Audit and Standards Committee, Wednesday 18 February 2026 at 2.00pm

Audit Completion Report - Azets

Decided Finance 4 papers

AI summaryMalvern Hills District Council's Audit and Standards Committee accepted Azets' 2024/25 Final Auditors Annual Report, which carries a disclaimed audit opinion. The disclaimer follows four years of prior disclaimed opinions due to insufficient assurance on opening balances.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFinal Auditors Annual Report 2024/25 noted by committee
MoneyNot stated
What happens nextBuild-back work continuesReserves and PPE assurance work continues in 2025/26
Who it affectsCouncil financial reportingSets out disclaimer on 2024/25 accounts

What was decided

The Audit and Standards Committee accepted the Final Auditors Annual Report 2024/25 from external auditors Azets.

The report records a disclaimed audit opinion because the auditors could not gain sufficient assurance on opening and closing balances ahead of the 27 February 2026 backstop date. Report P6, P7

No material audit adjustments or significant weaknesses in value for money arrangements were identified. Report P6, P10, P87, P95

Why

Disclaimers on the four previous years of accounts mean there is no assurance over comparators or opening balances, which limits what can be concluded for 2024/25. Report P8, P40, P41

Some testing areas could not be completed, including valuations of land and buildings, pension assets and liabilities, and IFRS 16 implementation, because of the backstop and the missing prior year assurance. Report P25, P27, P29, P45, P49, P55

No significant weaknesses were found in the council's arrangements for securing economy, efficiency and effectiveness in its use of resources, based on the value for money work presented in November 2025. Report P10, P95

What happens next

Auditors will complete remaining procedures, including the management representation letter, signed final accounts, and submission of the Whole of Government Accounts return to the National Audit Office. Report P7, P85

Build-back assurance work on reserves and Property, Plant and Equipment will continue into the 2025/26 audit, with a re-assessment of the pension valuation when the next triennial valuation is incorporated. Report P8, P33, P41, P46, P93

The audit certificate will be delayed until the Comptroller and Auditor General certifies the Whole of Government Accounts for 2024/25. Report P11, P85

The money

  • £51.800m Income reported in 2024/25 financial statements Report P58
  • £43.947m Expenditure reported in 2024/25 financial statements Report P58
  • £48,413k Property, Plant and Equipment balance Report P59, P74
  • £23,560k Cash and cash equivalents Report P62
  • £7,419k Short-term debtors balance Report P60

Options considered

  • Chosen: Accept the Final Auditors Annual Report 2024/25 as presented. The committee accepted the report; the alternative would have been to reject or seek further changes.

Implications

  • Financial: Auditors intend to issue a disclaimer of opinion on the 2024/25 financial statements, meaning no opinion is expressed on whether they give a true and fair view. Report P6, P25, P27, P29, P34, P42, P49, P55
  • Financial: Five consecutive years of disclaimed opinions create ongoing uncertainty about opening balances carried forward into future years. Report P8, P40
  • Legal: Auditors have not exercised any additional statutory powers or duties under the Local Audit and Accountability Act 2014. Report P11, P86
  • Risk: Build-back plan covers re-gaining assurance from 2020/21 to 2023/24 over the period 2024/25 to 2027/28 in line with LARRIG 06 guidance. Report P8, P91, P92, P93
  • Other: The audit certificate cannot be issued until the National Audit Office certifies the Whole of Government Accounts for 2024/25, so the certificate will be delayed. Report P11, P85

Who and where

  • Malvern Hills District Council as the audited body Report P1, P4
  • External auditors Azets, who carry out the audit Report P3, P4
  • The Audit and Standards Committee, as those charged with governance Report P4, P95
  • Users of the council's financial statements, including residents and stakeholders Report P4, P20
  • Worcestershire County Council Pension Fund and its actuary, where pension data is sourced Report P48, P76

Timeline

  • 28 February 2025: Backstop applied to 2023/24 audit, resulting in a disclaimer Report P37
  • 30 June 2025: National deadline for publication of accounts missed Report P13
  • July 2025: External Audit Plan reported to Audit and Standards Committee Report P6, P8
  • 8 July 2025: Council published its unaudited Statement of Accounts Report P13
  • November 2025: Auditor's Annual Report on value for money presented to Audit and Standards Committee Report P10, P95
  • 18 February 2026: Audit and Standards Committee meeting at which the report was accepted Report P2
  • 27 February 2026: Statutory backstop date for issuing the 2024/25 audit opinion Report P6, P7, P76

Plain English for the jargon

  • Disclaimer of opinion: An audit opinion stating the auditor cannot form an opinion on the financial statements, usually because sufficient evidence could not be obtained.
  • Backstop: A statutory deadline by which an audit opinion must be issued, after which a disclaimer may be the only option.
  • Build-back assurance: The programme of work to re-gain audit assurance over years for which a disclaimer was previously issued.
  • LARRIG: Local Audit Reset and Recovery Implementation Guidance issued by the National Audit Office to address the backlog in local audits.
  • CIPFA Code: The Code of Practice on Local Authority Accounting in the UK, setting out the accounting requirements for local councils.
  • IFRS 16: International Financial Reporting Standard on leases, which requires lessees to recognise right of use assets and lease liabilities.
  • WGA: Whole of Government Accounts, a consolidated set of public sector accounts.
  • PPE: Property, Plant and Equipment, a category of fixed assets on the balance sheet.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item87

Resolved

that the Audit and Standards Committee accept the Final Auditors Annual Report 2024/25.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Audit and Standards Committee

Malvern Hills District Council Audit Completion Report Year ended 31 March 2025

February 2026

Azets > Move forward with confidence 1 Your key team members Contents Purpose of this report

This report highlights the significant findings arising from the Executive summary 3 Karen Jones audit. We are responsible for performing the audit in accordance Key Audit Partner Financial statements 7 with International Standards on Auditing (UK), and the National [email removed] Building back assurance 36 Audit Office Code of Audit Practice and associated Auditor Guidance Notes. Michael Butler Value for Money 39 Associate Director Independence and ethics 41 Our audit is directed towards forming and expressing an opinion [email removed] on the financial statements that have been prepared by management with the oversight of the Audit and Standards Committee. Under the Code of Audit Practice, we are also required Simbongile Qupe Appendices 44 to consider the Council’s arrangements for securing economy, In-Charge auditor Appendix I: Fees efficiency and effectiveness in its use of resources and to report [email removed] any significant weaknesses we identify. However, our audit is not designed to test all internal controls or identify all areas of control weakness. As such, our work cannot be relied upon to disclose all This report has been prepared for the sole errors or other irregularities, or to include all possible use of those charged with governance, improvements in internal control that a more extensive should not be quoted in whole or in part examination might identify. without our prior written consent, and should not be relied upon by third parties. No responsibility is assumed by Azets Audit The primary responsibility for the prevention and detection of Services to any third parties. We do not fraud rests with management and those charged with governance, accept any responsibility for any loss including establishing and maintaining internal controls over the occasioned to any third party acting, or reliability of financial reporting, effectiveness and efficiency of refraining from acting, on the basis of the operations and compliance with applicable laws and regulations. content of this report, as this report was As auditors, we obtain reasonable, but not absolute, assurance not prepared for, nor intended for, any that the financial statements, as a whole, are free from material other purpose. misstatement, whether caused by fraud or error.

Azets > Move forward with confidence 2 Executive summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Completion Report: AzetsReport 1.6 MB DownloadRead as text
PDF
MHDC_Draft Audit Opinion_202425Report 160 KB Download
PDF
MHDC_LoR_202425Report 130 KB Download
PDF
Statement of Accounts 2024-25Report 215 KB Download

At this meeting

Whole meeting
84Confirmation of MinutesApproved
87Audit Completion Report - AzetsThis decision
88Audit Reports - InternalApproved

Who was there

6 of 10 attended
CG
Chris GreenCouncil Staff, present, as expected, virtual
DC
Councillor Dean ClarkeChair, present
LB
Councillor Lesley BrutonCommittee Member, present
KW
Councillor Kathy WellsCommittee Member, present
AW
Councillor Andrew WillmottVice-Chair, present
BJ
Barbara Joan Beard (Parish Councillor)Committee Member, apologies
AB
Andy BaldwinOfficer, present
MP
Meesha PatelOfficer, apologies
JM
Councillor John MichaelCommittee Member, apologies
MV
Councillor Malcolm VictoryCommittee Member, apologies

More from Malvern Hills Audit and Standards Committee

All decisions
MeetingDecisionOutcome
22 Sep 2026 Confirmation of MinutesRESOLVED : that the minutes of the previous meeting held on 9 July 2026, be approved and signed by the Chair as a tru... Approved Open
9 Jul 2026 Confirmation of MinutesResolved : that the minutes of the previous meeting held on 18 February 2026, be approved and signed by the Chair as ... Approved Open
9 Jul 2026 Audit Plan 2026/27RESOLVED : that the Audit and Standards Committee approve the . Approved Open
18 Feb 2026 Confirmation of Minutesthat the minutes of the previous meeting held on 26 November 2025, be approved and signed by the Chair as a true and ... Approved Open
18 Feb 2026 Audit Reports - Internalthat the Audit and Standards Committee approve the Internal Audit Charter and Mandate. The Internal Audit Progress Re... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies