Community Infrastructure Investment Plan 2025-28 Progress Update
ApprovedExecutive2 papers
AI summaryMalvern Hills District Council's Executive Committee approved £3.4M of Community Infrastructure Levy reserves for the Upton Hill Centre and Leigh Sinton Community Hub, and up to £157k for Holt Village Hall.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedPlus delegation on Section 106 reserves
Money£3.4M plus up to £157kFrom unallocated CIL reserves
What happens nextNot stated
Who it affectsCommunities across all wardsIncluding Upton, Leigh Sinton and Holt
What was decided
The committee noted progress on the Community Infrastructure Investment Plan 2025-28, with 45 grant agreements issued and three community asset projects completed. Report 2.1, P86
The committee approved £3.4M of unallocated CIL reserves to fund improvements at the Upton Hill Centre and the new Leigh Sinton Community Hub. Report P85
The committee approved up to £157k of CIL reserves to close the funding gap on a new Holt Village Hall, and delegated authority to the Deputy Chief Executive to use eligible Section 106 reserves. Report 2.3, 2.4, 4.15
Why
A £7.8M total cost to deliver the plan in full leaves a £3.39M funding gap, after the original £3M CIIP allocation and £1.4M of match funding. Report 5.3, P52
Football Foundation grant funding will not be accessible before March 2028, and construction inflation has pushed up costs on the Upton Hill and Leigh Sinton projects. Report 5.2, 5.11, 5.18
Unallocated CIL reserves stood at £3.57M as of 15 May 2026, and with Local Government Reorganisation under two years away the council would otherwise lose the ability to spend these reserves in the district. Report 6.3, 6.4, 8.2
What happens next
The Upton Hill Centre project is ready to commence in August or September 2026, subject to planning approval and the additional CIL allocation. Report 5.13
At Leigh Sinton, the grass pitch works could begin in September 2026, with the built facility starting in January 2027, again subject to planning and budget approval. Report 5.21
Officers will continue to support the remaining un-commenced legacy grant projects and will draw down a £106,312.80 Section 106 contribution from a 33-dwelling Holt Heath development towards the village hall before using CIL. Report 4.8, 4.14, 4.15
The money
£3.4M Unallocated CIL reserves for Upton Hill Centre and Leigh Sinton Community Hub
£157k Maximum additional CIL for Holt Village Hall Report 2.3
£780,927.19 Final tendered price for Holt Village Hall replacement Report 4.11
£156,927 Funding shortfall on Holt Village Hall after CIL and match funding Report 4.13
£106,312.80 Section 106 community infrastructure contribution from 33 dwellings in Holt Heath, plus RPI Report 4.14
£7,810,115 Total estimated cost to deliver the CIIP across all ten facilities Report P52
£3,392,747 Total funding gap on the council assets programme Report P52
£3,570,000 Unallocated CIL balance as of 15 May 2026 Report 6.3, P85
Options considered
Chosen: Allocate full £3.57M of unallocated CIL reserves to the Upton Hill and Leigh Sinton projects. Aligns with CIL regulations and avoids losing reserves before Local Government Reorganisation Report 6.4
Rejected: Wait for further external funding before progressing the larger projects. Football Foundation funding will not be available before March 2028 and the council faces a spending deadline before LGR Report 5.2, 6.4
Implications
Financial: An additional £3.4M from CIL and up to £157k more for Holt Village Hall, bringing total CIIP-related investment in community assets to £9.6M. Report P87
Risk: If the CIL reserves are not allocated now, the Upton Hill and Leigh Sinton projects would be undeliverable and the council would lose the ability to spend CIL in the district before LGR. Report 8.2
Legal: The projects align with CIL regulations on play areas, open spaces, cultural and sports facilities and other community safety infrastructure.
Equalities: Equalities impact assessment is not applicable to this progress update. Report 9.3
Who and where
Residents and community groups across all wards of Malvern Hills District Report P2, P20
Welland Junior Football Club and Upton Rugby Club users of the new 3G pitch at Upton Hill Report 5.8, 5.9
Leigh and Bransford Badgers Football Club and Leigh Sinton residents using the new community hub and pitches Report 5.16
Holt parish users of the replacement village hall Report P35, 4.12
30 of 48 legacy grant funded projects identified as having potential to operate as Community Wellbeing Hubs Report 4.9
Timeline
11 April 2025: Community Facility Legacy Grant Scheme opened for an 8-week application window
January 2026: Two lowest contractors submitted revised bids for Holt Village Hall Report 4.11
1 May 2026: Section 106 Agreement signed for 33 dwellings in Holt Heath Report 4.14
15 May 2026: Unallocated CIL balance recorded at £3,570,000 Report 6.3
20 May 2026: Status of 48 conditional grant offers recorded, with 45 agreements issued Report 4.5, P24
August or September 2026: Upton Hill Centre project ready to commence subject to planning approval Report 5.13
September 2026: Leigh Sinton grass pitch works could commence Report 5.21
January 2027: Leigh Sinton built facility due to commence Report 5.21
March 2028: Earliest point at which Football Foundation funding would be accessible Report 5.2
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure
CIIP: Community Infrastructure Investment Plan 2025-28, the council's framework for investing in community facilities
S106: Section 106 planning obligation, a developer contribution tied to a specific planning permission
LGR: Local Government Reorganisation, the restructuring of councils in the area
3G pitch: Third generation artificial grass pitch used for football and other sports
IFS: Infrastructure Funding Statement, which replaced the Regulation 123 list and sets out how CIL is spent
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item211
Resolved
RESOLVED that Executive Committee: i ) Notes the progress made so far in delivering the Community Infrastructure Investment Plan (CIIP) 2025-28. ii) Approves the allocation of £3.4M of unallocated CIL reserves to support the delivery of improvements at the Upton Hill Centre and the development of a new Leigh Sinton Community Hub. iii) Approves the allocation of up to £157k of unallocated CIL reserves to enable the construction of a new Holt Village Hall. iv) Delegates authority to the Deputy Chief Executive, in consultation with the Portfolio Holder for Resources to use any eligible Section 106 reserves to fund the projects as appropriate.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Community Infrastructure Investment Plan 2025-28 Progress Update Report Relevant wards: All wards
Portfolio holder: Councillor J Watkins, Portfolio Holder for Communities and Housing Head of Service: Jen Taylor, Director for Communities and Housing
Contact officer: Mark Hammond, Community Infrastructure and Development Manager If you have any questions about this report, please contact the portfolio holder or the contact officer.
1. Purpose and summary 1.1 This report provides an update on the progress made with the delivery of the Council’s Community Infrastructure Investment Plan 2025-28, including:
i) the investment into community owned public open space and community facilities via the Community Facility Legacy Grant Scheme, and
ii) the investment into the Council’s own assets.
1.2The report also includes recommendations for the approval of unallocated Community Infrastructure Levy (CIL) funds to support the full delivery of the Community Infrastructure Investment Plan 2025-28.
2. Recommendations that Executive Committee:
2.1Notes the progress made so far in delivering the Community Infrastructure Investment Plan (CIIP) 2025-28. 2.2 Approves the allocation of £3.4M of unallocated CIL reserves to support the delivery of improvements at the Upton Hill Centre and the development of a new Leigh Sinton Community Hub.
2.3Approves the allocation of up to £157k of unallocated CIL reserves to enable the construction of a new Holt Village Hall.
2.4Delegates authority to the Deputy Chief Executive, in consultation with the Portfolio Holder for Resources to use any eligible Section 106 reserves to fund the projects as appropriate.
3. Background 3.1 The Council adopted the Community Infrastructure Investment Plan 2025-28 (CIIP) and approved a capital budget allocation of £4M at its Executive Committee meeting in March 2025
3.2The CIIP provides the Council with a framework to invest in its communities, and has a strategic vision to:
i) “Deliver a legacy for the Malvern Hills District, by enhancing the current network of facility provision across the district, to ensure communities have access to high-quality, sustainable and accessible open spaces and facilities, that foster improved health and well-being and connect communities through sport, physical activity and social connection”.
3.3The CIIP is underpinned by, and supports the delivery of, key strategic plans and strategies including:
i) The Council Plan: focussing on accelerating the development of community hubs for wellbeing.
ii) The Council’s Connected Communities Strategy 2021-2041: focussing on developing healthier communities, safer and inclusive communities and stronger and sustainable communities.
iii) The South Worcestershire Development Plan review: supported by the South Worcestershire Playing Pitch Strategy 2020-2041, the Built Sports Facility Strategy 2020-2041 and the Open Space Assessment 2019.
4. Community Facility Legacy Grant Scheme Progress Update 4.1 As reported in the Community Facility Legacy Grant Scheme 2025 EC Report (Sep 2025). The grant scheme opened on 11 April 2025, for 8-weeks. 70 applications were received from across 15 of the district’s 18 wards. 4.2 The projects ranged in scale and scope, and included environmental improvements, refurbishments, facility enhancements, car park works and open space improvements.
4.3£1M was allocated to the grant scheme from the £4M CIIP budget. Due to the strength of the applications, an additional £894k of funding was identified through other sources including Section 106, CIL and destination zero.
4.4The increased £1.9M budget, allowed 48 projects to be awarded conditional grant offers. A further £1.15M was forecast to be secured through match funding, bringing the estimated total investment in community facilities to more than £3M as a direct result of the legacy grant scheme.
4.5As of 20 May 2026, out of the 48 projects that received conditional offers:
i) 45 grant agreements have been issued,
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.