RESOLVED that (i) electric vehicle charging points be installed on designated bays on selected long term car parks in the District; (ii) the Head of Customer and Environmental Services be authorised to procure the necessary equipment taking advantage of arrangements negotiated by other local authorities and obtain grant assistance from the Central Technology Belt; and (iii) setting the tariff and venue for electric vehicle charging bays and parking arrangements be delegated to the Head of Customer and Environmental Services in consultation with the relevant Portfolio Holders.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Ward: All Portfolio Holder: Cllr Mrs B Behan Executive Committee
15th February 2011
Report of Head of Customer & Environmental Services
”Plugged-in Places” – Installation of electric vehicle charging points
1. Purpose of Report 1.1 To seek approval to install electric vehicle charging points on the Council’s car parks as part of the national Plugged-in Places initiative.
Recommendation that -
(i) electric vehicle charging points are installed on designated bays on selected long term car parks in the District; (ii) the Head of Customer and Environmental Services is authorised to procure the necessary equipment taking advantage of arrangements negotiated by other local authorities and obtain grant assistance from the Central Technology Belt; and (iii) setting the tariff for electric vehicle charging bays and parking arrangements is delegated to the Head of Customer and Environmental Services in consultation with the relevant Portfolio Holders
2. Background 2.1 In December 2010 Government announced that the Midlands had been selected as one of eight UK “Plugged-in Places” to lead on electric vehicle infrastructure deployment. Led by Cenex, the UK’s first Centre for Excellence for Low Carbon and Fuel Cell technologies, a consortium of Midlands businesses and local authorities has secured £2.9 million of funding from Government to support a £6.3 million programme to install more than 500 charging posts in high profile locations. By encouraging the early adoption of low carbon and fuel cell technologies in automotive applications the aim is to assist the UK automotive supply chain to compete in global markets. The Society of Motor Manufacturers and Traders have produced a guide to electric cars containing frequently asked questions and answers which is available in the Members Room or can be downloaded from the SMMT website at www.smmt.co.uk .
2.2The Midlands Plugged-in Places project will be managed by Cenex and Central Technology Belt and has over 50 participants. These include the Council, Malvern Hills Science Park and Worcestershire County Council, all of whom submitted letter of support and initial expressions of interest last Autumn.
Page 1 Report No: EC1088 2.3 The first phase of the project (2011 to 2013) will see charging posts deployed in three areas:
(a) West Midlands: Coventry, Birmingham, Worcester and Malvern
(b) East Midlands: Leicester, Nottingham and Derby
(c) East Midlands: Corby and Northampton
2.4The inclusion of Malvern in the first phase, as part of the Central Technology Belt is extremely positive and reflects the importance of CTB and Malvern to this rapidly evolving technology. Locally there will be charging points at Malvern Hills Science Park and Worcester University enabling electric car journeys to be made along the length of the CTB. Installation of charging posts in Great Malvern will allow electric car users to fully access the town’s facilities, including the rail network and hills. It will also place Malvern Hills on the map for the anticipated rapid growth in the electric car market.
3. Proposed Installations 3.1 It is proposed to install 3kW multiple trickle charging posts on selected long stay car parks. Each post is capable of charging up to four vehicles. This type of charger is suitable for recharging all the electric vehicles currently on the market and those expected shortly. They are capable of delivering a full charge in around 8 hours and a useful top up in significantly less. Each post costs around £4,000 installed.
3.2Long stay car parks are identified as most suitable for the installation of charging points because of the charging duration required and the need to designate bays for this purpose. The typical level of daily usage also means that dedicated charging bays will not impact on the availability of parking spaces. In our initial expression of interest we indicated installing up to 4 such posts on each car park (total capacity up to 32 cars).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.