The Cabinet noted the use of the Leader’s urgency powers to extend the nine month Exclusivity Agreement to 24 September 2010 with Crest Nicholson for the entirety of Phase 1 of Rochester Riverside. 118/2010 The Cabinet agreed to delegate authority to the Chief Executive, in consultation with the Leader, to make any further changes to the Exclusivity Agreement with Crest Nicholson, as set out in paragraph 3.3 of the report, until 17 December 2010 . Reasons: The use of the Leader’s urgency powers and the delegation to the Chief Executive means that the opportunity for development activity at Rochester Riverside with the Council’s preferred developer is retained and that momentum is maintained on this flagship regeneration project.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report informs Members of a decision made by the Leader, using his urgency powers, to enable the Council to extend the Exclusivity Agreement with Crest Nicholson until 24 September 2010 for the entirety of Phase 1 of Rochester Riverside, and seeks a further delegation to 17 December 2010.
1. Budget and Policy Framework
1.1Paragraph 3.2 of part 3 (Responsibility for Cabinet Functions) of Chapter 3 (Responsibility for Functions) of the constitution permits the Leader of the Council to make decisions that are urgently required.
Background
2.1Council appointed Crest Nicholson (CN) as its preferred developer for Phase 1 of Rochester Riverside on 17 January 2008 (minute no. 484 (F)) and delegated authority to the Chief Executive, in consultation with the Leader, to grant a development agreement and lease of Phase 1. The area referred to as Phase 1 stretches from Doust Way to Blue Boar Creek and extends to approximately 7 hectares. It will include approximately 600 new homes together with new landscaped areas and river walk as well as some other mixed use buildings.
2.2Due to the economic downturn progress on the scheme has slowed considerably since late 2008. However, in mid September 2009, CN sought urgent agreement from the Council to enter into an Exclusivity Agreement (EA) by 31 October 2009 and this was agreed by the Leader using his urgency power and reported to Cabinet on 24 November 2009.
2.3Considerable progress has been achieved on the emerging scheme design and CN have continued to be committed to the project. The Rochester Riverside Project Board has agreed to an extension of the milestone dates to accommodate revisions to the designs. As the EA was due to expire on 31 July 2010 a formal extension of two months, to 24 September 2010, has been agreed by the Leader.
2.4The specific terms of the EA are subject to a confidentiality clause but in summary the key principles of the Agreement are: • An EA for a 9-month period, now extended until 24 September 2010. • An EA covering the whole of Phase 1 (approx 600 units) from Doust Way to Blue Boar Lane which is an identical area to that included in the Invitation to Bid documents • During the EA period CN, will progress the design development and related financial and business planning with the intention (subject to the Council and SEEDA’s approval) of submitting the first planning application in Summer 2010 • Specific milestones and dates are set out in the EA in order to ensure momentum is maintained on the project
2.5Owing to the timescales involved, the Leader, using his urgency powers, agreed that the Council, with SEEDA, would grant an extension until 24 September 2010 of the Exclusivity Agreement with Crest Nicholson for the entirety of Phase 1 of Rochester Riverside.
Risk management
3.1Rochester Riverside is Medway Council’s flagship regeneration project and of key importance in the Thames Gateway and has been the beneficiary of considerable investment by the public sector. The intention is to see the site redeveloped as a high quality sustainable neighbourhood. Without a developer or a partnership with the private sector this is not achievable.
3.2The original EA was due to expire on 31 July 2010 and without an extension would have automatically terminated. This could have led to a loss of CN’s involvement in the project thereby leaving the Council without a developer partner. The selection of CN in 2008 as preferred developer for Phase 1 of Rochester Riverside was a lengthy and rigorous process and would take considerable time to repeat at a time when the housing market is still uncertain.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.