RESOLVED that: i. Quarterly Performance Reports for Disabled Facilities Grants be made to the Executive Committee ii. Copies of those Quarterly Performance Reports be presented to Overview and Scrutiny Committee in order to monitor progress.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Report to Overview and Scrutiny Committee, 3 pages
Ward: All
Portfolio Holder: Cllr David Hughes Overview & Scrutiny Committee
8th February 2011 Disabled Facilities Grants – Update
Report of Head of Community and Economic Development 1. Purpose of Report 1.1 The Committee has requested a comprehensive report on the time taken to process grant applications and the status of current spend.
Recommendation that -
(i) The Committee note the progress made in committing expenditure against the current year’s budget and the updated waiting list position
2. Background/Introduction 2.1 The total budget available in 2010/11 to fund mandatory Disabled Facilities Grants (DFGs) and discretionary Home Repair Grants (HRGs) is £312,500.
2.2The work to determine grant funding and deliver the agreed contracts is now being carried by the Worcestershire Care and Repair (WCR) (formerly known as the Homes Improvement Agency HIA).
2.3WCR take a more holistic view of the issues people are encountering rather than just processing grant funding. In the first six months of operation initial figures show that 24 people have been helped to find solutions other than grant funding.
2.4The aim is to make sure that people can continue to live as independently as possible within their own homes.
3. Categorisation of Grant Funding. 3.1 Until April 2010 applicants were assessed on a first come first service basis regardless of the how acute the need. This changed in April 2010 changed to reflect the need of the applicant and to better target the resources. On referral by the Occupational Therapist, new enquiries are prioritised as Category 1 (highest), 2 or 3. These are outlined below.
Page 1 Report No: 4. Composition of the waiting list for DFGs 4.1 At end of December 2010 there were
(a) 95 enquiries on the waiting list still awaiting a referral to Care & Repair:
(b) 25 Pending visits by WCR
(c) 32 awaiting approval or additional information.
(d) 21 approved but not completed.
5. Grant Expenditure. 5.1 Actual spend to end December was £143,495.47. After allowing for committed schemes not yet paid (circa 86k) the amount of the budget remaining available for allocation at the end of December 2010 was £82,626.12. This allocation will be committed by the end of the financial year.
Page 2 Report No: 6. Waiting Times. 6.1 This schedule at appendix 1 provides a snapshot of timescales achieved in respect of projects where grants were completed in the year to date.
6.2For the 21 grants completed during the 9 months to December 2010, the median elapsed time from enquiry to approval was 61weeks prior to joining WCR and 37 weeks after joining. From approval to completion the time has improved from 32 weeks to 12 weeks.
6.3Another 21 grants are not yet completed, but work is in progress; for these projects, the elapsed time from enquiry to approval was 53 weeks prior to joining as opposed to 16 weeks after joining.
7. Conclusions 7.1 The evidence suggests that typical waiting times are improving considerably particularly for category 1 cases. Unfortunately as these are now prioritised this means that the time elapsed for non category 1 cases is rising although our statistics for these cases are not accurate or complete enough to provide for committee as yet.
7.2Waiting lists are also growing and consequently the funding required is also increasing and correspondingly the resources needed to assess and process applications within the budgets and funding available.
7.3The Council through its contract with Worcestershire Care and Repair has improved capacity and resilience and is attempting to find more resources and other solutions to offset cost and focus on outcomes rather than issuing of grants. Further reports will be available after the next monitoring meeting on 16th February.
Lee Robson
Head of Community and Economic Development
Page 3 Report No:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Overview & Scrutiny Work ProgrammeIt was agreed that the position would be kept under review, with a special meeting to be convened should any signific...
Overview & Scrutiny Work ProgrammeIt was agreed that this could be discussed at an upcoming O&S meeting as an agenda item and would be added to the Wor...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.