Resolved
i) that the contents of this report be noted; and ii) that the current Service Level Agreement be extended for a further 12 months, on its existing terms, to expire 31 March 2016.
Executive Committee noted this item on Tuesday 24 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
i) that the contents of this report be noted; and ii) that the current Service Level Agreement be extended for a further 12 months, on its existing terms, to expire 31 March 2016.
Executive Committee Tuesday 24 March 2015
Emergency Planning Service Level Agreement Relevant Wards All Portfolio Holder Councillor Phil Grove, Portfolio Holder for Economic Development, Tourism & Leisure and Health & Wellbeing
Author Amanda Smith, Community Services Manager [email protected]
Contact Officer As above If you have any queries or questions about the content of this report, the Chairman expects you to speak to the portfolio holder or contact officer in advance of the meeting.
1. Purpose 1.1 To provide Executive Committee with an update on the Council’s Service Level Agreement arrangements in relation to supporting its Emergency Planning responsibilities.
1.2To agree a 12 month extension on the current Service Level Agreement for Emergency Planning support.
Recommendation The Head of Community Services RECOMMENDS:
i) Executive Committee notes the contents of this report; and
ii) the current Service Level Agreement is extended for a further 12 months, on its existing terms, to expire 31 March 2016.
2. Background 2.1 In 2001, a Service Level Agreement (SLA) was developed between Worcestershire County Council (WCC) and the six Worcestershire district councils to provide greater resilience in the local authorities approach to fulfilling their emergency planning responsibilities.
2.2In April 2011, Bromsgrove and Redditch Councils, along with Wyre Forest District Council, withdrew from WCC’s SLA for Emergency Planning and entered into
1 Report No. EC1296 their own shared service for both Emergency Planning and Business Continuity.
2.3Currently a SLA is in place to provide Emergency Planning advice and assistance to each of the three district councils of South Worcestershire. Advice and assistance is provided by WCC Emergency Planning Unit and the existing agreement expires on 31 March 2015.
2.4Malvern Hills District Council is defined as a Category 1 responder under the terms of the Civil Contingencies Act (2004). Signing the SLA does not divest the Council of its statutory duty as a Category 1 responder.
2.5The key elements of the SLA are as follows:
a) Part 1: WCC Emergency Planning Unit activities in support of the Cabinet Office Expectation and Indicators set, 2008 Document.
b) Part 2: Scope of operational activity delivered by WCC Emergency Planning Unit to the benefit of district councils.
c) Part 3: Scope of operational activity delivered by the district councils.
d) Part 4: SLA 2012 -15 financial arrangements (£15,000 per year per district council).
2.6With the SLA drawing to a close the opportunity has arisen for each district council (or collectively as a group) to consider how it wishes to cover this statutory duty in the future.
3. Community Right 3.1 Following a Localism Act Community Right to to Challenge Bid Challenge expression of interest received from a private resilience agency to provide its Emergency Planning services, WCC carried out a formal appraisal process of its Emergency Planning service with the intention of identifying options for future outsourcing. This process began in April 2013 and formally concluded in October 2014 after only one of three potential bidders met the required business criteria set by WCC. The successful bidder was Herefordshire & Worcestershire Fire & Rescue Service (H&WF&RS). However, H&WF&RS and WCC have agreed to conclude the Right to Challenge process and instead pursue a collaborative rather than a contractual approach to closer working. This could occur under the terms of the Local Government (Goods & Services) Act 1970.
3.2A preliminary discussion has taken place
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Emergency Planning Service Level Agreement: EC1296Report | 4 pages | DownloadRead as text |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.