RESOLVED that (i) the BWB Stage 2 report of the Malvern Hills Flood Study be noted and adopted as the basis for prioritising action in relation to flooding from non-fluvial sources; (ii) the proposals for implementing the recommendations in the BWB report be adopted; (iii) funding for implementation be from the earmarked reserve for flood alleviation, authority for expenditure be delegated to the Head of Customer and Environmental Services except that expenditure in relation to works on “orphan land” and consideration of loans be subject to consultation with the relevant Portfolio Holders and following discussion with the relevant ward members; and (iv) a precis of the two BWB reports be produced and be published on the Council’s website.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Malvern Hills District Council Flood Study Stage 2 Report April 2009 BMW/173/MFSS2/REVC
EXECUTIVE SUMMARY This Stage 2 report has been produced on behalf of Malvern Hills District Council (MHDC) in respect of the Malvern Hills District Flood Study. The findings of this report are based on further investigation into the recommendations identified as part of the Stage 1 process and are an initial review into the possible flood alleviation options that may be feasible for MHDC to undertake, subject to site specific detailed investigation.
The high priority areas were visited as part of a site walkover assessment process to quality assure the findings of the parish council survey and Stage 1 flood study and confirm the source of flooding and direction of flood flows. Within the 19 high priority sites, differing flooding mechanisms have been identified within each of these locations from the July 2007 flood event.
The site assessment process has raised a number of sites within the high priority areas brought forward to the Stage 2 process that MHDC could further investigate as the drainage authority for dealing with specific flooding issues. The areas identified are Callow End, Corse Lawn, Eardiston, Elgar Avenue (Great Malvern), Lower Howsell Road area (Great Malvern), Holt Heath, Kerswell Green, Naunton, Shrawley, Suckley (Woodlands Road), Tenbury Wells, The Grove at Ryall, Willow Grange and Lake Farm/Drake Street (Welland).
It is recommended in the first instance that private home owners consider defending their properties from flooding with flood resilience measures in accordance with the recommendations of the Pitt Review, (2008) which Malvern Hills District Council supports.
The results of the catchment hydrology and theoretical culvert capacity calculations undertaken as part of the study show that the majority of the bridge/culvert structures that could cause an obstruction to flood flows present at eight of the high priority sites, actually appear in principle to have sufficient capacity to convey flood flows generated in the theoretical 100-year design return period event. The culverts that appear undersized in terms of capacity based on the calculations carried out are at Callow End, Elgar Avenue in Great Malvern and the Marlbank Brook road culvert (A4104) on Drake Street in Welland.
It should be noted that this report forms part of a study, which is considered to be an ongoing process that may be updated in the future by Malvern Hills District Council. This may be through in depth analysis at the different site locations should individual flood risk reduction schemes be promoted to a design stage or if alternative flood alleviation options are identified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.