RESOLVED that (i) the timetable adjustment to the Local Development Scheme of nine months as set out in Appendix 1 to report C260 for submission to the Government Office for the West Midlands, be approved, with the proviso that this may be adjusted for a further 3 months if additional time is required to ensure a robust and sound strategy is developed for the submission version of the South Worcestershire Joint Core Strategy; and (ii) delegated authority be given to the Head of Planning and Housing in consultation with the portfolio holder for Planning to make any consequential amendments to the text of the Local Development Scheme and any other necessary adjustments arising from the views of the Government Office f or the West Midlands views on the adjusted timetable . The following Councillors abstained from the vote on the above resolution and requested that their abstentions be noted: D. Clarke [name removed].R. Myatt J.W. Raine B. J. M. Pilcher D. G. C. Hull (personal interest) T.A.L. Wells [name removed]
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
8th September 2009 Report of Head of Planning and Housing Services
Adjustment to Local Development Scheme for Malvern Hills District 2009 – 2012
1. Purpose of Report 1.1 The purpose of this report is to seek Council approval of recommended changes the current Local Development Scheme (LDS) for the period up to 2012.
Recommendation that -
(i) the Council approves the timetable adjustment to the Local Development Scheme as set out in Appendix 1 for submission to the Government Office for the West Midlands; and
(ii) delegated Authority be given the Head of Planning and Housing in consultation with the portfolio holder for Planning to make any consequential amendments to the text of the Local Development Scheme and any other necessary adjustments arising from the views of the Government Office for the West Midlands views on the adjusted timetable.
2. Background 2.1 Local Development Schemes (LDS) are a statutory part of the planning process introduced by the Planning and Compensation Act (2004). A LDS sets out a three year rolling programme of planning policy work. Progress with a LDS is set out in an Annual Monitoring Report (AMR) which is submitted to GOWM every December. The Government advises local authorities to monitor and publish progress with their LDS in real time on their websites.
2.2The LDS has been already subject to several revisions which have been driven by operational considerations and changes in the relevant legislation.
2.3The current LDS was considered by the Planning Committee on 2nd December 2008 (minute ref. 20 refers) and approved by Council on 9th December 2008 (minute ref. 145 refers).
Page 1 Report No: C260 2.4 The LDS was formally submitted to GOWM. The revisions to the LDS approved by this Council were mirrored by changes made by Worcester City and Wychavon Councils.
2.5In order to meet the timeframe set out in the current LDS the draft SWJCS ("Pre-Submission" (to Secretary of State)) was scheduled to be considered by Members in November 2009. However, for the reasons set out below however a nine month timetable adjustment is now recommended.
2.6The South Worcestershire Joint Advisory Panel considered the need to adjust the LDS on 10th July 2009, at which time the Panel recommended to the three South Worcestershire Councils an adjustment of six months. However, following on from the meeting of the Panel, officers have undertaken a more detailed assessment of the adjustment and consider a further 3 months will be required to meet operational and organisational demands.
2.7As for all Core Strategies (CS) the SWJCS will have to meet the Planning Inspectorate's "Tests of Soundness" at an Examination in Public. One of these tests is whether a CS is founded on a robust and credible evidence base. Whilst the SWJCS' evidence base is already extensive it is considered that it needs to be more comprehensive to minimise the risk of the 'plan' being found "unsound" i.e. rejected by an independent inspector. Given the financial investment being made by the three Councils and the importance of delivering a sound plan in 2011 it is considered a significant risk to not achieve a comprehensive evidence base. The specific areas which require additional work include the following.
2.8Transportation - Whilst the evidence base for the Worcester area is reasonably comprehensive the County Council will not be formally considering the Worcester Transportation Strategy and validating the revised SATURN model until the Autumn this year. The outcome of this work is fundamental to the strategy for Worcester. Furthermore similar levels of evidence are not yet available for the other main settlements. A draft study has been produced by Worcestershire County Council for Malvern town but draft studies for the remaining towns are not anticipated until at least September. Following this there may need to be subsequent revisions to take on board officer.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.