143445/FO/2025 & 143446/LO/2025 - British Muslim Heritage Centre College Road Manchester M16 8BP
ApprovedPlanning1 paper
AI summaryManchester Planning Committee approves retention of the British Muslim Heritage Centre marquee for 18 months, with a new condition requiring three-monthly event schedules to be submitted in writing to the council.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedShorter than the three years requested, with Condition 3 amended
MoneyNot stated
What happens nextNot stated
Who it affectsNot stated
What was decided
The Committee resolved to approve application 143445/FO/2025 and 143446/LO/2025 to retain the existing temporary marquee for a period of 18 months, subject to conditions in the report, with Condition 3 amended to require written three-monthly event schedules to the Local Planning Authority. Report P1, P3, P86, P88
Why
Officers noted this is the fourth extension since the original 2013 consent, that no permanent proposal has been brought forward, and that the temporary consent lapsed on 31st October 2025 during consideration; the Heritage Advisory Panel considered the marquee caused significant harm to the heritage asset, while Environmental Health continues to receive noise complaints and the Manchester Heritage Advisory Panel recommended refusal. Report P86, P87, P88, P34, P29, P30, P31
Supporters cited community, religious and economic benefits including space for Friday prayers (800+), two Eids (3000+), Ramadan, weddings and conferences, and stated the centre has worked to manage noise, parking and community impact. Highways, Greater Manchester Police and Historic England raised no objection subject to conditions, with 1195-1196 emails of support received. Report P14, P15, P23, P25, P27, P32, P33
What happens next
The applicant is aiming to submit a full Master Plan application in January 2026 to replace the temporary marquee with a permanent building of an aspirational design that complements the Grade II* listed building. Report P11, P85, P86
Under the amended Condition 3, written details of all upcoming events for the next three-month period must be submitted to the Local Planning Authority within seven days of the permission, with similar submissions before each subsequent three-month period, and any exceptional new events must be notified.
Options considered
Chosen: Approve for 18 months with amended Condition 3 (3-monthly event notification). Committee decision following deferral on 18 December 2025 Report P14
Rejected: Approve for three years as requested. Officers considered a sufficient period had already been given across three previous extensions to enable a permanent proposal Report P86, P87
Rejected: Refuse, as recommended by Manchester Heritage Advisory Panel. Committee voted to approve with conditions instead Report P34
Implications
Legal: Section 72 of the Planning (Listed Buildings and Conservation Areas) Act 1990 requires special attention to preserving or enhancing the conservation area; Sections 16(2) and 66(1) require special regard to preserving the listed building and its setting. The marquee lies within the Whalley Range Conservation Area adjacent to a Grade II* listed building, with the entrance gate posts grade II listed. Report P2, P76, P77, P82
Equalities: 1195-1196 supporting representations were received (601 from addresses outside Manchester) emphasising the centre's role for religious observance, community cohesion, youth, women, the elderly and those with restricted mobility, and warning that closure would only relocate the same issues to another part of Manchester. Report P15, P23
Risk: Environmental Health continues to receive complaints about PA and music noise, traffic noise, engine revving and fireworks from events, and states a noise report is required to demonstrate control of noise from the marquee; residents report repeated non-compliance with hours, the noise limiter and traffic management. Report P29, P30, P31, P17, P18, P19, P20, P21, P22
Environment and climate: Residents report a decline in trees and hedges around the marquee over 12 years, two dead trees left in place, and concerns about biodiversity loss, air quality from idling wedding cars and gridlock on College Road and Clarendon Road during large events such as Eid al-Fitr 2025. Report P17
Other: The Manchester Heritage Advisory Panel considered the temporary marquee is causing detrimental impact on the setting of the adjacent listed building and the character of the conservation area and stated the application should be refused, while Highways requested confirmation of when the Travel Survey was undertaken and recommend conditioning the revised Events Management Strategy. Report P25, P26, P27, P34
Who and where
British Muslim Heritage Centre (applicant), a Grade II* listed building set in landscaped grounds within the Whalley Range Conservation Area Report P1, P2, P3
Local residents on College Road and Clarendon Road and the wider Whalley Range residential area Report P2, P14, P17
Ward Councillor Razaq, who wrote in support of the proposal Report P14
Worshippers attending Friday prayers (up to 800), Eid gatherings (over 3000), Ramadan prayers, weddings, conferences and community events Report P3, P23
Greater Manchester Police, Highways Services, Environmental Health, Historic England, Manchester Heritage Advisory Panel Report P25, P29, P32, P33, P34
Timeline
September 2013: Original planning permission and listed building consent (refs 100277/100278) granted for the temporary marquee for three years Report P3, P5
2016: Renewal granted under application 112122/FO/2016/S1 (with listed building consent to October 2019) Report P6
2018/2019: Variation approved under 116225/JO/2017 to allow use until 1.30am for night prayer during Ramadan 2018/2019 Report P7
2019: Further three-year renewal granted under 122963/FO/2019 (with listed building consent to October 2022) Report P8
2022: Further three-year renewal granted under 133465/FO/2022 (with listed building consent ref 133466/LO/2022 to 31 October 2025) Report P8
31 October 2025: The previous temporary consent for the marquee lapsed during consideration of the current applications Report P88
14 December 2025: Resident reports Clarendon Road gate not opened during an event, with all cars using College Road rather than the one-way arrangement and no visible security presence Report P18
18 December 2025: Application was previously deferred at Planning Committee; residents report fireworks issues after this date Report P14, P20
21 December 2025: Complaints about disamenity at events including lack of security, shouted rather than headset parking directions and late opening of the Clarendon Road exit Report P19
26 December 2025: Resident reports external lighting to the marquee left on after 11pm Report P20
28 December 2025: Resident reports guests leaving the marquee just after 11pm with cars still on site, shouting and car doors slamming Report P21
January 2026: Applicant aiming to submit a full Master Plan application to replace the marquee with a permanent building Report P11, P86
1 January 2026: Resident reports cars from an event still present at 10:56pm, Clarendon Road exit locked all evening and no visible security presence Report P22
12 February 2026: Planning Committee resolved to approve the application for a period of 18 months with amended Condition 3
Plain English for the jargon
BMHC: British Muslim Heritage Centre, the applicant and site operator
Marquee: Temporary PVC and glazing structure, 900 sq.m internal area, 4m to eaves and 8.9m to ridge, used for weddings, Friday prayers, Eid and conferences
Grade II*: A higher grade of listed building designation indicating particularly important buildings of more than special interest
Whalley Range Conservation Area: Designated heritage area in which the site sits, requiring special attention to preserving or enhancing its character under Section 72 of the Planning (Listed Buildings and Conservation Areas) Act 1990
Listed Building Consent: Separate consent required for works affecting a listed building, here ref 143446/LO/2025
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Decision The Committee resolved to approve the application for a period of 18 months, subject to the additional conditions recommended in the report, with Condition 3 amended to: Within seven days of the date of this permission, details of all upcoming events shall be submitted in writing to the Local Planning Authority for the next three-month period, and prior to each subsequent three-month period details of all planned events shall be submitted in writing to the Local planning Authority. Any exceptional new events that fall within the upcoming time period which have not been notified to the Local Planning Authority shall be ... view the full minutes text for item 8.
Word for word from the decision Manchester published for this meeting.Source: democracy.manchester.gov.uk
Application Number Date of Appln Committee Date Ward 143445/FO/2025 10th Sep 2025 12th Feb 2026 Whalley Range Ward
Proposal Extension of time for further three years for a temporary marquee.
Location British Muslim Heritage Centre, College Road, Manchester, M16 8BP
Applicant British Muslim Heritage Centre
Agent [name removed], Create It Studio Architects
This application was initially deferred in November 2025 to allow for a site visit. Following the visit in December 2025, the application was further deferred to enable the applicant to explore the provision of strengthened mitigation measures which could respond to issues and concerns raised by Members, officers and residents.
At the meeting in January 2026, following additional mitigation measures put forward by the applicant, Members resolved to be minded to approve the application. The application was therefore deferred and a request made that officers draft potential conditions that are robust and enforceable and which would minimise impact on the amenity of residents.
The additional mitigation measures put forward include:
- timers will be fitted to all relevant external and internal lights
- undertaking that any further temporary approval for the marquee will not lead to an application for it to become a permanent structure
-a comprehensive car park management plan will be implemented, including increased marshalling
-carrying out an independent acoustics review. It is stated that an independent acoustic expert has already been engaged to review soundproofing of the marquee and recommended works may include installing additional sound walls and insulation. Adjusting and redirecting internal speakers. Creating noise barriers by planting additional trees and shrubbery
- extend Security team hours to ensure all attendees leave the site on time.
- create a new Committee with councillors and neighbours to monitor activities
- reduce the maximum capacity of attendees to any marquee event from 800 to 550 people.
- have a dedicated ‘Out of hours’ phone number for residents to raise concerns. - maximum 4-hour parking limit with fines – contract with a parking company to monitor parking restrict parking to four hours. This includes fitting signs and cameras to enforce new rules.
- ensuring more robust contracts with customers, allowing for large fines for event hirers who contravene any of the rules including excessive noise.
- The current contract with the marquee operator is up for renewal. As part of the renewal of the contract they would be looking at adding an aspect of Social Value in any new contract to align with Manchester City Council’s policy.
For completeness and since the January meeting, a further representation has been received from a neighbouring resident which states that there was an event in the marquee on the 25 January, the PA system was very loud and has been on other occasions since planning was approved. Neighbouring residents who have said they are relieved that there will be proactive monitoring of future events by officers. Given that the council intends to monitor the activities at the marquee for the next 18 months the following is urged:
-ensure that the Council have the full list of events booked -that officers turn up unannounced and monitor the event from the very beginning until the staff have all left -staff walk around the whole site during events, not just the front -staff note parking and traffic on surrounding streets -also request an input into the future planning conditions, for example can they suggest that events finish at a particular time?
If Members remain minded to approve, the following conditions are recommended:
1.The marquee for use as ancillary events and function space is hereby granted for a limited period only; the use shall cease and the marquee shall be removed on or before 12 August 2027.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.