Resolved
RESOLVED that Executive Committee notes the annual update on progress towards the actions contained within the Destination Zero carbon reduction plan.
AI summaryMalvern Hills Executive Committee noted its annual Destination Zero carbon plan update: council emissions down 32% since 2018/19, district emissions down 34% since 2005, but a funding gap threatens decarbonisation of Malvern Splash and Theatres.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that Executive Committee notes the annual update on progress towards the actions contained within the Destination Zero carbon reduction plan.
Executive Committee 18 November 2025
Destination Zero Annual Progress Report 2024/25 Relevant wards: All wards
Portfolio holder: Cllr Jeremy Owenson, Portfolio Holder for Environment
Head of Service: Ian Edwards, Director of Economy and Environment Contact officer: Matt Barker, Carbon Reduction Manager If you have any questions about this report, please contact the portfolio holder or the contact officer.
1. Purpose and summary 1.1 The provide an annual update on progress towards the actions contained within the Destination Zero carbon reduction plan.
2. Recommendations 2.1 The committee is asked to note the progress made to date.
3. Background 3.1 On 23 July 2019, Council approved a motion to declare a climate emergency. Officers were asked to carry out the research to produce a carbon reduction plan in response to this, including recommendations for appropriate carbon emission reduction targets.
3.2Following a six-month period of extensive research and consultation the Council adopted its carbon reduction plan: Destination Zero, in January 2020. The plan sets out the aim of achieving net-zero carbon emissions as quickly as possible, with the Council’s own operations becoming carbon neutral by 2030 and the district as a whole by 2050 at the very latest. The plan identifies a number of priority areas which each contain a series of detailed actions to be delivered to help meet the overall aims of the plan.
3.3The Destination Zero plan also states that progress on the plan will be reviewed on at least an annual basis and reported to the Environment Policy Development Panel and the Executive Committee. This paper presents the annual update report (see Appendix 1) covering the 2024/25 financial year. The report updates on progress against the five key success measures set out in Destination Zero.
3.4It should be noted that the current Destination Zero plan is under review. The review is considering the success measures included in the plan. Therefore, future iterations of this annual update may be subject to a different format and measures.
4. Progress on Destination Zero Success Measures 4.1 The Destination Zero plan identifies the following overall success measures:
• Reduction to zero of the Council’s own greenhouse gas emissions • Reduction as far as possible towards net zero of district-wide greenhouse gas emissions (under the scope of local authorities) • Growth in size of the low carbon economy (to be defined) • Increased amount of renewable energy generation across the district • Increase in the amount of carbon captured through council action
4.2The annual update report at Appendix 1 reports against each of these measures in turn. A headline summary of progress is provided below.
4.3On a district-wide basis, the latest published data shows that emissions in 2023 were 336.8 ktCO2e. This represents a 34% decrease on the 2005 baseline. Domestic and transport sectors are the largest sources of emissions in the district. Domestic emissions have been falling steadily since 2005, although there was a slight rise in 2021 compared to 2020 there has subsequently been a more notable decrease in 2022 that continued into 2023. Transport emissions have remained fairly consistent since 2005 but fell significantly during the 2020, reflecting the impact of Covid-19 restrictions. Transport emissions subsequently rose back again in 2021 and 2022, but a drop has been reported again in 2023.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Destination Zero Annual Update Report 2024-25Appendix 1 | 14 pages | Download |
PDF |
Destination Zero Annual Progress Report 2024/25Report | 5 pages | DownloadRead as text |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.