Resolved
(i) The achievements and improvements in performance be noted; (ii) The strategic issues raised in sections 4.1 - 4.4 be addressed; and (iii) The Committee thanked staff for the outcomes of their efforts.
Executive Committee noted this item on Tuesday 25 November 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) The achievements and improvements in performance be noted; (ii) The strategic issues raised in sections 4.1 - 4.4 be addressed; and (iii) The Committee thanked staff for the outcomes of their efforts.
Executive Committee Tuesday, 25 November 2014
Quarterly Performance Report Relevant Wards All Portfolio Holder Councillor Paul Cumming Author Head of Resources - Andy Baldwin [email protected] Tel: 01684 862236 Contact Officer Finance Manager – Becky Floyd [email protected] Tel: 01684 862315
If you have any queries or questions about the content of this report, the Chairman expects you to speak to the portfolio holder or contact officer in advance of the meeting.
1. Purpose 1.1 To inform the committee of council performance during the first quarter of 2014/15 and advise of the strategic issues and risks facing the council over the next few months.
Recommendation The Head of Resources RECOMMENDS that: (i) The achievements and improvements in performance be noted; (ii) The strategic issues raised in sections 3.1 - 3.5 be addressed; and (iii) Executive Committee thank staff for the outcomes of their efforts.
2. Executive 2.1 The report presents performance and progress on Summary initiatives during quarter 2 as well as presenting an update on strategic issues.
2.2Performance is running at similar levels to the previous year with a few exceptions. There has been an improvement in planning appeals which moves the Council into a slightly safer position regarding delegation, although this is still a very significant risk for the authority. Planning performance generally has improved in comparison to 2013/14 and Q1.
1 Report No. EC? 2.3 Building control applications and income continue to decline in comparison to prior years.
2.4The staff survey was undertaken during Q2, the results of which show some areas of concern – particularly around the relationship between members and staff and the perception of the Council with the general public.
3. Background 3.1 The Performance Management Framework provides for the quarterly review of corporate performance at a strategic level by Portfolio Holders and senior managers.
3.2The latest review was informed by data and progress reports from individual managers and was structured around the council‟s operational performance, highlights of projects and initiatives, and the strategic issues facing the organisation over the next few months. Data contained in this report comes from a variety of independent public sources, the latest Viewpoint Survey and the council‟s own performance management system.
3.3This report covers the six months ending on 30 September 2014.
4. Strategic Issues 4.1 South Worcestershire Development Plan and Risks Work over Q2 focussed on completing the „call for sites‟ exercise and the formulation of recommended Main Modifications to the submitted SWDP. The recommended main modifications only addressed changes to the SWDP required to address the Planning Inspector‟s recommended increase to the Objectively Assessed Housing Need (OAHN) for South Worcestershire (28,370 dwellings). As part of this work the SWDP evidence base has been updated, where necessary, and infrastructure providers have been consulted about the overall increase in proposed housing growth and specific recommended allocations which has resulted in a full update of the Infrastructure Delivery Plan (IDP).
All three councils formally approved proposed modifications to the SWDP on 30th September, following member briefings. A six week consultation period is now underway in Q3 for the public to make comments. Whilst the three Councils have approved the changes for consultation purposes, the consultation is being undertaken whilst the plan remains at the Examination phase and therefore consultation responses will be passed directly to the Inspector. Once the consultation is completed the Inspector will
2 Report No. EC? undertake a second stage of his examination.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Copy of 2014-15 Q2 Performance appendixAppendix | 5 pages | Download |
PDF |
Quarterly Performance Report: EC1284Report | 13 pages | DownloadRead as text |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.