OVERVIEW AND SCRUTINY COMMITTEE Date: 2 October 2019
Report of the Section 106/Section 278 Review Group Relevant Wards – All
Portfolio Holder – Councillor Tony Rowley, Executive Board Member for Planning, Infrastructure and Urban Design
Head of Service – Jack Hegarty, Managing Director, Wychavon District Council
Contact Officer – Spencer Winnett, Member Support Officer
(If you have any queries or questions about the content of this report, please speak to the portfolio holder or contact officer in advance of the meeting.)
1. Purpose and Summary 1.1 The report presents the findings and recommendations of the Overview and Scrutiny Committee’s Section 106/Section 278 Review Group, which has examined Section 106 (s106) and Section 278 (s278) developer contributions, with particular focus on:
1.1.1 Looking at how Wychavon District Council (WDC), working with Worcestershire County Council (WCC), can get the developer funded infrastructure built more quickly, to the correct standard and in accordance with any planning conditions that were agreed when the planning consent was given.
1.1.2 Producing a report for the Overview and Scrutiny Committee with recommendations on improvements that will benefit Wychavon District Council, Worcestershire County Council, residents, councillors and developers.
1.2A full Terms of Reference is attached as Appendix A.
1.3The review was carried out over an eleven-month period due to the incremental nature of incoming information from developers and local authorities, and also because the review spanned the time period before and after the May 2019 local elections. The new Section 106/Section 278 Review Group’s first meeting was on 19 July 2019.
1 Report No. EC 1.4 At an early stage, it was agreed that the review was primarily concerned with the s278 process and highways related infrastructure issues, such as those experienced along the Station Road in Pershore and at Yew Tree Hill in Droitwich Spa.
1.5It was subsequently noted that the Overview and Scrutiny Committee had recently discussed s106 contributions in 2017. This information was shared with the current Review Group.
2. Recommendations 2.1 To propose to WCC, the creation of a WDC / WCC jointly funded s278 engineers post as part of the 2020/21 budget process. This could possibly be funded from additional planning fee income, or it could be developer funded.
2.2Where the developer / applicant is prepared to fully remunerate WCC for a full or partial s278 infrastructure design for developments – and providing the standard of the design is of a standard acceptable to the Highways Authority – this should happen. This would allow drawings to accompany a planning application and could help speed up the s278 process. It has been indicated that certain developers are prepared to support this approach financially.
2.3Development team approach
To seek the agreement of Worcestershire County Council to set-up a joint Wychavon District Council / Worcestershire County Council Development Team to work together primarily, but not exclusively, on points a – c below. The Development Team should come together at the outset of planning process, and the relevant developers should be included at appropriate stages in the process. This recommendation complements the recent Wychavon/Malvern Hills Local Government Association (LGA) Corporate Peer Review action to create such a Development Team and the working arrangements could equally be applied to Malvern Hills District Council.
a. Pre–commencement conditions
(i) Reduce the number of pre-commencement conditions and trigger related conditions. The overall objective should be to reduce the number of pre- commencement conditions on planning permissions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Report of the Section 106/ Section 278 Review GroupReport | 8 pages | DownloadRead as text |
Follow Overview and Scrutiny Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Overview & Scrutiny Work ProgrammeIt was agreed that the position would be kept under review, with a special meeting to be convened should any signific... | Agreed | Open |
| 17 Jun 2026 | Confirmation of Minutes from Previous MeetingRESOLVED that the minutes of the previous meeting of the Overview and Scrutiny Committee, held on 10 February 2026, b... | Decided | Open |
| 17 Jun 2026 | Overview & Scrutiny Annual Report 2025/26RESOLVED that the Overview and Scrutiny Annual Report 2025/26 be approved and submitted to Council for review. This w... | Approved | Open |
| 6 Jan 2026 | Confirmation of Minutes from Previous MeetingRESOLVED that the minutes of the meeting of the Overview and Scrutiny Committee, held on 11 November 2025, be confirm... | Decided | Open |
| 11 Nov 2025 | Overview & Scrutiny Work ProgrammeIt was agreed that this could be discussed at an upcoming O&S meeting as an agenda item and would be added to the Wor... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.