Resolved
that the Quarterly Performance Report be NOTED.
Overview and Scrutiny Committee noted this item on Tuesday 10 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Quarterly Performance Report be NOTED.
Overview and Scrutiny 10 September 2019
Quarterly Performance Report Relevant Wards - All Portfolio Holder – Cllr. S. Rouse Head of Service - Deputy Chief Executive – Andy Baldwin Contact Officer - Finance Manager – Becky Floyd (If you have any queries or questions about the content of this report, please speak to the portfolio holder or contact officer in advance of the meeting.)
1. Purpose and Summary 1.1 To inform the committee of council performance during the first quarter of 2019/20, 1.2 To advise the committee of the strategic issues and risks facing the council which reflect the existing and future financial and organisational pressures on the council.
2. Recommendations i) The achievements and improvements in performance be noted; ii) The strategic issues raised in section 4 be addressed; iii) Executive Committee thank staff for the outcomes of their efforts.
3. Background 3.1 The Performance Management Framework provides for the quarterly review of corporate performance at a strategic level. 3.2 The report has been informed by data from a variety of independent public sources and the council’s own performance management system and progress reports from service managers. Appendix 1 of this report provides the council’s performance measures for 2019/20. 3.3 The Five Year Plan objectives have been updated wherever possible to provide running performance up to the end of Q1, and can be found in Appendix 2. 3.4 The strong performance in numbers of green waste customers and associated income, missed bins as a proportion of all bins, and results of the 2019 Staff Survey, are welcomed. Where under-performance has been identified, it has been, or is being, addressed as a matter of urgency.
4. Strategic Issues and Risks – 4.1 South Worcestershire Development Plan Review (SWDPR)
The SWDPR continues on track with respect to the project timetable set out in the Local Development Scheme (LDS) however, the timetable remains particularly tight
1 Report No. EC to reach publication of a Preferred Options document by November 2019. This is compounded by ongoing uncertainty around possible changes to the Government’s standard methodology for calculating housing need, and dependence on the response times of other agencies and organisations to input to various aspects of the review and the associated evidence base.
Extensive work continues to put in place the necessary evidence base required to support the SWDPR, including a review of the historic Development Boundaries, the results of which will be published alongside the Preferred Options in November.
Site assessments of all sites submitted under the SWDPR Call for Sites exercise (over 1,000 sites across south Worcestershire) are nearing completion, with those that did not immediately fail because they are too small or liable to flooding now out for consultation with experts on their potential as allocations for housing, employment and other uses.
The updated Strategic Housing and Employment Land Availability Assessment, along with the Village Facilities Rural Transport Study, are due to be published in early Q2.
4.2Business Plan Achievement
The council’s business plan has identified target savings of £950,000 over the period 2018-2023. The Council is on course to achieve the 2019/20 target savings of £320,000 under the four categories outlined in the plan: (i) Efficiencies; (ii) Partnership and Services; (iii) Investment and growth; (iv) Income generation. Whilst the council has a robust track record for the achievement of savings, there are still difficult decisions ahead over the period of the business plan. The council is facing budgetary pressures within service areas which are closely monitored by SMT.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Q1 2019-20 Performance dataAppendix 1 | 5 pages | Download |
PDF |
Five Year Plan Review Q1 201920Appendix 2 | 6 pages | Download |
PDF |
Quarterly Performance ReportReport | 10 pages | DownloadRead as text |
Follow Overview and Scrutiny Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Overview & Scrutiny Work ProgrammeIt was agreed that the position would be kept under review, with a special meeting to be convened should any signific... | Agreed | Open |
| 17 Jun 2026 | Confirmation of Minutes from Previous MeetingRESOLVED that the minutes of the previous meeting of the Overview and Scrutiny Committee, held on 10 February 2026, b... | Decided | Open |
| 17 Jun 2026 | Overview & Scrutiny Annual Report 2025/26RESOLVED that the Overview and Scrutiny Annual Report 2025/26 be approved and submitted to Council for review. This w... | Approved | Open |
| 6 Jan 2026 | Confirmation of Minutes from Previous MeetingRESOLVED that the minutes of the meeting of the Overview and Scrutiny Committee, held on 11 November 2025, be confirm... | Decided | Open |
| 11 Nov 2025 | Overview & Scrutiny Work ProgrammeIt was agreed that this could be discussed at an upcoming O&S meeting as an agenda item and would be added to the Wor... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.