HS2 Phase 2b Western Leg (Crewe-Manchester) hybrid Bill Petitioning
AgreedCommittee1 paper
Constitutional and Nomination Committee agreed this item on Friday 4 March 2022. Below is the council's own wording, with the papers it was decided on.
Decision To recommend that Council, subject to being satisfied that it is expedient for Manchester City Council to do so, oppose elements of the HS2 Phase 2b Western Leg (Crewe- Manchester) hybrid Bill as detailed in the report submitted. Council is recommended to: (1) Resolve, being satisfied that it is expedient for Manchester City Council to do so, to oppose elements of the HS2 Phase 2b Western Leg (Crewe- Manchester) hybridBill introduced into 24 January 2022 session of Parliament as detailed in the report. (2) Subject to (1) above, delegate authority to the Strategic Director (Growth and Development), in consultation with the Leader of the Council and City Solicitor, to take all such steps as may be necessary to give effect to the above resolution including all those steps required for the Council to submit any petition and thereafter to maintain and if considered appropriate authorise the withdrawal of any petition points that have been resolved in respect of the Bill, and to negotiate and/or seek assurances/ undertaking/agreements to the Bill.
Word for word from the decision Manchester published for this meeting.Source: democracy.manchester.gov.uk
This report sets out a procedural matter, specifically, seeking Full Council approval for the City Council to object to elements of the HS2 Phase 2b Western Leg (Crewe- Manchester) hybrid Bill, deposited in Parliament on 24 January 2022.
Recommendations
Constitutional and Nomination Committee is asked to recommend that Council, subject to being satisfied that it is expedient for Manchester City Council to do so, oppose elements of the HS2 Phase 2b Western Leg (Crewe- Manchester) hybrid Bill as detailed in the report
Council is recommended to:
(1) Resolve, being satisfied that it is expedient for Manchester City Council to do so, to oppose elements of the HS2 Phase 2b Western Leg (Crewe- Manchester) hybrid Bill introduced into 24 January 2022 session of Parliament as detailed in the report.
(2) Subject to the above, delegate authority to the Strategic Director (Growth and Development), in consultation with the Leader of the Council and City Solicitor, to take all such steps as may be necessary to give effect to the above resolution including all those steps required for the Council to submit any petition and thereafter to maintain and if considered appropriate authorise the withdrawal of any petition points that have been resolved in respect of the Bill, and to negotiate and/or seek assurances/ undertaking/agreements to the Bill.
The overall financial and resource implications of reaching agreements and/or petitioning will be the subject of further assessment as matters requiring agreement and associated technical work are better understood. As additional funding requirements become known, resources will be identified and reported for approval in accordance with the Council’s financial procedure rules.
Financial Consequences – Capital
None directly from this report.
Contact Officers:
Name: Rebecca Heron Position: Strategic Director - Growth and Development Telephone: 0161 234 5515 E-mail: [email protected]
Name: Pat Bartoli Position: Director of City Centre Growth & Infrastructure Telephone: 0161 234 3329 Email: [email protected]
Background documents (available for public inspection):
The following documents disclose important facts on which the report is based and have been relied upon in preparing the report. Copies of the background documents are available up to 4 years after the date of the meeting. If you would like a copy please contact one of the contact officers above.
Report to Executive 14 December 2016 - Manchester Piccadilly High Speed 2 (HS2) Phase 2 Route Announcement
Report to Economy Scrutiny 1 February 2017 - High Speed Rail – High Speed 2 (HS2) and Northern Powerhouse Rail (NPR)
Report to Executive 18 October 2017 - Greater Manchester HS2 and Northern Powerhouse Rail Growth Strategy
Greater Manchester HS2 and NPR Growth Strategy: The Stops are Just the Start 2018
Report to Executive 7 March 2018 – Manchester Piccadilly Strategic Regeneration Framework Update 2018 Report to Executive 27 June 2018 – Manchester Piccadilly Strategic Regeneration Framework Update 2018
Manchester Piccadilly Strategic Regeneration Framework 2018
HS2 Working Draft Environmental Statement 2018, available at: https://www.gov.uk/government/collections/hs2-phase-2b-working-draft- environmental-statement
Report to Economy Scrutiny 7 November 2018 - HS2 Working Draft Environmental Statement (WDES)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Constitutional and Nomination Committee at Manchester and we tell you when its next papers are published, before the meeting rather than after it.
Elections Act Duties Progress ReportDecision The Committee noted the report, in particular: • The ongoing work to implement promotion of the Voter ID sch...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.