Resolved
that i) The achievements and improvements in performance, be noted; ii) The strategic issues raised in section 4 be addressed; iii) Executive Committee thank staff for the outcomes of their efforts.
Executive Committee noted this item on Tuesday 11 February 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
that i) The achievements and improvements in performance, be noted; ii) The strategic issues raised in section 4 be addressed; iii) Executive Committee thank staff for the outcomes of their efforts.
Planning Services 2018/19 2019/20 Previous YTD APL RAG Commentary year Owner SP ref Performance Indicator Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
DCA2 Major' planning applications determined within 13 weeks or agreed See Quarterly Performance Report for commentary and comparison of performance against national target, which is good. This /8 extension of time (valid to decision) (%) 100 73 88 100 83 92 100 87 91 75 measure is of small numbers of major applications, with 9 determined in Q3.
DCA2 Minor' planning applications determined within 8 weeks or agreed /8 extension of time (valid to decision) (%) 92 95 89 92 84 79 86 92 83 85 64 'minor' applications determined in Q3. See commentary in Performance Report.
DCA2 Other' planning applications determined within 8 weeks or agreed extension of time (valid to decision) (%) 97 98 96 98 88 100 97 97 95 85 137 'other' applications determined in Q3 /8
N/A Planning applications determined (n) 224 215 191 171 208 198 210 801 616 N/A
N/A Income generated from fees (£) 178,302 270,131 177,621 149,373 183,530 164,940 146,073 775,428 494,543 739,200
Designation threshold is now 10% (2018). Data since Q3 2017/18 are official data but experimental, and have yet to be verified. Q3 DCA1 Duncan Rudge
Major planning appeals allowed (24 months rolling)(%) 5.4 6.0 5.8 ¯¯ ¯¯ ¯¯ ¯¯ 5.8 ¯¯ <10% figures published in Q1 of 2019/20. Change of measure - a revised DC online satisfaction survey has been used from 2016/17. Results should be treated with caution DCA9 Satisfaction with planning services (%) 44 63 45 43 ¯¯ 67 ¯¯ 49 67 To be set due to very small response rate. Only 3 responses were received in Q3 and, therefore, results not reported.
DC11 Householder (HOU) applications determined within 6 weeks (%) 32 60 65 43 45 30 52 50 43 50 66 'householder' applications determined YTD in 2019/20 out of a total of 179 received. See commentary in QPR. Validation - Major applications processed within 7 working days (from DCV2 receipt to acknowledgement, excluding invalid period) (%) 100 100 100 100 100 100 93 100 97 95 Validation - Minor applications processed within 5 working days (from DCV2 receipt to acknowledgement, excluding invalid period) (%) 92 95 88 86 87 91 97 91 92 95 Validation - Other applications processed within 5 working days (from DCV2 receipt to acknowledgement, excluding invalid period) (%) 90 96.0 95 95 94 97 99 94 97 95 Following the lower performance seen in Q1, as anticipated, figures have increased significantly for Q2 and into Q3 now that new DCV2 Validation - PAs/PDsapplications processed within 3 working days (from 87 94 84 82 79 90 96 86 88 95 and existing members of staff are working to capacity after the completion of training, and as a result of a temporary member of staff receipt to acknowledgement, excluding invalid period) (%) addressing this area of concern specifically. DCE1 Enforcement - Cases closed within 12 weeks (%) 44 76 51 47 54 37 56 52 48 80 See commentary in QPR. Holly Jones
Plans checked within ten days (Malvern) (%) 88 94 88 95 87 92 92 91 90 90 TBC
Building regulations applications received (Malvern) (n) 114 104 89 92 84 88 72 399 244 N/A
Income generated from fees (£) 48,841 39,489 43,300 38,994 29,558 37,190 23,921 170,624 90,669 142,410 Responses to Heritage consultations within statutory timescales (% in 21 118 consultations responded to in Q3. (Although the system does not include everything, this still gives a good indication of the MH16 days) 63 55 60 43 71 71 57 52 63 85% team's workload.) Determination of Listed Building Consents within statutory timescales (% Jim Burgin
MH17 in 8 weeks) 86 93 96 100 96 94 100 93 97 80% 9 Listed Building Consent applications in Q3 Determination of applications for works to trees protected by TPO (% in 8 MH18 weeks) 92 90 100 100 100 95 100 95 98 90% 17 TPO applications in Q3
Determination of notifications for works to trees in a conservation area (% MH19 in 6 weeks) 97 97 94 100 97 92 92 97 94 100% 48 conservation area notifications in Q3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EC1529 APP1: Performance DataReport | 4 pages | DownloadRead as text |
PDF |
EC1529 APP2: Five Year Plan ReviewReport | 6 pages | Download |
PDF |
Quarterly Performance ReportReport | 9 pages | Download |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.