CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Malvern Hills District Council
Executive Committee, Tuesday 24 July 2012 at 5.00pm

Heritage Lottery Fund application for Route to the Hills Project - EC1163

Approved Executive 1 paper

Executive Committee approved this item on Tuesday 24 July 2012. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

RESOLVED that (i) the Council acts as lead applicant on behalf of the Route to the Hills Board, to apply for funding from the Heritage Lottery Fund; and (ii) authority to approve and submit the funding application be delegated to the Head of Community Services in consultation with the Portfolio Holder for Economic Development and the Route to the Hills Board.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 5 pages

Ward: Priory Portfolio Holder: Cllr P Grove Executive Committee

24th July 2012

Report of Head of Community Services

Heritage Lottery Fund application for Route to the Hills Project

1. Purpose of Report 1.1 To seek approval for the Council to be the lead applicant, on behalf of the Route the Hills Board, in applying for funding from the Heritage Lottery Fund. If successful, this will result in acceleration of the programme of improvements to public open space, heritage interpretation and signage in Great Malvern.

Recommendation that -

(i) the Council acts, as lead applicant on behalf of the Route to the Hills Board, to apply for funding from the Heritage Lottery Fund; and

(ii) authority to approve and submit the funding application be delegated to the Head of Community Services in consultation with the Portfolio Holder for Economic Development and the Route to the Hills Board.

2. Background 2.1 The Route to the Hills (RTTH) Landscape Development Plan provides a long- term strategic approach to improve and enhance the public open space in the centre of Great Malvern which includes Priory Park and Rose Bank Gardens. In addition, the Plan aims to strengthen the transport links between the town of Great Malvern and the Malvern Hills, thereby maximising the economic and social benefits of the project.

2.2Since October 2010, the Plan has been adopted by six partner organisations who now manage the project collectively through the RTTH Board. The RTTH partner organisations comprise of; Malvern Hills District Council, Malvern Town Council, Malvern Civic Society, High Street Malvern, Malvern Hills Conservators and Great Malvern Priory Parochial Church Council.

2.3The Plan and associated appendices can be viewed by visiting: www.malvernhills.gov.uk/routetothehills

Page 1 Report No: EC1163 2.4 In November 2011, Executive Committee (EC1115) resolved that £25,000 be made available to the RTTH Board to support the delivery of Stage 1 of the RTTH Development Plan.

2.5In January 2012, Council funds were used to commission a team of specialists; Parkin Heritage and Tourism, Andrew Meredith Associates and TACP Ltd. to work with the RTTH Board to create and deliver the Stage 1 Plan, which includes the development of landscape design priorities and an associated funding strategy.

2.6In order to deliver the Stage 1 Plan the Board, with support from the team of specialists, will need to attract funds in the region of £1.4million.

3. Progress with Development of Stage 1 Plan 3.1 Following a comprehensive review of different sources of external funding available to support the project, the specialists have concluded that Heritage Lottery Fund (HLF) is the most appropriate ‘large scale’ funding stream to support the delivery of the RTTH Development Plan.

3.2The HLF offers grants in the region of £100,000 to £5million, for projects addressing its priorities of conservation, participation and learning.

3.3Therefore, in addition to reflecting the Board’s initial priorities of improvements to open space, heritage interpretation and community engagement the specialists have also incorporated the HLF priorities within the Stage 1 Plan. This is to ensure that the project has the best possible chance of attracting the necessary funds.

3.4HLF advisors have acknowledged that Malvern has a significant and largely unrecognised heritage value and have indicated that they would welcome the submission of a funding application from the Route to the Hills Board, aligned to its stated priorities.

3.5As a result of the initial consultation and feedback from HLF advisors, the specialists formally registered an interest in applying for funding in the region of £800,000 through the submission of a pre-application to HLF, on behalf of the Board, in May 2012.

3.6The RTTH Board considered and approved the Stage 1 Plan priorities in April 2012. The Stage 1 Plan and Funding Strategy will be developed, reflecting the HLF priorities, and considered by the Board at its meeting in September 2012.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Heritage Lottery Fund application for Route to the Hills Project: EC1163Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Malvern Hills

Search all
  1. Heritage Lottery Fund application for Route to the Hills Project - EC1163This decision
  2. Release of Funds from Investment in Priorities Earmarked Reserve to Support the Development of Route to the Hills Heritage Lottery Fund Application - EC1115Decided

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open
15 Sep 2026 Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. Approved Open