Internal Audit Plan - 2010/2011 Annual Report

Noted Finance 5 papers

Audit Committee - For later meetings please search for Audit and Standards Committee noted this item on Wednesday 27 July 2011. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED that the report be noted.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Audit Committee - For later meetings please search for Audit and Standards Committee, 5 pages

Ward: All Portfolio Holder: Cllr P Cumming Audit Committee 27th July 2011

Report of Acting Service Manager – Worcestershire Internal Audit Shared Service

Internal Audit Plan – 2010/2011 Annual Report 1. Purpose of Report 1.1 To provide the overall results in terms of meeting Internal Audit's (IA's) objectives as set out in the internal audit plan for 2010 / 2011, provide an overall audit opinion and give a more detailed account of the work performed in the last quarter of the year.

Recommendation that -

(i) The Report is Noted

2. Background/Introduction 2.1 The IA plan was approved by the Audit Committee on the18th March 2010. This report summarises the work of IA throughout 2010/2011, and also updates the committee on the progress of IA's work in the last quarter of the year. The plan was updated during the year and a revised version was approved by Audit Committee on the 27th January 2011.

3. Report 3.1 Inputs

A summary of the position at 31st March 2011 is provided at Appendix 1.

3.2Outputs

During 2010/11 Internal Audit was required to:

(a) report on 17 full systems audits including health checks of which five must suitably assist the External Auditor reach their “opinion” (systems audits are primarily intended to be constructive attempts to improve the control and risk management environment leading to more effective outputs/outcomes); (b) provide sufficient audit resources for other operational areas which assist the Council to maintain and/or improve its control systems and risk management processes or implement/reinforce its oversight of such systems.

Page 1 Report No: Other operational areas consist of:-

• carrying out certain health check audits in areas which are not due for a detailed systems audit in the year but nonetheless audit experience has shown need some attention each year to ensure that controls continue to operate properly – for example procurement, risk register, petty cash accounts;

• providing an on-going consultancy to managers on internal control, for example where system changes are being made;

• carrying out investigations into any suspected instances of fraud and follow up fraud intelligence reports; and

• follow-up any significant outstanding matters from previous audit reports.

All of the above work was performed by the Worcester City Council Internal Audit team during April and May 2010 and Worcestershire Internal Audit Shared Service Internal Audit Team for the remainder of the 2010 / 11 financial year in accordance with the agreed principles and methodology. Consequently, taking all the operational areas together the final number of audit report outputs for the year was 17.

3.3Systems Audits

During the first quarter to 30 June 2010 and second quarter to the date of Audit committee, 3 audits relating to 2010 / 2011 and 1 Health Check were completed and details of these audits were reported to the Audit Committee on 23rd September 2010.

During the second quarter to 30 September 2010 and third quarter to the date of Audit Committee, 5 audits relating to 2010 / 2011 plan were completed and details of these audits were reported to the Audit Committee on 27th January 2011.

During the third quarter to 31 December 2010 and fourth quarter to the date of Audit Committee, 1 audit relating to 2010 / 2011 was completed and details of this audit was reported to the Audit Committee on 17th March 2011.

During the fourth quarter to 31 March 2011 a further 4 audits were completed. Details of these audits are provided at Appendix 2. The remainder of the audits have been completed and two final reports have been issued, one of which is included in Appendix 2. The final two are nearing completion awaiting management comment.

89% of the 2010/2011 plan has been achieved with a productivity rate of 81% as reported at Appendix 1. Summary details are based on the revised audit plan.

3.4Other Operational Work

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Appendix 2Appendix 2 6 pages Download
PDF
Appendix 3Appendix 3 1 pages Download
PDF
Appendix 4Appendix 4 2 pages Download
PDF
Internal Audit Plan: 2010/2011 Annual ReportReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Malvern Hills

Search all
  1. Internal Audit Plan - 2010/2011 Annual ReportThis decision
  2. Audit Reports - InternalApproved
  3. Annual Report of Internal Audit 2024/25 including Audit OpinionNoted
  4. Draft Internal Audit Plan 2025/26Approved
  5. Internal Audit Progress Report 2024/25Noted
  6. Internal Audit Update ReportNoted

More from Malvern Hills Audit Committee - For later meetings please search for Audit and Standards Committee

All decisions
MeetingDecisionOutcome
28 Feb 2019 Certification of Claims and Returns Annual Report 2017-18that the external auditors report on Certification Work for the year ended 31 March 2018 be accepted and the level of... Noted Open
28 Feb 2019 Audit Planning Reportthat the external auditors report on the Audit Plan for year ending 31 March 2019, be accepted. Decided Open
28 Feb 2019 Internal Audit Progress Reportthat the report, be noted. Noted Open
28 Feb 2019 Draft Internal Audit Plan 2019-20that the Internal Audit Annual Plan and Key Performance Indicators for 2019-20, be approved. Approved Open
18 Oct 2018 Confirmation of Minutes of Previous Meetingthat the minutes of the meeting held on 19 July 2018 be confirmed and signed by the Chairman as a true and correct re... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies