That the press and public be excluded from this item on the grounds that the business to be transacted would result in disclosure of exempt information as defined in paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972. The Committee considered the joint report of the Head of Community Services and Head of Resources. The report sought the approval of the Committee to the new contractual arrangements for Malvern Splash Leisure Complex, Sport Dyson Perrins Leisure Centre, Sport Martley Leisure Centre and Tenbury Community Pool Ltd. It was confirmed that the changes would result in significant financial savings and reduced repair and maintenance responsibilities for The Council, whilst protecting the jobs of the existing staff at the facilities. The Committee thanked the Community Services Manager and her team for the work they had put into this item. (i) that a contract is let to Freedom Leisure for a period of 15 years for the management and operation of Malvern Splash Leisure Complex, Sport Dyson Perrins Leisure Centre and Sport Martley Leisure Centre commencing from 1 April 2015; (ii) that the council allocates appropriate resources to cover its own responsibilities under this contract, as outlined in section 5 of this report; (iii) that a 5 year grant is awarded to Tenbury Community Pool Limited to support the management and operation of Tenbury Swimming Pool by their chosen operator Freedom Leisure, commencing from 1 April 2015; and (iv) that delegated authority is given to Head of Community Services and Head of Resources, in consultation with the Portfolio Holder with responsibility for Finance and Property and the Portfolio Holder with responsibility for Leisure, to finalise these contract and grant arrangements.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Portfolio Holder: Cllr P Grove and P Cumming Executive Committee
28 October 2014
Report of Head of Community Services and Head of Resources
Award of Contract & Grant Award: Malvern Hills District Leisure Facility Management Contracts
1. Purpose of Report 1.1 To recommend Freedom Leisure as the council‟s preferred bidder for the management and operation of the following leisure facilities: Malvern Splash Leisure Complex; Sport Dyson Perrins Leisure Centre and Sport Martley Leisure Centre.
1.2The council enters into a 15 year contract with Freedom Leisure and allocates appropriate revenue and capital resources to cover its own responsibilities under this contract from 1 April 2015.
1.3To recommend a 5 year grant to Tenbury Community Pool Limited to support the management and operation of Tenbury Swimming Pool by their preferred bidder Freedom Leisure.
The Head of Community Services and the Head of Resources RECOMMENDS:
(i) that a contract is let to Freedom Leisure for a period of 15 years for the management and operation of Malvern Splash Leisure Complex, Sport Dyson Perrins Leisure Centre and Sport Martley Leisure Centre commencing from 1 April 2015; (ii) that the council allocates appropriate resources to cover its own responsibilities under this contract, as outlined in section 5 of this report; (iii) that a 5 year grant is awarded to Tenbury Community Pool Limited to support the management and operation of Tenbury Swimming Pool by their chosen operator Freedom Leisure, commencing from 1 April 2015; and (iv) that delegated authority is given to Head of Community Services and Head of Resources, in consultation with the Portfolio Holder with responsibility for Finance and Property and the Portfolio Holder with responsibility for Leisure, to finalise these contract and grant arrangements.
Page 1 Report No: EC1271 2. Background 2.1 In July 2012, Executive Committee (EC1161) approved the contract alignment of the following leisure facilities: Malvern Splash Leisure Complex; Sport Dyson Perrins Leisure Centre and Sport Martley Leisure Centre until 31 March 2015. Thus providing the council with an opportunity to review its approach to future procurement of management arrangements following completion of its strategic review.
2.2As an outcome of the strategic review, in April 2013, Executive Committee (EC1199) approved the development of a Sport & Leisure Strategy to provide a framework for the future of the district‟s provision including the council‟s role in sport and leisure provision.
2.3In March 2014, Executive Committee (EC1246) approved the Malvern Hills District Sport & Leisure Strategy 2014-2024 entitled „Active Communities Malvern Hills District: A Vision for the Future’. The Committee recognised that the strategy was aimed at supporting sustainable facilities and empowering communities within the constraints of the current financial climate.
2.4The strategy also provided guidance to the council on its approach to leisure facility procurement, which included securing a more sustainable long term future for its community centres. As a result, in July 2014, Executive Committee (EC1260) approved the long term lease of Malvern Vale Community Centre and Upton Hill Community Centre to Worcestershire YMCA.
2.5Tenbury Swimming Pool is owned by the Tenbury Community Pool Limited and was built in 1970‟s following a community fundraising campaign to fund its construction. With council support through an annual grant subsidy, the Company contracts the management of the facility to Sport Leisure Management Limited (SLM). This contract expires on 31 March 2015.
2.6The council, acknowledging the Company‟s inexperience in this area, agreed to manage the procurement process for Tenbury Swimming Pool on behalf of the Company at the council‟s own expense.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.