Southern Area Planning Committee deferred this item on Wednesday 21 November 2018. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the application be deferred for the following reasons: 1. Cricket Club – Officers to investigate the concern raised about the proximity of the local centre in respect of the adjacent Cricket Club. 2. Transport Matters - Officers to seek further clarification from WCC Highways as to whether they are content with the transport assessment work that has been carried out and consider whether the part signalised gyratory design solution adequately mitigates the impact of the proposed development on the local highway network. 3. Education Provision – Officers to seek further clarification from WCC LEA regarding on-site provision of a primary school and whether WCC LEA consider that they could justify land on the application site being safeguarded for that purpose. Voting: For 11, Against 8
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
SWDP56 Development of North East Comment Malvern: A. Within the area of North-East Malvern, Policy Compliant 56.84ha (gross) of land, as identified on the Policies Map, are allocated for a The application site makes up 51.98ha of sustainable, well-designed mixed-use the allocation and comprises a local centre urban extension. (to include a mix of uses, up to 800 homes, and up to 8.11ha of employment generating uses (10 ha as part of the wider allocated site). B. Development within this area will See below B (i –v) incorporate the following elements: B (i) 10ha of employment-generating uses. Policy Compliant
The application site would deliver up to 8.11ha of employment generating uses. The Local Centre would also house employment generating uses. The wider allocation includes the existing Countrywide Store (0.21ha), part of the highways depot (0.15ha). The proposals would therefore contribute towards the delivery of 10ha of employment generating uses across the allocation in general accordance with this Policy SWDP 56 B(i). B (ii). 800 dwellings of which up to 40% will Policy Compliant* be affordable housing in accordance with SWDP 15. The proposed development would deliver up to 800 dwellings and 20% affordable housing* in accordance with Policy SWDP 15.
*20% affordable housing, following detailed development viability assessment consistent with SWDP15B. B (iii) Community infrastructure including a Not Fully Policy compliant primary school, a community hall, a cemetery and a police post. The development would deliver community infrastructure including a community hall which would also accommodate a police post. The provision of a primary school and cemetery has is not included in the current proposals.
The justification for the provision of a primary school at the site has changed and the County Council has confirmed that the development no longer supports the requirement for a new school. An off site financial contribution is now sought.
In terms of cemetery provision this was included as part of the original proposal but has since been omitted as the surface water impacts of such provision was of concern. Further the Town Council, as the provider / manager of cemetery space in Malvern, do not wish to take up the option of cemetery land here and welcome the removal of it from the proposals.
B (iv) Green Infrastructure to provide public Policy compliant open space, including play space, formal playing pitches, informal recreation areas Sporting and recreation facilities to be and allotments and to facilitate the physical provided on site to meet the needs of the and visual separation of the development development. from the settlement of Newland. Areas of open space are provided throughout the site and providing a clear separation between the development and the settlement of Newlands meeting the policy requirement.
B (v) Facilities for public transport and safe Policy compliant pedestrian and cycle routes linking to local shops, including the Malvern retail park, Routes linking the site to existing employment areas, health care, education employment, shopping and community and Malvern Link Station. facilities are provided. The applicant will also make a proportionate contribution to wider transport network impact based on the additional demands that the application generates. Contributions are made toward the town centre bus service as well as towards the Malvern to Worcester Active Travel Corridor (walking and cycling route).
B (vi) Neighbourhood shopping facilities. Policy compliant
Facilities are proposed to be provided within the local centre.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
M/25/01044/FUL - Grove Farm, PendockLee Walton, Principal Planner, presented the report and presentation to the members of the Committee, referring to th...
M/25/01235/RM - Cales Farm, MalvernSimon Jones, Development Manager, presented the report and presentation to the members of the Committee, referring to...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.