Internal Audit Progress Report for 2017/18 and residual reporting of 2016/17

Noted Finance 1 paper

Audit Committee - For later meetings please search for Audit and Standards Committee noted this item on Thursday 21 September 2017. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

that the report be noted.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Audit Committee - For later meetings please search for Audit and Standards Committee, 14 pages

Audit Committee Thursday, 21st September 2017

Internal Audit Progress Report for 2017/18 and residual reporting of 2016/17 Relevant Wards All

Portfolio Holder Cllr J O’Donnell

Head of Service Head of Internal Audit Shared Service – Andy Bromage Worcestershire Internal Audit Shared Service Email: [email protected]

Contact Officer As above (If you have any queries or questions about the content of this report, please speak to the portfolio holder or contact officer in advance of the meeting.)

1. Purpose and Summary 1.1 To provide an update of Internal Audit’s progress towards meeting its objectives as set out in the audit plan for 2017/18 as approved by the Audit Committee on 8 March 2017 and report on residual 2016/17 reviews.

2. Recommendations i. The Head of Internal Audit Shared Service RECOMMENDS that the report is noted. 3. Background 3.1 This report updates the committee on the position at the end of August 2017 in terms of resources used and audit work completed. It also informs the committee, for information, on the ‘high’ priority findings and recommendations where appropriate that have been identified as part of the completed audits.

o Much internal audit work is carried out “behind the scenes” and is demand led but is not always the subject of a formal report. Productive audit time is accurately recorded against the service or function as appropriate.

1 Examples include:  Governance, for example, assisting with the Annual Governance Statement  Risk management  Dissemination of information regarding potential fraud cases likely to affect the Council  Drawing managers’ attention to specific audit or risk issues  Audit advice and commentary  Internal audit recommendations: follow up review to analyse progress  Day to day audit support and advice for example control implications, etc.  Networking with audit colleagues in other Councils on professional points of practice  National Fraud Initiative  Transformation o The Council is required under Regulation 5 of the Accounts and Audit Regulations 2015 to “undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance”. o The Worcestershire Internal Audit Shared Service (WIASS) is committed to providing an audit function which conforms to the Public Sector Internal Audit Standards 2013. o We recognise there are other review functions providing other sources of assurance (both internally and externally) over aspects of the Council’s operations. Where possible we will seek to place reliance on such work thus reducing the internal audit coverage as required. o WIASS confirms it acts independently in its role as internal audit. o Audit reports finalised SINCE PREVIOUS PROGRESS REPORTING MEETING 22nd JUNE 2017. 3.2 2017/18 AUDITS IN PROGRESS AS AT 31st AUGUST 2017

The following reviews are at clearance stage:  Corporate - Performance Indicators  ICT Services – General Data Protection Regulations (GDPR) and, work was ongoing in regards to:  Resources - Procurement / Contract Compliance  Resources - Disabled Facilities Grants  Planning (New System) o As work on the above audits is classed as on-going or awaiting a management response a final ‘Assurance’ level will be assigned on completion and the appropriate details of any high priority recommendations reported to the next available Committee.

2 2016/17 AUDIT REVIEW SUMMARY DETAILS  Council Tax o The review found the following areas of the system were working well:  The annual billing process is suitably controlled;  The process for identifying new properties for billing purposes is working effectively;  The process for reconciling Academy system records with payments and the financial ledger;  Performance management arrangements are suitable for the purposes of the service.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Progress Report for 2017/18 and residual reporting of 2016/17Report 14 pages DownloadRead as text

At this meeting

Whole meeting
28Confirmation of Minutes of Previous MeetingDecided 31Statement of Accounts 2016/17Noted
32Internal Audit Progress Report for 2017/18 and residual reporting of 2016/17This decision
33Date of Next MeetingDecided

On this subject at Malvern Hills

Search all
  1. Internal Audit Progress Report for 2017/18 and residual reporting of 2016/17This decision
  2. Audit Reports - InternalApproved
  3. Annual Report of Internal Audit 2024/25 including Audit OpinionNoted
  4. Draft Internal Audit Plan 2025/26Approved
  5. Internal Audit Progress Report 2024/25Noted
  6. Internal Audit Update ReportNoted

More from Malvern Hills Audit Committee - For later meetings please search for Audit and Standards Committee

All decisions
MeetingDecisionOutcome
28 Feb 2019 Certification of Claims and Returns Annual Report 2017-18that the external auditors report on Certification Work for the year ended 31 March 2018 be accepted and the level of... Noted Open
28 Feb 2019 Audit Planning Reportthat the external auditors report on the Audit Plan for year ending 31 March 2019, be accepted. Decided Open
28 Feb 2019 Internal Audit Progress Reportthat the report, be noted. Noted Open
28 Feb 2019 Draft Internal Audit Plan 2019-20that the Internal Audit Annual Plan and Key Performance Indicators for 2019-20, be approved. Approved Open
18 Oct 2018 Confirmation of Minutes of Previous Meetingthat the minutes of the meeting held on 19 July 2018 be confirmed and signed by the Chairman as a true and correct re... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies