Resolved
Decision The Committee were to Minded ... view the full minutes text for item 24.
Planning Committee decided this item on Thursday 10 April 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee were to Minded ... view the full minutes text for item 24.
The application proposes a part 12, part 33 storey student accommodation (PBSA) building with ground floor amenity space. Consent is also sought on a temporary basis for an associated Construction Compound.
2 objections have been received.
Principle of the proposal and the schemes contribution to regeneration
The proposals are in accordance with national and local planning policies, and would bring significant economic, social and environmental benefits. It would develop a vacant, brownfield site which currently has a negative impact on the area.
The proposed PBSA meets the policy requirements set out in policy H12 of the Core Strategy and increase the supply of student accommodation. 15% of the accommodation would affordable, available on a discounted rent.
The construction compound would be in situ for the duration of the construction period only.
Economic : The proposal would generate 254 full-time equivalent (FTE) during the 3 year build period, contributing c.£26m GVA to the economy. Once operational, the development would support 25 equivalent FTE jobs and contribute c.£0.96m GVA to the local economy. A local labour proposal would ensure local people benefit.
Social : This proposal would redevelop a vacant, low quality brownfield site close to the Oxford Road Corridor. 861 bedspaces (15% of which would be affordable) would support the student accommodation pipeline.
Environmental: This is a highly accessible area where walking and cycling is encouraged. Green infrastructure would be created including bird and bat boxes to improve biodiversity. Renewable technologies would meet some of the buildings energy needs. Sustainable drainage would manage surface water. The design would improve the appearance of this key site at a gateway route into the City Centre.
Impact on the historic environment: The building would impact on the setting of some nearby listed buildings and a non designated heritage asset (NDHA). It would cause a low level of less than substantial harm to one of the listed buildings which would be outweighed by the benefits of the scheme.
Impact on local residents: There would be impacts on daylight/sunlight and overlooking. Construction impacts including from the Compound could be managed to minimise the effects on residents and businesses. Noise outbreak from plant and the commercial unit would meet relevant standards. The PBSA would be a significant proposal near to an established residential community and its scale would be noticeable. This is an area where change is needed and expected.
A full report is attached below for Members consideration.
Description of site/building
The application relates to 2 sites, one for the Proposed Development (the Site) and one for the associated Construction Compound. The Site where is located is 0.25 ha and bounded by Plot 9A (currently being developed as a 9 storeys office), Plot 10A (which has permission for a 13 storey office), Hulme Street; and Medlock Street. Medlock Street is a gateway route into the City Centre. Most recently this site has been used as a compound for the plot 9A development.
The compound site is 0.46 ha, bounded by the River Medlock; Cambridge Street; Macintosh Mills; and River Street. It is currently used as a construction compound, in relation to the construction of Plot 10B
Application sites
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
141786/FO/2024: Plot 9B First Street, Manchester: Deansgate WardReport | 6.8 MB | DownloadRead as text |
Follow Planning Committee at Manchester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Aug 2026 | Supplementary Information on Applications Being ConsideredDecision To receive and note the late representations. | Noted | Open |
| 6 Aug 2026 | Supplementary Information on Applications Being ConsideredDecision To receive and note the late representations. | Noted | Open |
| 9 Jul 2026 | Supplementary Information on Applications Being ConsideredDecision To receive and note the late representations. | Noted | Open |
| 9 Jul 2026 | 145243/FO/2026 - Land on the corner of Lord Street and Cheetham Hill Road, Cheetham, ManchesterDecision The Committee resolved to approve subject to finalising a Section 106 agreement to secure the affordable hou... | Approved | Open |
| 11 Jun 2026 | Supplementary Information on Applications Being ConsideredDecision To receive and note the late representations. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.