CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Malvern Hills District Council
Southern Area Planning Committee, Wednesday 21 January 2026 at 6.00pm

M/25/01543/FUL - Langland Stadium, Langland Ave, Malvern WR14 2EQ

Approved Planning 3 papers

AI summarySouthern Area Planning Committee approved a covered spectator stand and clubhouse terrace canopy at Langland Stadium in Malvern, delegating the final decision to the Director of Planning and Infrastructure.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCovered stand and terrace canopy, delegated to officers
MoneyNot stated
What happens nextDirector of Planning to issue decisionAfter 21 day notice and condition sign-off
Who it affectsLangland Stadium usersTotal covered capacity rises to 691

What was decided

The Committee voted 12 to 0, with no abstentions, to approve full planning permission for the Hills View Stand and improvements to the clubhouse terrace with a new canopy, in line with the officer recommendation. Report P4, P5

Final issuance of the decision notice was delegated to the Director of Planning and Infrastructure, subject to the expiry of 21 days from the date of serving notice on the site owner in the correct format under Article 13 of the Development Management Procedure Order.

The Committee accepted amendments to conditions covering roofing materials, to ensure the National Landscape Partnership agreed, and opening times of the terrace and clubhouse, to be agreed with the local Ward Member.

Why

The Planning Officer recommended approval, and the application was supported by the applicant in a statement to the Committee. Report P4

Supporting information clarified that the current certified stadium capacity is 1,320, with 281 existing covered places, and that the proposed Hills View Stand would add 410 covered standing places, bringing total covered provision to 691. Report P10, P11, P12

Additional supporting information addressed the materials proposed for the stand's roof, described as plastisol coated steel single skin sheets, 0.7mm. Report P13, P14

What happens next

Notice in the correct format must be served on the owner of the site, in line with Article 13 of the Development Management Procedure Order.

A 21 day period from the date of serving notice must expire before the decision notice is issued.

Any further representations received between the committee resolution and the issuing of the decision notice must be considered by officers.

Options considered

  • Chosen: Approve in line with officer recommendation, with amended conditions on roofing materials and opening times. Voted 12 for, 0 against, 0 abstentions, after amendments agreed to address National Landscape and Ward Member concerns. Report P4

Implications

  • Legal: The decision is subject to formal service of notice on the site owner under Article 13 of the Development Management Procedure Order and a 21 day representation period.
  • Other: The roofing material condition is tied to agreement with the National Landscape Partnership, and the opening times condition is tied to agreement with the local Ward Member.

Who and where

  • The applicant, who spoke in support of the application under the Public Participation Scheme
  • Users of Langland Stadium, with total covered spectator capacity set to rise from 281 to 691 Report P10, P11, P12
  • The National Landscape Partnership, which must agree the roofing materials condition
  • The local Ward Member, who must agree the opening times condition
  • Ward Member Councillor Paul Bennett, who proposed the motion, and Councillors M Driscoll, J Gallagher, B Nielsen, and J Raine, who spoke to the item

Timeline

  • 21 January 2026: Southern Area Planning Committee resolves to approve the application, subject to conditions, with the final decision delegated to the Director of Planning and Infrastructure. Report P1, P2
  • 21 days from serving of notice on the site owner: Notice period expires before the decision notice can be issued by the Director of Planning and Infrastructure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item113

Resolved

Marcel Grater, Planning Officer, presented the report and presentation to the members of the Committee, referring to the related update sheet. The following verbal updates were given: 1. The resolution be amended as follows: That the decision to APPROVE the application and GRANT Full Planning Permission be delegated to the Director of Planning and Infrastructure, subject to – a) The expiry of 21 days from the date of the serving of notice on the owner of the site in the correct format (to reflect the requirements of Article 13 of the Development Management Procedure Order. b) The consideration of any further representations received between the resolution of committee to grant full planning permission and the issuing of the decision notice by your officers. No representative of the Parish Council made a statement under the Public Participation Scheme. No objectors addressed the Committee under the Public Participation Scheme. [name removed], addressed the Committee under the Public Participation Scheme, as the applicant, in support of the application. Councillor P Bennet spoke to the item as Ward Member. Councillors M Driscoll, J Gallagher, B Nielsen, and J Raine spoke to the item. Following the discussion, Clare Bull, Development Manager, advised the Committee that conditions pertaining to roofing materials and the opening times of the terrace and clubhouse could be amended to ensure the National Landscape Partnership agreed to the roofing materials and opening times could be agreed with the local Ward Member. A motion to APPROVE planning permission, in line with officer recommendation, with the above amendments, was proposed by Councillor P Bennett, seconded by Councillor B Nielsen, and voted upon. Voting: For 12, Against 0, Abstentions 0. The motion was carried.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Southern Area Planning Committee

Southern Area Development Management Committee

21 January 2026

UPDATES

ITEM 6: Planning Ref: Site: Ward Councillor Recommendation M/25/01543/FUL Langland Cllr Paul Bennett Approval Stadium Langland Avenue Malvern WR14 2EQ

Proposal: Construction of covered spectators stand 'Hills View Stand'. Improvements to the clubhouse terrace with new canopy.

Officer: Marcel Grater

Parish/Town Council: Malvern CP

Applicant: [name removed] Supporting Information Received

• Supporting information provided in respect of the maximum capacity of the Stadium:

“In summary, the current certified capacity is 1,320, based on the existing provision. This includes 155 covered seated places and 126 covered standing places within a single stand, giving covered provision for 281 people in wet weather.

The proposed Hills View Stand will provide a maximum capacity of 410 people, all standing and covered. This would increase total covered provision to 691.

In addition, the proposed Clubhouse Canopy will further increase covered provision, particularly benefiting wheelchair users. The exact additional capacity is still to be finalised; however, calculations have been undertaken in accordance with the Green Guide to Safety at Sports Grounds, using standard standing space assumptions (600mm widths).”

• Supporting information provided with regards to the materials to be used for the proposed stand’s roof.

“Plastisol coated steel single skin sheets - 0.7mm

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Individual Committee updates_M2501543FULReport 184 KB DownloadRead as text
PDF
Langland Stadium M2501543FULReport 203 KB Download
PDF
M/25/01543/FUL: Langland Stadium, Langland Ave, Malvern WR14 2EQReport 1.9 MB Download

At this meeting

Whole meeting

Who was there

12 of 16 attended
JO
Councillor Jeremy OwensonCommittee Member, apologies
JW
Councillor Julie WoodVice-Chair, present
MA
Councillor Martin AllenCommittee Member, present
PB
Councillor Paul BennettCommittee Member, present
MJ
Councillor Mark John DriscollCommittee Member, present
JG
Councillor John GallagherCommittee Member, present
NM
Councillor Natalie McVeyCommittee Member, apologies
NM
Councillor Neville MillsCommittee Member, present
BN
Councillor Beverley NielsenChair, present
CP
Councillor Cynthia PalmerCommittee Member, apologies
JR
Councillor John RaineCommittee Member, present
MV
Councillor Malcolm VictoryCommittee Member, present

All 16 on the meeting page

More from Malvern Hills Southern Area Planning Committee

All decisions
MeetingDecisionOutcome
26 Aug 2026 Confirmation of Minutes of Previous Meetingthat the minutes of the previous meeting held on 24 June 2026, be approved and signed by the Chair as a true and corr... Approved Open
26 Aug 2026 M/25/01044/FUL - Grove Farm, PendockLee Walton, Principal Planner, presented the report and presentation to the members of the Committee, referring to th... Refused Open
26 Aug 2026 M/25/01235/RM - Cales Farm, MalvernSimon Jones, Development Manager, presented the report and presentation to the members of the Committee, referring to... Approved Open
26 Aug 2026 M/26/00634/FUL - The Hill Centre, Tunnel HillSimon Jones, Development Manager, presented the report and presentation to the members of the Committee, referring to... Approved Open
24 Jun 2026 Confirmation of Minutes of Previous MeetingRESOLVED : that the minutes of the previous meeting held on 18 March 2026, be approved and signed by the Chair as a t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies