89/2012 The Cabinet approved an extension of three months for the installation of cremators and abatement equipment at Medway Crematorium . 90/2012 The Cabinet agreed that these decisions are considered urgent and therefore should not be subject to call-in . Reasons: The extension is the most appropriate and cost effective option.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
A project has been agreed that provides for the enlargement of two chapels, improved car parking facilities and for the installation of cremators and mercury abatement equipment at Medway Crematorium.
A specialist supplier of cremators and a principal building contractor have been appointed through agreed procurement processes.
This report seeks permission from the Cabinet to agree to an extension to the contract timetable.
1. Budget and Policy Framework
1.1The decision is within the council’s policy and budget framework, including the Council Plan.
1.2This report is being presented as an urgent item because of the requirement to install cremators capable of removing mercury by 31 December and the two (previously) selected contractors must be in receipt of a contract, agreed by the Council, before they can start placing orders with their suppliers. This agreement to extend is time critical and any further delay would mean that this target date is not achieved.
1.3The Chairman of the Business Support Overview and Scrutiny Committee has agreed that the taking of these decisions cannot be reasonably deferred, in accordance with Rule 16 (Special Urgency) of the Access to Information Rules (Part 2 of Chapter 4 in the Constitution). 1.4 Additionally and in line with rule 16.11 of Chapter 4, Part 5 of the Constitution, call-in can be waived where any delay likely to be caused by the call-in process would seriously prejudice the Council’s or the Public’s interests. The Chairman of the Business Support Overview and Scrutiny Committee has agreed that the decisions proposed are reasonable in all the circumstances and to them being treated as a matter of urgency and to waive call-in.
Background
2.1The Cabinet considered a Gateway 3 Procurement Tender Process Review and Contract Award in respect of the design and provision of new cremators and abatement equipment to Medway Crematorium on 19 April 2011. A small contract was awarded for this contractor to assist with the design works associated with the installation of cremators in an existing building. The intention is for this contractor to be novated across to the principal contractor once they were appointed.
2.2The Cabinet considered a further Gateway 3 Procurement Tender Process Review and Contract Award in respect of improvements to Medway Crematorium Stage 2 on 17 April 2012. That report dealt with the procurement of principal contractors to oversee the installation of cremators; build larger chapels and improve the car parking arrangements. This report was considered 2 months later than originally timetabled because the first set of tender submissions did not demonstrate the level of quality expected and so a second Invitation to Tender (ITT) was issued to contractors.
2.3Since the award of the second contract design work has progressed on this Design and Build project, but, on 23 May 2012, the contractor responsible for supplying and fitting the cremators advised that the aforementioned delays in securing a principal contractor had meant slippage in their programme and that they will not be able to supply all of the equipment by 31 December 2012 as originally timetabled.
2.4A revised programme has been provided that allows for the installation of 1 abated cremator by 31 December 2012, which means that the crematorium will still be able to comply with the target of 50% abatement by the end of December. The remaining cremators will then be installed with completion expected in March 2013.
2.5The 2 contractors have yet to formally agree to enter into a formal contractual arrangement but this will be possible as soon as the Council agrees to provide an extension.
Options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.