Resolved
Decision To note the report submitted and the comments raised.
Audit Committee noted this item on Monday 3 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note the report submitted and the comments raised.
In October 2017 Audit Committee were provided with an update on plans to achieve ICT Disaster Recovery (DR) capability for the Council. Members requested that a further update be provided to Committee as this work progressed. Work is underway to establish the DR capability by the end of September 2019 and this report sets out the associated approach and timescales.
This approach means that three Internal Audit recommendations relating to DR are no longer deemed relevant; as they will be superseded by the new solution. This report sets out the context for this proposal.
Audit Committee on 31 July confirmed that the DR report should also include an update on actions being taken in respect of access to the Public Service Network (PSN). This update is set out in the report.
Audit Committee are asked to consider the assurance provided by the update report.
Wards Affected: All
Contact Officers:
Name: Bob Brown - Chief Information Officer Email: [email protected] Telephone: 0161 234 5998
Background documents (available for public inspection):
The following documents disclose important facts on which the report is based and have been relied upon in preparing the report. Copies of the background documents are available up to 4 years after the date of the meeting. If you would like a copy please contact one of the contact officers above.
● DR Report to Audit Committee October 2017 ● Outstanding Audit Recommendations report to Audit Committee July 2018 ● ICT Update Report to Scrutiny Committee July 2018 1. Introduction and Background
1.1Disaster recovery (DR) and business continuity planning are integral parts of the overall approach to risk management. Since all of risks cannot be eliminated, organisations implement disaster recovery and business continuity plans to prepare for potentially disruptive events.
1.2Both processes are equally important for the Council because they provide detailed strategies on how services will continue to operate during severe interruptions and in the aftermath of major incidents and disasters. At present the Council has no formal disaster recovery capability and a programme of work is underway to address this issue to ensure systems and services are available.
1.3A report to Audit Committee in October 2017 set out the approved strategy to develop a disaster recovery capability; and at the same time to improve the underlying resilience of the Council’s ICT infrastructure to help minimise the risks of interruptions and incidents.
1.4Along with resilience and disaster recovery, ICT security is also a key risk to any large organisation. One of the ways in which the Council’s ICT security arrangements are reviewed and assured is through a programme of ongoing Public Services Network (PSN) compliance that is led by the Cabinet Office. This enables the Council to access the PSN which helps public sector organisations work together, reduce duplication and share resources.
1.5This report update Audit Committee on progress to date in respect of DR and PSN.
2. Data Centre Programme Update
2.1The overall objective of the Data Centre (DC) Programme is to ensure high availability of critical business applications, services and ICT infrastructure. The programme will remove single points of failure within ICT infrastructure through the delivery of a resilient and robust data centre solution for the Council. The programme is based on the operation of services from two active data centres rather than a ‘traditional’ model of a primary and back-up data centre. This model means that each data centre will always be active and in the event of interruption or disaster at one, the other centre will act as an almost immediate failover solution.
2.2The programme is made up of three projects:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ICT Assurance Update: Disaster Recovery Planning and Public Service NetworkReport | 153 KB | DownloadRead as text |
Follow Audit Committee at Manchester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | 2025/26 Annual Accounts DraftDecision The Committee note the report. | Noted | Open |
| 28 Jul 2026 | External Audit ‘Audit Strategy MemorandumDecision The Committee note the report. | Noted | Open |
| 28 Jul 2026 | Work Programme and Decisions MonitorDecision The Committee note the report. | Noted | Open |
| 16 Jun 2026 | Draft Annual Governance Statement 2025/26Decision The Committee note the contents of the draft version of the Council’s 2025/26 Annual Governance Statement an... | Noted | Open |
| 16 Jun 2026 | Accounting Policies 2025/26Decision The Committee approve the accounting concepts and policies to be used in preparing the Council’s 2025/26 ann... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.