Audit progress report Manchester City Council November 2018 CONTENTS 1. Audit progress
2. National publications
This document is to be regarded as confidential to Manchester City Council. It has been prepared for the sole use of the Audit Committee. No responsibility is accepted to any other person in respect of the whole or part of its contents. Our written consent must first be obtained before this document, or any part of it, is disclosed to a third party. 2 1. AUDIT PROGRESS
Purpose of this report
This report provides the Audit Committee with an update on progress in delivering our responsibilities as your external auditors.
Audit progress
2018/19 is the first year that Mazars is your external auditor following the award of the audit contract by Public Sector Audit Appointments Limited (PSAA). This is our first progress report in respect of the 2018/19 audit year. Our key audit stages are summarised in the diagram shown over the page.
Upon completion of our initial planning and risk assessment, we will present our Audit Strategy Memorandum to the Audit Committee for discussion.
We have met with senior members of your finance team, including the City Treasurer and Head of Internal Audit, to discuss the audit process and to agree timescales for the completion of our audit work. Regular liaison meetings will continue throughout the year.
We have also helped host the Audit Committee’s development session on 8 October 2018 and presented to Members on the Role of External Audit which generated much discussion.
We are working with Grant Thornton, as your predecessor auditor, as part of the handover process to ensure a smooth transition for your finance team.
1. Summary 2. Audit progress 3. National publications 4. Contact details
3 1. AUDIT PROGRESS
• Final review and disclosure • Updating our understanding of checklist of financial statements the Council • Final partner review • Initial opinion and value for • Agreeing content of letter of money risk assessments representation • Development of our audit • Reporting to Audit Committee strategy • Reviewing post balance sheet • Agreement of timetables events • Preliminary analytical • Signing our opinion procedures Planning Completion Nov 18-Jan July 2019 19
Fieldwork Interim June-July Jan-April 19 19 • Review of draft financial • Documenting systems and statements controls • Reassessment of audit • Walkthrough procedures strategy, revising as • Controls testing, including necessary general and application IT • Delivering our planned audit controls testing • Early substantive testing of • Continuous communication transactions on emerging issues • Liaison with auditors of your • Clearance meeting group companies
1. Summary 2. Audit progress 3. National publications 4. Contact details
4 2. NATIONAL PUBLICATIONS Publication/update Key points National Audit Office (NAO) Transformation guidance for Audit Key questions for Committees to 1. Committees consider for transformation projects. Provides more background for new Committee Members, including the 2. Code of Audit Practice overarching Code which governs our work. Roles and responsibilities of the NAO Defines our responsibilities as your 3. and local auditors external auditor. Includes guidance in respect of the VfM Guidance and information for 4. arrangements review which may be of auditors interest to Committee Members. Public Sector Audit Appointments Ltd (PSAA) Mazars Annual Regulatory and 5. Overall assessment of ‘green’. Compliance Report 2017/18 Inaugural meeting in April 2018; invite to 6. Local Audit Quality Forum, PSAA all Audit Committee Chairs and Chief Finance Officers. Local Government Association (LGA) Speeding up delivery: learning from Report highlights some distinctive 7. councils enabling timely build-out of projects and innovative practices. high quality housing Reflections by LGA which may be of 8. Sector-led improvement in 2017/18 interest to the Council.
1. Audit progress 2. National publications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Audit Progress Report and UpdateReport | 802 KB | DownloadRead as text |
Follow Audit Committee at Manchester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | 2025/26 Annual Accounts DraftDecision The Committee note the report. | Noted | Open |
| 28 Jul 2026 | External Audit ‘Audit Strategy MemorandumDecision The Committee note the report. | Noted | Open |
| 28 Jul 2026 | Work Programme and Decisions MonitorDecision The Committee note the report. | Noted | Open |
| 16 Jun 2026 | Draft Annual Governance Statement 2025/26Decision The Committee note the contents of the draft version of the Council’s 2025/26 Annual Governance Statement an... | Noted | Open |
| 16 Jun 2026 | Accounting Policies 2025/26Decision The Committee approve the accounting concepts and policies to be used in preparing the Council’s 2025/26 ann... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.