101/2011 The Cabinet approved the Abbey Court School, Elaine Primary School and Twydall Primary School projects to proceed to Gateway 2 of the procurement process and invite tenders for the schemes of works, on the basis set out in paragraph 3.9 of the report (Procurement via a below EU Threshold Select List).
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to commence the batched procurement of building works at Abbey Court School in Rainham, Elaine Primary School in Strood and Twydall Primary School in Gillingham. All three schools have been identified as being priorities to receive funding as part of the Council’s Primary Capital Programme. These projects support the Council’s strategy to provide improved accommodation for the pupils, families and local communities.
If approved, this batched procurement process will be conducted on the basis of procurement lots, whereby tenderers will be able to bid for one or more of the individual school projects and possibly all three.
The aim of the procurement is to procure either a single contract for all three schools or a series of individual contracts that deliver the requirements of the schools, whilst ensuring best value for money.
The contracts will be awarded as a whole or as a series of contracts, based upon an individual evaluation for each school and also an overall batched evaluation for all three schools. Therefore, all three school procurement projects will be evaluated separately but have the option to be awarded both separately and collectively based upon whichever procurement option provides optimum value for money outcomes. Cont…/ Abbey Court School, Rainham The project is needed to address some of the deficiencies in spaces, including size of teaching and learning spaces and medical and therapy areas, and much needed storage for wheelchairs and other equipment.
Many of the general teaching classrooms are below the required area highlighted in BB102 guidelines. The project aims to enlarge two of the current classrooms by remodelling existing spaces, create additional storage, and much needed therapy, physio and medical rooms.
In addition to the improvements for the children, provision of improved staff work areas is also planned, together with an entrance lobby for the recently built nursery block. The proposed plans are to build an area on a new first floor for the staff accommodation, to avoid taking any outside learning and play space as the site has little external provision currently.
Elaine Primary School At Elaine School, the aim is to provide an additional classroom to accommodate the forecast increase in roll in 2011/12 and beyond, as well as creating much needed additional parking and circulation for vehicles, and a staff work area, which was previously allocated as teaching space. There will also be 1 temporary classroom from September 2011, which will be removed following completion of the new extension, thus allowing the school to accept pupils in the new academic year
Twydall Primary School The project at Twydall will support the amalgamation in September 2011 of the Infant and Junior Schools by joining the two buildings with a linking corridor, as well as a new block incorporating staff and administration accommodation, and combined entrance for the new school. In addition there will be a one-way circulation road for vehicles and drop-off point for taxis and minibuses for children with disabilities. Some of the vacated accommodation in the current junior building will be developed to create a specialist unit for children with hearing impairments and cochlear implants.
This Gateway 1 report has been approved for submission to Cabinet after review and discussion at Children and Adults Directorate Management Team meetings on 19/01/2011 for Elaine Primary, 16/06/2011 for Twydall Primary and 30/06/2011 for Abbey Court, and consideration at the Strategic Procurement Board on 6 July 2011.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.