Resolved

RESOLVED that (i) authority be delegated to the Head of Planning, Economy and Housing, in consultation with the portfolio holders for Housing, to re-commission the Home Improvement Agency (Worcestershire Care and Repair) with effect from 1 st April 2014 onwards; and (ii) the Head of Planning, Economy and Housing to ensure that the recommendations and findings of the Overview and Scrutiny Task and Finish Group regarding HIA re-commissioning (Report to O & S Committee 9 th July 2013 refers) are considered by the partnership in drawing up the detailed service specification.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 5 pages

Ward: All Portfolio Holders: Councillors A Penn / V Myatt Executive Committee

23rd July 2013

Report of Head of Planning, Economy and Housing

Care and Repair Agency Contract re-commissioning

1. Purpose of Report 1.1 The report represents a recommendation to Executive Committee on 28th May 2013 (Report EC1204), proposing the re-commissioning of a joint Home Improvement Agency for Worcestershire.

1.2A decision on the recommendation was deferred on 28th May 2013, to enable to findings of the Overview and Scrutiny Task and Finish Group looking at Disabled Facilities Grants and Support to Older People to report its findings and to assess whether the findings can be incorporated in the proposed re- commissioning process (minute 8 refers).

1.3The Committee may wish to refer to the previous report (EC1204) for background information regarding the operation of the HIA and the timetable for re-commissioning.

Recommendation that –

Authority be delegated to the Head of Planning, Economy and Housing, in consultation with the portfolio holders for Housing, to:

(i) Re-commission the Home Improvement Agency (Worcestershire Care and Repair) with effect from 1st April 2014 onwards.

(ii) The Head of Planning, Economy and Housing to ensure that the recommendations and findings of the Overview and Scrutiny Task and Finish Group regarding HIA re-commissioning (Report to O & S Committee 9th July 2013 refers) are considered by the partnership in drawing up the detailed service specification.

2. Backrgound 2.1 On 28th May 2013 this Committee resolved to extend the current Service Level Agreement between this Council and Festival Housing Limited (Worcestershire Care and Repair) until 31st March 2014. The extension was proposed to enable the end dates of the various Worcestershire District Council contracts with Festival Housing Limited to be aligned and to establish a timetable for joint re-

Page 1 Report No: EC1215 commissioning. Festival Housing was subsequently advised of the wish to extend the current Service Level Agreement and have agreed to the extension.

2.2The Committee however, resolved to defer a decision on joint re- commissioning of the HIA with the other Worcestershire District Councils in the light of the on-going work of the Overview and Scrutiny Task and Finish Group referred to in paragraph 1.2 above.

2.3A meeting was held (19th June 2013) between officers within Housing Services and the Task and Finish Group to consider the then provisional findings and recommendations of the Group.

2.4The meeting concluded that the Housing options services, including DFG administration, should continue to be delivered in an integrated way by a Worcestershire Home Improvement Agency (HIA) or similar organisation, acting in an independent advocacy role. Specifically the proposed re- commissioning presented to this Committee in May 2013 should continue.

2.5The Group’s findings and recommendations considered at Overview and Scrutiny Committee at its meeting on 9th July 2013 fall into three broad categories. Those recommendations aimed at this Council as the housing authority for the district, a number which recommend lobbying of other organisations and those which should be considered as part of the re- commissioning process for the HIA.

2.6The seven recommendations which fall into this latter category can be fed into the process of establishing the detailed service specification for the HIA. Clearly, as the re-commissioning the HIA is a joint procurement process it will be necessary to reach agreement with the partner authorities over their inclusion in their current or possibly amended form.

2.7The recommendations (contained in the Overview and Scrutiny Report dated 9th July) seek to improve and streamline the overall process, develop options and alternatives to formal Disabled Facilities Grants, provide better value for money and efficiencies and integration with other areas of activity such as integration with the work of the Health Authorities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Care and Repair Agency Contract re-commissioning: EC1215Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Malvern Hills

Search all
  1. Care and Repair Agency Contract re-commissioning - EC1215This decision
  2. Care & Repair Worcestershire - Home Improvement Agency re-commissioning - EC1281Agreed
  3. Care and Repair Agency Contract re-commissioning - EC1228Decided
  4. Care & Repair Agency contract re-commissioning - EC1204Agreed

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open
15 Sep 2026 Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies