Resolved
The Audit Committee noted progress on the Council’s risk management activities.
Audit Committee noted this item on Tuesday 5 July 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
The Audit Committee noted progress on the Council’s risk management activities.
This report updates to Committee on the progress of the Council’s risk management activities.
1. Budget and Policy Framework
1.1Good corporate governance requires that local authorities identify all their significant strategic and operational risks, and put effective risk management and internal control systems in place. All local authorities are now obliged to publish an annual statement on their systems of governance, which include risk management and internal control.
2.1In February 2006, the Council recognised that the existing risk strategy and risk management would not meet the criteria for the then CPA assessments. A number of measures were agreed that would affect a culture change and ensure that risk management processes were robust and embedded into the organisation. These have been incorporated into the action plan within the Risk Management Strategy.
2.2The Council uses a risk management methodology and model that was developed by an external consultant. Each year Internal Audit carries out an annual review of the Council’s progress in adopting and embedding this method for the identification, evaluation and recording of risk.
2.3The Council’s risk management activities continue to be co-ordinated by the Strategic Risk Management Group (SRMG), which is chaired by the Director of Regeneration, Community & Culture and includes the Chief Finance Officer and representatives from the service directorates and various support functions. 3. Advice and analysis
3.1Cabinet undertook the annual review of the strategy on 30 November 2010 and agreed the strategy and officers’ recommendations that no significant changes needed to be made at that time.
3.2The Risk Management Audit 2010/2011 confirmed that risk management arrangements are satisfactory. However it identified that training and arrangements regarding the creation of directorate risk registers require further development.
3.3These two issues were outstanding actions from the plan reported to the Audit Committee in March 2010.
3.4Service risks continue to be recorded in service plans and monitored by Service Managers and through Assistant Directors quarterly reports. It was agreed that adding risks to Covalent, the Council’s performance management system, should be in a later phase of implementation (2011/12) and that training would be provided to assist managers in using Covalent to manage risks.
3.5The Strategic Risk Management Group, in consultation with the Research and Review team (who manage Covalent), have agreed a phased approach to take this forward.
3.5.1 Phase 1: Service-level risks identified as part of the divisional business planning process will be uploaded into Covalent (together with mitigating controls where possible). To be completed end of July 2011 . 3.5.2 Phase 2: Data to be extracted by division via Covalent reports to determine quality and training needs. To be completed end of August 2011
3.5.3 Phase 3: Draft risk registers to be put to DMTs for comment together with the escalation process. Throughout September 2011
3.5.4 Phase 4: Train officers in relation to updating risk assessments and providing progress commentary on mitigating actions. Throughout October and November 2011
3.5.5 Phase 5: Undertake first updating cycle. Throughout December 2011.
3.5.6 Phase 6: Incorporate any remaining mitigating actions from service plan risk registers that can be uploaded into Covalent. Throughout December 2011 3.5.7 Phase 7: Produce directorate risk registers that meet the criteria as set out in the escalation procedure. February 2012
3.5.8 Phase 8: Undertake a further programme of training for managers and members. March 2012 onwards
3.6In-house training for Members is planned for July 2011.
4. Financial, legal and risk implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of Risk ManagementReport | 104 KB | DownloadRead as text |
Follow Audit Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Internal Audit Strategy 2025-28 Progress UpdateThe Committee noted the progress during 2025-26 against the Internal Audit Strategy 2025-28. | Noted | Open |
| 30 Jul 2026 | National Fraud Initiative Exercise - Annual UpdateThe Committee noted the report. | Noted | Open |
| 30 Jul 2026 | Audit Committee - Review of Terms of ReferenceThe Committee approved the suggested changes to Terms of Reference and provide a recommendation to Full Council for a... | Approved | Open |
| 30 Jul 2026 | Exclusion of the press and publicThe Committee agreed not to exclude the press and public and defer the item to the following meeting. | Agreed | Open |
| 19 Mar 2026 | Internal Audit Update 1 December 2025 to 28 February 2026The Committee noted the outputs and performance against the Internal Audit Plans for Medway for the period 1 December... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.