Resolved
The Audit Committee noted the progress in delivering the 2010/11 programme and that all key assurance work will be completed to support the needs of the annual governance statement and external audit.
Audit Committee noted this item on Tuesday 28 September 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
The Audit Committee noted the progress in delivering the 2010/11 programme and that all key assurance work will be completed to support the needs of the annual governance statement and external audit.
To advise Members of progress in delivering the approved 2010/11 work programme.
1. Budget and Policy Framework 1.1 Following the Council’s decision to establish this committee, it is within the remit of this committee to take decisions regarding accounts and audit issues.
2. Background – 2010/11 Programme 2.1 Members approved the internal audit 2010/11 work programme on 30 June 2010. The programme is derived from a number of sources, which are:-
• the Council’s risk identification process, identified through the risk register, business and service plans, • internal audit’s view of risk, • work requested by Members, Chief Executive, Chief Finance Officer, directors and other officers, • predetermined audits that form part of an agreed arrangement with the external auditor.
2.2The approved programme and progress to date is set out at Annex A. Additions to the plan are shown at Annex A whilst items removed from this year’s programme are shown at Annex B.
2.3Audit work on the key financial systems, work carried out on behalf of the external auditor, corporate governance, risk management and prevention of fraud and corruption are considered key activities and are given priority when resources are allocated. The aim is that all of the key assurance audits will be completed to meet the needs of the governance statement and external audit. 3. Risk Management, Financial and Legal implications
3.1There are no risk management, financial or legal implications arising directly from this report.
4 Recommendations 4.1 Members are asked to note the progress in delivering the 2010/11 programme and that all key assurance work will be completed to support the needs of the annual governance statement and external audit.
Lead officer contact
Name Richard Humphrey Job Title Audit Services Manager Telephone: 01634 332355 Email: [email protected]
None Annex A Internal Audit Programme 2010/11
Directorate/Department Authority Children and Regeneration Business Wide Adults Community Support Activity and Culture Department
Key Financial Systems
Capital Budgetary Control Q4 Capital expenditure can only be incurred on schemes included in the council’s capital programme. Members approve the schemes on the basis of appraisals of their expected cost and funding; but once approved, responsibility for their administration is delegated to directorates.
Cabinet is responsible for monitoring the capital budget and they must ensure that actual expenditure for each scheme in the programme remains within the approved projected budget and specified target over their lifetime.
The capital programme for 2010/2011 and beyond incorporates current approved schemes as they are forecast to rollover into 2010/2011 and a proposed schedule of schemes for future years. When the 2010/11 budget was set, the capital monitoring forecast showed that almost £77 million of the current approved programme approaching £155 million will be delivered in future years and some capital resources to fund the programme will roll forward from 2009/2010 and new allocations will become available.
The audit will examine procedures and arrangements for collecting and reporting information on the cost and progress of capital schemes.
*Capital Budgetary Control – School’s programme Q4
At the Audit Committee on 30 June 2010, Members requested that the capital budget audit be extended to cover the schools’ capital programme. Annex A Internal Audit Programme 2010/11
Directorate/Department Authority Children and Regeneration Business Wide Adults Community Support Activity and Culture Department
Key Financial Systems
Care Director Income Q4 In 2009, the Raise adult social care system was upgraded to Care Director. There have been problems in the system’s ability to invoice clients and an emergency system has been used until the income module can be fixed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Work ProgrammeReport | 195 KB | DownloadRead as text |
Follow Audit Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Internal Audit Strategy 2025-28 Progress UpdateThe Committee noted the progress during 2025-26 against the Internal Audit Strategy 2025-28. | Noted | Open |
| 30 Jul 2026 | National Fraud Initiative Exercise - Annual UpdateThe Committee noted the report. | Noted | Open |
| 30 Jul 2026 | Audit Committee - Review of Terms of ReferenceThe Committee approved the suggested changes to Terms of Reference and provide a recommendation to Full Council for a... | Approved | Open |
| 30 Jul 2026 | Exclusion of the press and publicThe Committee agreed not to exclude the press and public and defer the item to the following meeting. | Agreed | Open |
| 19 Mar 2026 | Internal Audit Update 1 December 2025 to 28 February 2026The Committee noted the outputs and performance against the Internal Audit Plans for Medway for the period 1 December... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.