M/23/00219/OUT - Station House, Newnham Bridge, Tenbury Wells, WR15 8JE

Approved Planning 2 papers

Northern Area Planning Committee approved this item on Wednesday 1 October 2025. Below is the council's own wording, with the papers it was decided on.

Item127

Resolved

RESOLVED that the decision to APPROVE the application and Grant Outline Planning Permission be delegated to the Director of Planning and Infrastructure, subject to the following: a) The satisfactory completion of a Legal Agreement to secure: i ) a financial contribution towards off-site affordable housing provision. ii) the delivery of 2 self-build units. b) The imposition of conditions set out in the officer report, and subject to the addition of 3 further conditions, following a review of all final condition wording and order by officers. i ) Demolition, clearance or construction work and deliveries to and from the site in connection with the development hereby approved shall only take place between the hours of 08:00 and 18:00hrs Monday to Friday and 08:00 and 13:00hrs on a Saturday. There shall be no demolition, clearance of construction work or deliveries to and from the site on Sundays or bank Holidays. Reason: To protect residential amenity in accordance with Policy SWDP21 of the South Worcestershire Development Plan. ii) The Development hereby approved shall not commence until a Construction Environmental Management Plan has been submitted to and approved in writing by the Local Planning Authority. This shall include: a) Measures to ensure that vehicles leaving the site do not deposit mud or other detritus on the public highway; b) Details of site operative parking areas, material storage areas and the location of site operatives facilities (offices, toilets etc); c) Details of any temporary construction accesses and their reinstatement. d) A highway condition survey, timescale for re-inspections, and details of any reinstatement. The measures set out in the approved Plan shall be carried out and complied with in full before development commences and maintained during the construction of the development hereby approved. Site operatives' parking shall be kept available for that purpose for the entire construction phase. Reason: To ensure the provision of adequate on-site facilities and in the interests of highway safety. iii) The details submitted pursuant to any application for reserved matters shall include: a) A survey of all existing trees and hedges on the application site in accordance with BS 5837:2012 (Trees in Relation to Design, Demolition and Construction). b) An arboricultural impact assessment and ... view the full minutes text for item 127.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Northern Area Planning Committee, 23 pages

NORTHERN AREA PLANNING COMMITTEE 1 October 2025

Application Number M/23/00219/OUT

Site Address Station House, Newnham Bridge, Tenbury Wells, WR15 8JE

Description of Outline Application for the Erection of 2 No. Self-Build Dwellings Development with access from A456. All other matters reserved.

Case Officer Anna Priestley-Clarke Applicant [name removed].

Parish Knighton on Teme CP Agent [name removed] Member(s) Cllr Douglas Godwin

Reason for Referral Ward Member referral Expiry 28 April 2023 to Committee Date

EoT Key Issues - Housing Land Supply - Principle of the development - Self-build - Design, landscape character and visual impact - Historic environment - Residential amenity - Access and Highway Safety - Biodiversity - Flooding and drainage - Affordable housing

Recommendation Approval 1. SITE DESCRIPTION AND DETAILS OF PROPOSAL

1.1The site constitutes an area immediately to the west of the centrally placed Station House and follows on from a previous application which was allowed at appeal for 3 self-build dwellings to the land on its eastern side.

1.2The proposal seeks planning permission for the development of 2(no) self-build dwellings on land associated with and to the west side of Station House. The application is in outline with all matters reserved except for access.

1.3Scale, Layout, Appearance and Landscaping are reserved matters, and this detail would be considered by a subsequent application. However, indicative plans have been provided to demonstrate how two dwellings could be accommodated within this site.

1.4The following documents have been submitted as part of the application:

- Consultation Statement/Statement of Community Involvement - Design and Access Statement - Planning Statement inc Water Management Statement - Elite Ecology Biodiversity Impact Assessment and Biodiversity Enhancement Strategy August 2021 - Elite Ecology PEA Report May 2021 - Elite Ecology PEA Report November 2024 - Elite Ecology PEA Bat Activity Survey October 2021 - Focus Environmental Consultants PEA with preliminary roost assessment 05 th February 2025 - Energy Statement

2. PLANNING POLICY AND LEGISLATIVE FRAMEWORK

2.1The Development Plan

2.1.1 The determination of a planning application is to be made pursuant to section 38(6) of the Planning and Compulsory Purchase Act 2004, which is to be read in conjunction with section 70(2) of the Town and Country Planning Act 1990. Section 38(6) requires the local planning authority to determine planning applications in accordance with the development plan, unless there are material circumstances which 'indicate otherwise'. Section 70(2) provides that in determining applications the local planning authority "shall have regard to the provisions of the Development Plan, so far as material to the application and to any other material considerations."

2.1.2 The development plan consists of the South Worcestershire Development Plan 2016 and the Waste Core Strategy for Worcestershire - Adopted Waste Local Plan 2012-2027 and any made Neighbourhood Plans (add any adopted Neighbourhood Plans)

2.1.3 South Worcestershire Development Plan (SWDP)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
M/23/00219/OUT: Station House, Newnham Bridge, Tenbury Wells, WR15 8JEReport 23 pages DownloadRead as text
PDF
Planning Presentation: M2300219OUTReport 11 pages Download

At this meeting

Whole meeting

Who was there

10 of 18 attended
BJ
Councillor Barbara Jones-WilliamsVice-Chair, present
DC
Councillor Dean ClarkeChair, present
IM
Ian MacleodOfficer, expected
SJ
Simon JonesOfficer, expected
JM
Councillor John MichaelCommittee Member, apologies
DG
Councillor Douglas GodwinCommittee Member, present
LB
Councillor Lesley BrutonCommittee Member, present
PL
Councillor Pam L CummingCommittee Member, apologies
PJ
Councillor Paul J CummingCommittee Member, apologies
DH
Councillor David HarrisonCommittee Member, present
DW
Councillor Daniel WaltonCommittee Member, present
KW
Councillor Kathy WellsCommittee Member, present

All 18 on the meeting page

More from Malvern Hills Northern Area Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Confirmation of Minutes of Previous MeetingRESOLVED that Vote: For 11, Against 0, Abstentions 0 the minutes of the previous meeting of the Northern Area Plannin... Decided Open
2 Sep 2026 M/25/00768/RM - Land At (Os 8202 5595 West Of Worcester), Martley Road, Lower BroadheathRESOLVED that the application for the reserved matters of landscaping be APPROVED, in accordance with officer’s recom... Approved Open
2 Sep 2026 M/26/00885/FUL - Land At (Os 7833 5108), Leigh SintonRESOLVED that planning permission be GRANTED, subject to the conditions set out in the agenda report and the followin... Approved Open
5 Aug 2026 Confirmation of Minutes of Previous MeetingRESOLVED that Vote: For 10, Against 0, Abstentions 0 the minutes of the previous meeting of the Northern Area Plannin... Decided Open
5 Aug 2026 M/26/00425/HP - The Laurels, Kerswell Green, Worcester, WR5 3PERESOLVED that planning permission be REFUSED contrary to the Officer’s recommendation for the following reason: i ) T... Refused Open