Resolved
The committee noted the report.
Business Support Overview and Scrutiny Committee noted this item on Wednesday 15 December 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
The committee noted the report.
This report seeks to present members with a brief overview of the importance of the Council’s Forward Procurement Plan (FPP) and Contracts register and how its uptake and use can ensure an effective contract monitoring is achieved.
1. Policy Framework
1.1The specific requirements for all Directorates to maintain an up to date contracts register and Forward Procurement Plan (FPP) is in line with the Council’s Procurement Rules, agreed by Full Council.
2.1Whilst considering the Risk Management Strategy and the 6 monthly review of the Council’s Corporate Business Risk Register at the previous committee meeting on 4 November 2010 Members of the committee requested that they receive a report setting out details of the Council’s forward procurement plan and contracts register.
3. The Forward Procurement Plan
3.1The Council maintains an 18-month rolling Forward Procurement Plan (“FPP”). Details of projects with an estimated contract term value exceeding £100,000 are recorded on the FPP. Project details recorded on the FPP are as set out below:
• Name of Project Manager • Project Title • Value of the intended procurement activity • The month when the project is intended to be delivered at each of the Council’s Gateway 1, 2,3,4 stages • Project status – up to date status narrative • Strategic context • Planned project progress in the form of green, amber and red traffic lights
3.2Officers across the Council are required to ensure details of their projects as stated above are recorded on the plan at the point of project conception. The Council Directorates maintain Directorate forward plans and these to the Strategic Procurement team on a monthly basis for incorporation into the FPP.
3.3The FPP is published on a monthly basis and stands as a standard agenda item for discussion at meetings of the Procurement Board and Officer Scrutiny Panel. Officers are called upon to provide responses to queries on their projects as and when necessary at said meetings.
3.4In order to provide a level of transparency of the Council’s procurement activities and to raise the awareness of Suppliers to the Council’s procurement activities, the FPP is published on the Council’s website and is therefore open for public inspection.
4. The Contracts Register:
4.1The Council’s Contracts register details all procurement activities with an estimated contract term value in excess of £100,000. The register is held by the Council’s Strategic Procurement team. Upon completion of a procurement activity, Officers are required to ensure their Directorate contract registers are updated to include details of completed contracts. Updated contract registers are forwarded to the Council’s Strategic Procurement team on a monthly basis.
4.2Each Directorate maintains a contracts register and has a designated point of Officer contact.
4.3The absence of a Contracts Register could result in the following;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Contract Register and the Forward Procurement PlanReport | 73 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.