County Council, the pension fund administrator.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.