The Cabinet noted the comments of the Business Support Overview and Scrutiny Committee . 178/2011 The Cabinet approved the Risk Management Strategy, as set out in Appendix A to the report . 179/2011 The Cabinet approved the amendments to the Council’s Risk Register as detailed in section 4 of this report . Reasons: The establishment of a corporate framework for risk management is recommended by CIPFA and SOLACE and will complement and support the work already being carried out within each directorate to manage risks .
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
In accordance with paragraph 4.1 of the Council’s Risk Management Strategy, this report is to discuss both the annual review of the Risk Management Strategy and the 6 monthly review of the Council’s Corporate Business Risk Register
1. Budget and Policy Framework
1.1The Risk Management Strategy underpins all aspects of Council work and is fundamental to the Performance Plan in terms of "giving value for money”.
Background
2.1Cabinet undertook the annual review of the strategy on 30 November 2010 and agreed with the strategy and officers’ recommendations and that no significant changes needed to be made at that time.
2.2The Corporate Risk Register was last reviewed by Cabinet on 29 March 2011. The following changes were made to the register at that time:
Risk Ref: SR 21 – Procurement downgraded to C2. Risk Ref: SR23 – ‘Improvement Plan for Housing Service (HRA)’ downgraded to E2 3. Related Information
3.1The Risk Management Audit 2010/2011 confirmed that risk management arrangements are satisfactory. However it identified that training and arrangements regarding the creation of directorate risk registers require further development.
3.1.1 These two issues were outstanding actions from the plan reported to the Audit Committee in March 2010.
3.1.2 Service risks continue to be recorded in service plans and monitored by Service Managers and through Assistant Directors quarterly reports. It was agreed that adding risks to Covalent, the Council’s performance management system, should be in a later phase of implementation (2011/12) and that training would be provided to assist managers in using Covalent to manage risks.
3.1.3 The Strategic Risk Management Group, in consultation with the Research and Review team (who manage Covalent), have agreed a phased approach, detailed in Appendix D, to take this forward
4 Advice and analysis
4.1The Strategic Risk Management Group has reviewed the Risk Strategy, (Appendix A) and recommended that no significant changes need to be made at this time
4.2Risks owners have reviewed their risks and updated them as detailed in Appendix C and the following recommendations have been proposed:
4.2.1 SR 24 – Managing Change be replaced with a new risk SR 30 Delivering Better for Less Transformation.
4.2.2 SR 09a - ‘Delivering the Transformation Agenda’ be removed as the Transformation programme no longer exists and that it be replaced by a new risk SR 25 ‘Adult Social Care Demographics’ to recognise that the focus must now be on the demographic impact on both demand and capacity to deliver statutory responsibilities. The risk rating of C2 remains the same.
4.2.3 SR 09b – ‘Keeping vulnerable young people safe and on track’ be retained and refocused but remove and create a new risk concentrating on looked after children (ref SR26) risk rating B2. This reflects the fact that there is National and local evidence that children and young people in care are more vulnerable to poorer outcomes which could impact on our statutory responsibilities and regulatory judgement and increased costs. 4.2.4 SR 08a – ‘Partnership Working’ be removed as it is too generic and be replaced with three new risks focusing on key partnerships as described in 4.2.5, 4.2.6 and 4.2.7.
4.2.5 Create a new risk SR 27 risk rating B2 to reflect the fact that Councils are responsible for poor performance of schools including independent, academies and free schools but lack levers for change with potential impact on our statutory responsibilities and regulatory judgement and could have financial consequences.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.